In Franklin County (Brookville), one office handles the whole permit path: the Area Plan Commission & Building Department issues building permits, runs zoning and carries out building inspections for all construction in the county except Batesville. It is in Room 107 of the Franklin County Government Center, 1010 Franklin Avenue, Brookville (765-647-5731). Every structure first needs a $30 location improvement permit, and every permit sits through a five-day review period before it can be issued.
What requires a building permit in Franklin County?
The department labels its location improvement permit as required for any structure, from a house to a pool or pole barn. A building permit follows on one of the department’s application forms: the accessory building application for accessory buildings, additions, pools, decks, porches, signs, remodels and miscellaneous work, the commercial application for commercial buildings and commercial additions, and a separate single-family dwelling application for new homes.
Accessory form covers
- Garages, with wall height, porch size and cost
- Pole barns, with post layout and truss design sheet
- Room additions, with a floor plan of the house and addition and smoke detector locations
- Decks, porches, signs, remodeling and in-ground or above-ground pools
Attachments that apply
- Health Department letter when bedrooms are added
- Plot plan with distances to all lines, building sizes and the septic location
- Written approval from any incorporated town or property owners’ association
- Notarized Notice of Agriculture Activity signed by the owner
What the zoning code lets you build without a permit
The county zoning code lists basic homeowner uses that need no permit: patios, walks, driveways, curbs, drainage installations, retaining walls, mailboxes, lamp posts, gardens, outdoor fireplaces and non-permanent structures such as storage sheds and small greenhouses. Fences, walls and structural screens are also allowed without a permit, subject to the fence rules in Section 80.05.10, and so are fall-out shelters. Swimming pools are allowed only with a permit. Decks, garages, carports, permanent storage buildings and similar home uses are allowed but must be built to the applicable building code.
The towns differ. Under Ordinance 14-2012, in Brookville, Oldenburg, Mount Carmel and Cedar Grove a permit from the town is required before installing driveways, patios, curbs, drainage devices, walks or retaining walls, or any shed, greenhouse or other structure over 150 square feet.
Plans for an accessory building must show a footer cross-section or post layout, header details and the truss design sheet unless the building is prefabricated. Under Section 80.34 of the zoning code an accessory building may never be used for living, sleeping or housekeeping.
Data center moratorium and draft rules
Data centers are on hold under a moratorium while a Data Center Work Group drafts zoning rules. Version 6.0 of the draft, dated September 23, 2026, would allow them only as a Class 3 conditional use in the I-1 Enclosed Industrial district, after a two-stage review by the Area Plan Commission and BZA, with 300-foot setbacks, a 75-foot height limit and applicant-funded independent reviews and escrow. The July 8, 2026 APC minutes show the draft still being revised before a public hearing; the county’s pages do not give the moratorium’s end date.
Short on time to read all of this?
Get a free quote →What the county decides and what the state holds
The county writes its zoning code, The Franklin County Citizens Zoning and Subdivision Control Code, which divides its jurisdiction into 15 districts from A-1 Prime Agriculture to the industrial districts, sets its permit fees and inspects construction. A certificate of occupancy is issued once the work complies with Chapter 90, the building code chapter of the county’s Code of Ordinances, and any participating town’s requirements. For commercial work it wants the state’s side on file: the commercial application asks for a copy of the plans as submitted to the State of Indiana and a copy of the Construction Design Release.
Franklin County building department: who handles permitting
The Franklin County Area Plan Commission & Building Department issues building permits, administers zoning and conducts building inspections for all construction in the county except the City of Batesville. It also takes petitions to the Area Plan Commission and the Board of Zoning Appeals for variances, conditional uses, rezonings and subdivisions. Jerry Barnhart is the Chief Building Inspector. The commission’s October 28, 2026 special meeting agenda listed the appointment of a new Area Planning Director.
| Item | Detail |
|---|---|
| Office | Franklin County Government Center, 1010 Franklin Avenue, Room 107, Brookville, IN 47012 |
| Phone | 765-647-5731 |
| Chief Building Inspector | Jerry Barnhart |
| APC and BZA meetings | Government Center Room 203, second floor; the BZA meets right after the APC; meetings can also be joined by Zoom |
| Related county offices | Health Department, Room 210 (765-647-4322); Surveyor (765-647-5651); Soil & Water (765-647-2651); Commissioners (765-647-4985) |
| Place | Building permits |
|---|---|
| Batesville (city, 2,007 residents in Franklin County) | Not the county: the department excludes Batesville, and only part of the city lies in Franklin County |
| Brookville (town, 2,663) | County department, with the town’s written approval attached |
| Oldenburg (651), Laurel (414), Cedar Grove (148), Mount Carmel (90) | County department, with the town’s written approval attached |
The zoning code allows an incorporated town to add zoning requirements of its own by town ordinance, and leaves enforcement of any such extra rules to the town (Ordinance 14-2012). Use the Franklin County GIS map, linked from the department’s page, to find the parcel number, zone and township the location permit asks for.
