In Owen County, building permits come from the Owen County Building and Planning Department, 86 E Market Street, Spencer (812-829-5033), headed by Planning Director and Building Administrator Eddie Honea. It issues residential and commercial building permits, electrical and demolition permits, reviews plans, inspects, and runs zoning for the Plan Commission and BZA. The Town of Spencer issues its own permits at its municipal building. Fees rose under Ordinance 2026-08: since August 11, 2026 a new house costs $400 plus $0.20 for each square foot over 650, payable only in cash or by check in the exact amount.
What requires a building permit in Owen County?
The county’s notice to permit applicants sets the test by system, not by project: a permit is needed before any construction, alteration or repair that involves or affects the electrical, plumbing, ventilating, heating or air-conditioning systems or the structure. The fee schedule and forms name the common projects.
Permit required
- New one- and two-family dwellings and manufactured homes
- Additions and alterations to homes, and unfinished porches and decks
- Garages, barns and pole barns
- Swimming pools holding more than 10,000 gallons
- New electrical services and service upgrades, including outbuildings and campers
- Commercial and industrial (Class 1) buildings, additions and alterations
- Demolition and wireless communication facilities
No building permit
- Cosmetic repairs and maintenance such as floor coverings, painting and roofing
- Repair or maintenance of a private home done by the person living in it
- A home an owner builds to live in, where the department grants an exemption (the electrical permit is still needed)
Before a permit can be issued for a site in an identified floodplain, the application says the Indiana Department of Natural Resources must be contacted. Owners who start without a permit face the county’s violation fines, which begin at $300 for a first offense.
What Owen County decides and what the state holds
Owen County’s building code is its Ordinance 1992-10, and one- and two-family dwellings are solely under the county Building Administrator’s jurisdiction. The county sets its own fees, fines, setbacks and zoning (Chapter 155 of the County Code, zoning and subdivision control). Commercial work is different: no county permit for a commercial building is issued until a copy of the state release for construction has been received. A one-year moratorium adopted on September 22, 2026 (Ordinance 2026-011) pauses new data center development, including rezonings for future data centers, while the Plan Commission drafts permanent rules.
Short on time to read all of this?
Get a free quote →Owen County building department: who handles permitting
The Building and Planning Department handles building permits for homes and commercial buildings, electrical and demolition permits, plan checks, inspections, code enforcement, zoning guidance and enforcement, and Plan Commission and BZA business. The department asks applicants to call before sending any payment. In October 2026 the Commissioners discussed delays in processing Plan Commission and BZA applications while the Building Administrator post was vacant and the Building Inspector carried permits and inspections; the department page now lists Eddie Honea in that post.
| Office | Details |
|---|---|
| Building and Planning Department | 86 E Market Street, Spencer, IN 47460; 812-829-5033 |
| Health Department (septic) | 751 E. Franklin Street, Spencer; 812-829-5017; weekdays 8 a.m. to noon and 1 to 4 p.m. |
| Highway Department (driveways, right of way) | 812-829-3335; highway.department@owencounty.in.gov; weekdays 8 a.m. to 4 p.m. |
| Surveyor | 60 S. Main Street, Spencer; 812-821-6908 |
| Courthouse (Auditor, addressing) | 60 S. Main Street, Spencer; 812-829-5000 |
Spencer and Gosport
Owen County has two towns. The Town of Spencer handles its own building permits: its forms page sends applicants to the municipal building at 90 N. West Street (812-829-3213) and points to Chapter 150, Building Regulations, of its town code. For Gosport, the published sources do not say who issues building permits; the town’s posted ordinances cover water rates, mobile homes, sewer lids and parking, so ask Town Hall at 812-879-4334 before relying on the county permit. Everywhere else in the county, the county department issues permits.
Owen County permit types
The county uses separate forms for Class II structures (homes and their outbuildings), Class 1 structures (commercial), electrical work, demolition and pools, plus an exemption application for owner-builders. Each permit runs for one year from issue; if the work is not finished, the applicant re-applies by paying a renewal fee.
Residential permits
- Class II Structures Permit: the form asks for the township, section, parcel, zone and subdivision, whether the site is in a floodplain, the contractor, and square footage broken down by floor, finished and unfinished basement, roofed deck, garage, pole barn and carport, plus the construction cost. It prints the county setbacks: 75 feet from a county road and 25 feet from property lines.
