Ripley County, Indiana Building Permit Guide

To get a building permit in Ripley County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Ripley County’s Area Planning & Building office in the Annex at Versailles issues improvement location permits and building permits for the unincorporated county and six member towns; Batesville runs its own Building Commissioner.

Authority: Ripley County Area Planning & BuildingFees: Schedule of January 1, 2016Phone: 812-689-6068
Authority
Area Planning & Building102 W. First North St., Versailles
New house
$115 + $0.10/sq ftIncludes the $15 ILP fee
Permit trigger
144 sq ft or largerAny building or structure
Hours
Mon–Fri 8–4Building 812-689-6068

In Ripley County, the Area Planning & Building office in the county Annex at 102 W. First North Street, Versailles, issues the improvement location permit (ILP) and the building permit for the unincorporated county and the towns of Versailles, Osgood, Milan, Sunman, Holton and Napoleon. Any building or structure of 144 square feet or more needs a building permit, and a new house costs $115 plus $0.10 per square foot under the fee schedule in effect since January 1, 2016. Batesville is outside the Area Plan Commission and issues its own permits.

What requires a building permit in Ripley County?

The county’s Building Permit Requirements page sets one size rule: any building or structure of 144 square feet or larger needs a building permit, and no permit is issued without plans or structural drawings such as the truss sheet. Separately, Chapter 80 of the county code (the Area Zoning Code) requires an improvement location permit before any structure, improvement or use of land is placed, altered or erected anywhere in the Area Plan Commission’s territory, platted or not.

Permit needed

  • New houses, additions and alterations (charged on the single-family line of the fee schedule)
  • Manufactured, modular and single-wide homes
  • Accessory buildings and additions to them at 144 square feet or more
  • Above-ground and in-ground pools
  • Electrical service upgrades
  • Duplexes, commercial buildings, churches and schools
  • Signs, billboards and wireless towers

Other approvals that come with it

  • A driveway culvert permit from the county highway department for any construction that needs a driveway
  • A septic permit, or a letter from the town or sewer provider confirming water and sewer hookup
  • An 811 locate ticket number before the permit issues
  • Floodplain review where the parcel is in a flood zone
  • Town approval inside Sunman under its Ordinance 2025-07

The application form also asks whether any proposed building will house livestock and prints a 950-square-foot minimum living area on its first-floor line. Work begun under an ILP must start within six months of issue and be finished within twelve, unless the Executive Director extends the time for good cause.

What Ripley County decides and what the state holds

The county says it adopted the state building rules under IC 36-7-8-3 and IC 36-7-2-9 at the direction of the Indiana Department of Homeland Security, so the Building Commissioner inspects to the codes the state commission adopts. Zoning, setbacks, subdivision, the flood plain district and permit fees are local. For commercial and industrial buildings, Chapter 80 holds back the certificate of occupancy until the state has approved the plans, a review now handled through the Indiana Department of Homeland Security’s Construction Design Release.

Short on time to read all of this?

Get a free quote →

Ripley County building department: who handles permitting

The Area Plan Commission’s territory is the unincorporated county plus the six towns that adopted the Area Zoning Code with the commissioners: Versailles, Osgood, Milan, Sunman, Holton and Napoleon, each of which appoints a member to the commission. The Executive Director, Derek Walker, issues ILPs and serves as Flood Plain Administrator; under Section 80.39 an ILP can carry the building permit authorization of the county Building Inspector. Derick Welton is listed as Building Commissioner and Building Inspector. The code notes that the City of Batesville does not take part in the Area Plan Commission or the county zoning code.

Who issues permits in Ripley County
PlacePermit office
Unincorporated Ripley CountyRipley County Area Planning & Building, 102 W. First North St., Versailles; Area Planning 812-689-6062, Building Dept. 812-689-6068
Versailles, Osgood, Milan, Holton, NapoleonSame county office under the Area Zoning Code
SunmanCounty office, after prior approval from the town under Ordinance 2025-07
Batesville (city; only part of it lies in Ripley County)City Building Commissioner, 812-933-6103

The office is open Monday to Friday, 8 a.m. to 4 p.m. To confirm which side of a town line a parcel falls on, the Surveyor’s office keeps the county GIS map, which shows the parcel number used on every application.