Not sure this scope needs a permit?
Get a free quote →Franklin County permit types
The department’s forms are posted on its Planning, Zoning & Building page. Each job starts with the one-page location improvement permit: owner and contractor, structure type, site address, parcel number (Franklin County parcels begin with 24-), zone, floodplain yes or no, township, acreage and the four setbacks.
Residential permits
Accessory buildings, additions, pools, decks and similar work use the Franklin County Building Permit Application for accessory use, addition, pool and miscellaneous work, which asks for the owner, builder, township, section, range, acreage and subdivision, and whether the building will have electric, plumbing or a new meter. Homes in Lakeshore Resort or New Fairfield, or sites in campgrounds such as Hickory Woods or Twin Forks, need the association’s written approval. If an addition adds bedrooms on a septic system, bring a Health Department letter stating that the septic is adequate.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
The commercial application covers commercial buildings and additions. Its checklist: a copy of the building plans as submitted to the state (11 by 17 inches or larger), a copy of the Construction Design Release, a new driveway permit from the County Highway Department or INDOT, a septic permit or a letter of availability from the sewer provider, a plot plan, approval from any incorporated town or owners’ association, a notarized Notice of Agriculture Activity, an IDEM Rule 5 stormwater approval through Franklin County Soil & Water if 1 acre or more is disturbed, and compliance with the Franklin County Development & Construction Standards.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning petitions. Variances, conditional uses, rezonings, subdivisions and appeals are filed with the department for the APC or BZA.
- Septic. The Franklin County Health Department, Government Center Room 210 (765-647-4322).
- Driveways. Franklin County Highway Department, 1360 Fairfield Avenue, Brookville (765-647-4271), or INDOT on a state highway.
- Construction standards. The Commissioners (765-647-4985) or the County Surveyor (765-647-5651).
- Floodplain. The location permit asks whether the site is in the floodplain, and the zoning code sets the floodplain administrator’s review.
Franklin County permit costs and fees
The department posts its permit fees on its Planning, Zoning & Building page as a building inspection fee for each type of construction plus the $30 location improvement permit; the page gives no adopting ordinance or date, so confirm the figure at 765-647-5731 when you file. The zoning code’s own filing fee section (Section 80.11.05) also sets the $30 location permit and $20 for each certificate of occupancy application.
Rather talk it over?
Call 1-855-478-4290 →| Work | Building inspection fee |
|---|---|
| Single-family dwelling, including modulars | $300 plus $5 per 100 sq ft if over 960 sq ft |
| Manufactured home (double-wide, etc.) | $250, plus $100 if a basement is present |
| Two-family dwelling | $500 plus $5 per 100 sq ft |
| Multi-family dwellings | $600 plus $5 per sq ft (as posted) |
| Residential addition | $200 plus $5 per 100 sq ft |
| Accessory building | $75, plus $25 for electric and $25 for plumbing |
| Attached and unenclosed lean-tos and decks | $50 flat |
| In-ground pool / above-ground pool | $200 flat / $75 flat |
| Commercial buildings, additions and remodels | $500 up to 10,000 sq ft, plus $5 per 100 sq ft over 10,000 sq ft (the page adds that it “becomes $1,000 plus $5 per sq ft”); cannot exceed $6,500 |
| Churches or non-profit organizations | $250 flat |
| Temporary structures | $50, plus $25 for electric |
| Re-inspection / meter check / sign | $45 / $45 / $50 flat |
| Location improvement permit (every structure above) | $30 |
Petition fees on the same page: change of use $50, change of zone $300, conditional use $300, variance $300, and subdivisions $300 plus $20 per lot up to 20 lots and $10 per lot over 20. The zoning code (as amended by Ordinance 2016-8, passed May 23, 2016) lists a lower $150 for a Class 2 conditional use and no per-lot subdivision charge, so ask which figure applies. Petitioners also pay for the newspaper notice and the notices to interested parties.
Worked example: a 400-square-foot residential addition costs $200 plus 4 × $5 ($20), or $220, plus the $30 location permit, for $250. Septic or sewer letters, driveway permits, Rule 5 stormwater approval and the state’s Construction Design Release are charged by the offices that issue them.
Rather not deal with the Franklin County building department?