- Electrical permit: for a new service or an upgrade from 100 to 200 or 200 to 400 amps, on dwellings, outbuildings or a camper; the owner affirms the work will not affect the septic system, and the county inspector must approve it before the utility energizes the service.
- Owner-builder exemption: an owner building a home to live in may apply, under IC 36-7-8-3(d), to be exempted from the county building code, signing a waiver and hold-harmless; the electrical permit still applies and the septic system must pass the Health Department’s inspection before anyone moves in.
- Pools over 10,000 gallons need the swimming pool permit, which also asks whether a deck is attached.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
The Class 1 Structures Permit Application asks for the architect or engineer and their license, the contractor, the project type (new building, alteration, addition or repair), use, location, square footage and estimated cost. The county issues it only after receiving a copy of the state release for construction. Wireless communication facilities have their own $1,000 permit.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The department checks the lot against Chapter 155; rezonings and subdivisions go to the Plan Commission, which posted 2026 meetings on third Tuesdays, and variances and conditional uses to the BZA, whose 2026 meetings fell on second Thursdays.
- Septic. A new house needs a Health Department septic permit ($75), with a soil analysis by a state-registered soil scientist; repairs and modifications need their own permit.
- Driveway. Any new access to a county-maintained road needs a Highway Department driveway permit; state highways are INDOT’s.
- Floodplain. Sites in an identified floodplain must contact the Indiana Department of Natural Resources before the permit can issue.
Owen County permit costs and fees
Fees come from Ordinance 2026-08, which amended the county building permit fee schedule on its third and final reading at the Commissioners’ meeting of June 4, 2026; the schedule took effect on August 11, 2026. The minutes record the reasons as alignment with surrounding counties and the department’s finances. The county takes cash or check only, in the exact amount, and works out the fee once the application is in.
| Work | Fee |
|---|---|
| One- or two-family dwelling (Class II) | $400 plus $0.20 per sq ft over 650 sq ft |
| Additions and alterations to a Class II structure | $200 plus $0.20 per sq ft over 500 sq ft |
| Unfinished porches and decks | $0.10 per sq ft |
| Garage, barn or swimming pool over 200 sq ft | $200 plus $0.10 per sq ft |
| Garage, barn or swimming pool under 200 sq ft | $200 |
| Class I (commercial) structure | $1,000 plus $0.20 per sq ft over 2,000 sq ft |
| Class I additions or alterations | $700 plus $0.25 per sq ft over 1,250 sq ft |
| Electrical, residential / commercial | $100 / $150 |
| Demolition | $100 |
| Re-inspection | $50 |
| Renewal: one-year / six-month extension | 80% / 50% of the original fee |
| Wireless communication facility | $1,000 |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a 1,850-square-foot house is $400 plus (1,850 − 650) × $0.20 = $240, or $640, and a separate residential electrical permit adds $100. A 1,000-square-foot addition is $200 plus 500 × $0.20 = $100, or $300. The older notice to applicants still quotes a $25 re-inspection fee; the 2026 schedule sets $50. Under the violation fines in Section 151.999 (as of January 30, 2024), building without a permit costs $300, then $500 and $1,000 for repeat offenses; working on after a stop order costs $2,500, $5,000 and $10,000; and work not ready for a scheduled inspection costs $50 the first time.
Trade permits and who may pull them
Owen County issues its own electrical permits under Ordinance 2023-014, and electrical changes must be inspected and approved by the county Building Inspector before the property gets power. Plumbing, heating and ventilating work are covered by the building permit, since the notice makes any work that affects those systems permit work. Septic work belongs to the Health Department.
- Owners: repairs and maintenance on a private home done by the occupant need no permit, and an owner building a home to live in may seek the exemption, but the electrical permit is not covered by it.
- Plumbing contractors need the state plumbing contractor license; the county’s pages show no separate local plumbing license.
- Builders: the Class 1, Class II and pool forms ask for the contractor’s details and, on the commercial and pool forms, a builder license number; the county’s pages describe no local contractor registration program, so ask the department before relying on one.
- Demolition needs utilities properly cut off first, approval from the township fire department if the building will be burned, and qualified contractors for large unsafe structures.