Ripley County permit types

One county form, the Application for Improvement Location Permit, covers the zoning permit and the building permit together. It asks for the section, township and range from the deed, the tax parcel number, proof of ownership by recorded deed, the zoning district, the septic permit number or sewer letter, the 811 ticket, the driveway permit and a floodplain answer, then the size of each floor, garage and porch.

Residential permits

  • New houses and additions: a full printed set of construction plans with truss sheets must come with the application; the office says it cannot accept electronic copies.
  • Manufactured homes: the installer’s name and license number and the installation manual are required.
  • Accessory buildings: anything not attached to the house, with questions on concrete floor, electric, plumbing and insulation.
  • Engineered framing: the Firefighter Safety Notification form under IC 22-11-21 records whether the roof or floor uses engineered components.
  • Temporary uses and RVs: separate temporary-permit forms and a county notice on when an RV may be lived in.

Commercial permits

Commercial work is charged at $315 plus $0.15 per square foot, with flat fees for churches, schools, towers and signs. Class 1 buildings, which include any building where someone works as an employee, also need the state Construction Design Release, and the county will not issue a commercial or industrial certificate of occupancy until the state has approved the plans.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Driveway culvert permit. Issued at the county highway garage, 2710 N. Hasmer Hill Road, Osgood (812-689-4720); the highway crew sizes the culvert and either installs it or approves the owner’s installation, and only galvanized steel or double-wall plastic pipe is allowed. The permit runs six months, and the ILP form also accepts a driveway permit from the state highway department.
  • Street address. After the driveway permit issues, Area Planning assigns the street number; the septic permit cannot issue without it.
  • Septic or sewer. The Ripley County Health Department issues residential septic permits; inside a town, a letter from the town confirms water and sewer hookup.
  • Zoning relief. Variances, special exceptions, rezonings and plats go to the Board of Zoning Appeals or the Area Plan Commission, which meet monthly at 7:00 p.m.; the next listed dates are December 8, 2026, then January 5, 2027 (commission) and January 26, 2027 (board).
  • Flood plain. The flood plain district in Section 80.21 was replaced by Ordinance 2012-06, passed October 15, 2012, and the Executive Director administers it.

Ripley County permit costs and fees

The Planning & Building Department fee schedule has been in effect since January 1, 2016. Every permit fee in it already includes the $15 improvement location permit fee, payment is by check or cash only (exact change for cash), and fees are paid with the application and are not refundable.

Ripley County permit fees (schedule as of January 1, 2016)
WorkFee
Single-family dwelling: new, additions, alterations$115 + $0.10 per sq ft
Manufactured dwelling, single wide / manufactured or modular$115 / $215
Accessory building / addition to accessory building$115 / $90
Manufactured portable building$40
Electric upgrade$40
Pool, above ground / in ground$40 / $80
Duplex$500
Commercial$315 + $0.15 per sq ft
Churches and schools$365
Wireless tower / cabinet building$990 / $265
Sign on site / off site / billboard$80 per sign / $65 per sign / $765
BZA application or rezoning$250 each
Subdivision / high-density subdivision$125 + $25 per lot / $500 + $25 per lot
Unit development$300 + $5 per acre + $100 per phase

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the schedule: a new house with 1,800 square feet of covered floor area is $115 plus 1,800 × $0.10, or $295, which includes the ILP fee. The printed Chapter 80 still lists older figures (a $10 ILP fee, a $5 certificate of occupancy fee and a $50 late-filing fee for an ILP sought after a notice of violation); the 2016 schedule is the one the office posts as current. The $100 septic permit is paid separately to the Health Department.

Trade permits and who may pull them

Ripley County runs plumbing, electrical and mechanical work through the same application as the building: the form asks whether the job includes electric, plumbing and insulation, and an electrical service upgrade on its own has a $40 permit line.

  • Plumbing: the application requires the Indiana-licensed plumber’s name and license number before a permit issues, and the county’s form says a licensed plumber must do any plumbing in Ripley County under IC 25-28.5.
  • Electrical: the form records the electric provider (Southeastern Indiana REMC, Decatur County REMC or Duke); the county pages describe no separate electrician license or registration.
  • Manufactured homes: the installer must hold a license, and its number goes on the application.
  • Contractors: the application lists the contractor’s name and contact details; the county pages and forms show no general-contractor registration.