Get a free quote →Trade permits and who may pull them
Franklin County does not post separate electrical, plumbing or mechanical permit forms. The building applications ask whether the building will have electric, plumbing or a new meter, and the Building Department’s inspectors inspect the construction. The forms name a builder but ask for no local contractor license or registration number.
- Plumbing: Indiana licenses plumbing contractors; the county’s forms add no local plumbing license.
- Electrical and HVAC: no county license or registration appears on the county’s pages or forms.
- Owner-builders: the forms allow the owner to be the builder (“same as owner or builder”), and the owner or contractor signs.
How to apply for a Franklin County building permit
Use the county GIS map for the parcel number, zone, township and floodplain status, and confirm the site is not in Batesville.
Septic permit or Health Department letter, driveway permit, town or association approval and, for commercial work, the state design release.
The owner signs the Notice of Agriculture Activity before a notary.
The $30 location improvement permit plus the accessory, single-family or commercial building application, with plans and a plot plan.
Bring the package to the Government Center at 1010 Franklin Avenue, Brookville.
All permits are subject to a five-day waiting period.
Review, corrections and what causes delay
The zoning code sets a matching rule: a site plan or development plan must be furnished at least five days before the improvement location permit is issued, though the code lets that period be waived. The site plan must be drawn to scale with a legal or site description and acreage, all buildings and septic sites, the width and length of every entrance and the adjoining roads. Enlarging a non-conforming use in the floodplain district is sent to the Department of Natural Resources first, and its conditions are written into the permit.
The accessory application warns that everything on it must be in order before a building permit is issued. Items that depend on someone else, such as a town or owners’ association letter, a septic letter for added bedrooms or a driveway permit, have to be in hand along with the truss design sheet. Commercial projects that disturb an acre or more also wait on the Rule 5 stormwater process.
Inspections in Franklin County
The department conducts building inspections for all construction in its area, led by the Chief Building Inspector; call 765-647-5731 to arrange them. The plans it requires show what it will look at: footers or post layout, headers, trusses and, for additions, the smoke detector locations. Inside the floodplain, the zoning code has the floodplain administrator inspect projects and keep as-built elevation and floodproofing records.
Want this handled start to finish?
Get a free quote →Complaints about construction or zoning use the department’s complaint application.
Indiana building code in Franklin County
FEMA’s Community Status Book lists unincorporated Franklin County (community 180068) as participating in the National Flood Insurance Program, with flood maps effective January 16, 2014. Brookville Lake and its surroundings fall in the R-E Recreation district of the county zoning code.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Franklin County permit search and official resources
The county has no online permit search; ask the department in Room 107 for permit and inspection records. APC and BZA agendas and minutes from 2023 to 2026, data center work group papers and the meeting schedule are posted on the department’s page, and meetings are livestreamed and archived on the county’s YouTube channel.
- Franklin County Planning, Zoning & Building
- Location improvement permit ($30)
- Accessory building, addition and pool application
- Commercial building permit application
- Variance application
- Franklin County Citizens Zoning and Subdivision Control Code
- Data center regulations, executive summary (v6.0)
- APC minutes, July 8, 2026
- Franklin County Health Department
- Franklin County Highway Department
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Franklin County building permit FAQs
Who issues building permits in Franklin County?
The Area Plan Commission & Building Department in Brookville, for all construction in the county except the City of Batesville.
Does a pole barn need a permit?
Yes. It needs the $30 location improvement permit and an accessory building permit ($75, plus $25 each for electric and plumbing) with a post layout, header detail and truss design sheet.
How long does a permit take?
Every permit is subject to a five-day review period once the application is complete.
I live in Brookville or Oldenburg. Who handles my permit?
The county department, but you must attach the town’s written approval.
Do I need a permit for a fence or a small shed?
The county zoning code allows fences and non-permanent storage sheds without a permit, but Brookville, Oldenburg, Mount Carmel and Cedar Grove require a town permit for any shed or structure over 150 square feet.
Can I live in my garage or pole barn?
No. Section 80.34 of the zoning code bars any accessory use for living, sleeping or housekeeping.
Is a data center allowed?
Not while the moratorium lasts; draft rules would allow data centers only as a conditional use in the I-1 district.
What does the location permit cost?
$30 for every structure. The building inspection fee is on top: for example $75 for an accessory building, plus $25 each for electric and plumbing.
Simplify Franklin County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Franklin County sooner?
Let Alliance prepare, file, and track your Franklin County permits while your crew stays on the job.
More Indiana permitting guides
Fayette County
Read guide →Ripley County
Read guide →Dearborn County
Read guide →Fulton County Building Permit Guide
Read guide →Gary Building Permit Guide
Read guide →Gibson County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Franklin County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.