Rather not deal with the Owen County building department?
Get a free quote →How to apply for an Owen County building permit
Parcels in the Town of Spencer go to the town; check Gosport with its Town Hall; the rest of the county comes to 86 E Market Street.
Apply for the $75 septic permit with a soil analysis, and for a driveway permit on a county road.
Show the whole property, lot dimensions, every improvement and labeled setbacks to property lines, septic and other buildings.
Class II for a home or outbuilding, Class 1 for commercial, plus the electrical application for new or upgraded service.
Call before sending payment; the fee is set once the application is reviewed and is paid in cash or by check for the exact amount.
It expires after one year; extensions cost 80% or 50% of the original fee.
Review, corrections and what causes delay
Missing septic approval, a site plan without setbacks, a floodplain lot that has not been cleared with the Department of Natural Resources, or a commercial job without its state release will stop a permit. Zoning cases wait for the monthly Plan Commission or BZA meeting; several 2026 months had no meeting, and the October 2026 minutes record a backlog of applications during the administrator vacancy. Since January 1, 2026 state law has required a unit that permits one- and two-family work to review the plans within 7 business days.
Inspections and certificates in Owen County
The permit holder, contractor, owner or lessee must tell the department when the work reaches each stage the Building Inspector has set. The department then has at least 48 hours, not counting Saturdays, Sundays and holidays, to carry out the inspection, so call ahead of the day you need it. The schedule of inspections is available from the department’s office, and the inspector may add inspections where needed.
At the final inspection the Building Inspector issues an occupancy certificate, and using the building before it is issued can bring a stop-work order, an injunction or a claim for damages by the county. Occupying a dwelling without final approval also carries a fine of $250, rising to $1,000 for a third offense, and the same applies to using a pool before its final. On a new or upgraded service, the property receives power only after the county inspector has approved the electrical work.
Indiana building code in Owen County
Owen County’s building ordinance and its Chapter 155 zoning and subdivision rules are published on American Legal Publishing. FEMA’s Community Status Book lists unincorporated Owen County (community 180481) as taking part in the National Flood Insurance Program, with flood maps effective March 3, 2014.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Owen County permit search and official resources
Request permit, inspection or zoning records under Indiana’s Access to Public Records Act through the county’s online public records form, choosing “Building and Planning” as the department, or by mail, in person or by phone; keep each request to one property or project. Plan Commission and BZA agendas and minutes, and the Commissioners’ minutes, are posted on the county website.
- Owen County Building and Planning Department
- Building permit fees effective August 11, 2026
- Commissioners’ minutes, June 4, 2026 (Ordinance 2026-08)
- Before applying for building permits
- Class II structures permit application
- Electrical permit application
- Class 1 structures permit application
- Application for exemption from building permit
- Building violation fines
- Commissioners’ minutes, September 22, 2026 (data center moratorium)
- Health Department septic permits
- Owen County Highway Department
- Public records request
- Town of Spencer building permits
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Owen County building permit FAQs
How much is a building permit for a new house in Owen County?
$400 plus $0.20 for each square foot over 650, so an 1,850-square-foot house is $640 before the $100 electrical permit.
Can I build my own house without a county permit?
An owner building a home to live in can apply for an exemption from the county building code, but still needs the electrical permit and a Health Department septic inspection before moving in.
Do I need a permit for a new roof?
No. Roofing, painting and floor coverings count as cosmetic repairs and maintenance, for which the county requires no permit.
How do I pay?
Cash or check only, in the exact amount; call the department before sending a payment.
Does the county issue permits in Spencer?
No. The Town of Spencer handles building permits at its municipal building, 90 N. West Street.
How much notice does an inspection need?
The department has at least 48 hours, excluding weekends and holidays, after a request to complete an inspection.
Can a data center be built in Owen County now?
Not while the one-year moratorium adopted on September 22, 2026 (Ordinance 2026-011) is in force.
Simplify Owen County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Owen County sooner?
Let Alliance prepare, file, and track your Owen County permits while your crew stays on the job.
More Indiana permitting guides
Clay County
Read guide →Monroe County
Read guide →Putnam County
Read guide →Parke County Building Permit Guide
Read guide →Peru Building Permit Guide
Read guide →Pike County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Owen County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.