Septic systems must be installed by a Ripley County registered installer, who also draws the system design for the Health Department.

Rather not deal with the Ripley County building department?

Get a free quote →

How to apply for a Ripley County building permit

1. Check the parcel

Find the tax parcel number and township on the county GIS map and confirm the property is not in Batesville.

2. Get the driveway permit and address

Apply at the highway garage in Osgood; once it issues, Area Planning assigns the street number.

3. Arrange septic or sewer

Order a soil analysis and file the septic application with house plans, or get the town’s hookup letter.

4. Call 811

The locate ticket number goes on the application.

5. Complete the ILP application

Add the recorded deed, a site plan in ink on clean paper, printed plans with truss sheets and the plumber’s license number.

6. File and pay at the Annex

Bring it to 102 W. First North St., Versailles, and pay by check or cash.

7. Post the permit

Post the address and the permit on site before work starts.

Review, corrections and what causes delay

Section 80.39 builds in a five-day period between filing the site plan and issuing the ILP, which the office may waive. Applications without a tax parcel number, a recorded deed, a septic permit or sewer letter, the 811 ticket or printed plans are not issued. Owners must also affirm they have searched the recorder’s and surveyor’s records for easements and restrictive covenants, because the county says no permit is issued without that written statement and that a building over an easement may have to be removed.

Inspections and certificates in Ripley County

Every construction job is inspected, with at least 24 hours’ notice to the Building Department at 812-689-6068, and the application number is needed to book. The county lists these stages:

  • Footer or post hole, before the pour
  • Basement or crawl-space walls, before the pour
  • Under-floor plumbing, before the pour
  • Perimeter drain, before backfill (downspouts may not drain into it)
  • Framing and rough-in, then a second rough-in to confirm code compliance
  • Final, with gutters, handrails, the driveway culvert and the permanent 911 address in place under Ordinance 1991-3

The certificate of occupancy issues only after every inspection is passed. The county warns that a house without one may be denied the homestead exemption, because the certificate is presented to the Auditor’s office to claim it.

Indiana building code in Ripley County

FEMA’s Community Status Book lists unincorporated Ripley County (community 180221) as participating in the National Flood Insurance Program, with a current map dated November 2, 2012 that shows no base flood elevations; that listing covers only the unincorporated county. Flood plain permits in the Area Plan Commission’s territory come from the Executive Director under Ordinance 2012-06.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Ripley County building permit FAQs

Do I need a permit for a shed in Ripley County?

A shed or other structure of 144 square feet or more needs a building permit; an accessory building permit is $115, including the ILP fee.

How much is a building permit for a new house?

$115 plus $0.10 per square foot of covered area, so a 1,800-square-foot house is $295, payable by check or cash.

Does the county issue permits in Batesville?

No. Batesville is outside the Area Plan Commission and has its own Building Commissioner (812-933-6103).

Can I submit plans by email?

No. The ILP application says the office cannot accept electronic copies, so bring a printed set with truss sheets.

Can a homeowner do the plumbing?

The county application says any plumbing in Ripley County must be done by an Indiana-licensed plumber, whose name and license number go on the form.

How much is a septic permit?

$100, paid in person at the Health Department after a soil analysis and an installer’s design.

How do I book an inspection?

Call the Building Department at 812-689-6068 with your application number at least 24 hours ahead.

When do the Area Plan Commission and BZA meet?

Monthly at 7:00 p.m., with the BZA at 7:00 p.m. or right after the commission; the remaining 2026 date is December 8, and a variance or special exception application costs $250.

Ripley County permit search and official resources

The county posts no online permit search; permit, ILP and certificate records are kept by Area Planning & Building at the Annex, so ask there by phone or in person with the parcel number or application number. State Construction Design Release files for Class 1 projects can be looked up on IDHS’s project activity pages.

Inspections are where schedules slip.

Get a free quote →

Simplify Ripley County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Ripley County sooner?

Let Alliance prepare, file, and track your Ripley County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Ripley County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.