Building in Parke County starts at the Parke County Planning and Zoning Office, the Plan Commission’s office on the first floor of the courthouse, 116 W. High St., Room 105, Rockville (765-569-3394, planning@parkecounty.in.gov). It issues the improvement location permit, which the county calls a building improvement permit, for every structural building improvement: $50 for a house, garage or farm building and $100 for a commercial or industrial building under Ordinance 2009-10, and ten times that if work starts before the permit. A complete application is usually issued the same day.
What requires a building permit in Parke County?
The county’s rule is short: all structural building improvements need a building improvement permit, the improvement location permit (ILP) issued by the Plan Commission’s office. The permit application lists what it is used for.
Improvement location permit
- Single-family houses and modular homes
- Single-wide and double-wide mobile homes
- Room additions and other residential accessory buildings
- Attached and detached garages
- Commercial, industrial and public buildings and their accessory buildings
- Farm buildings and grain bins, permitted as a “courtesy” farm accessory permit
- Wells, which need a separate $50 well permit
Other county approvals
- Septic installation or repair: a Health Department permit
- Driveway onto a state or federal highway: a state release
- Cell towers: the county’s cell tower placement procedure
- Data centers: a petition to the Planning and Zoning Commission under Ordinance 2026-11
- Occupancy: a certificate of occupancy ($10)
The county’s pages do not publish a list of work that is exempt, so ask the office before assuming a project needs no permit. Starting first is costly: under Ordinance 2009-10 an ILP applied for after construction has begun costs ten times the normal fee.
What Parke County decides and what the state holds
The county’s permit is a land-use permit under its zoning ordinance, which covers the unincorporated county and any town that has agreed to join it. That ordinance makes the Plan Commission’s administrator the Building Commissioner, who also acts as county building inspector until the Commissioners set up a separate office, and requires a certificate of occupancy before a new improvement is used. The county sets its own fees, setbacks and land rules, such as a half-acre minimum for a house on AP (agriculture productive) or AFR (agriculture forest recreation) land where the soil suits a septic system. Class 1 buildings also need the state design release.
Short on time to read all of this?
Get a free quote →Parke County building department: who handles permitting
The Planning and Zoning Office serves the Parke County Plan Commission and the Board of Zoning Appeals, and its well permits are signed by the Plan Commission administrator, Beth Martin. The office is open Monday to Thursday from 8 a.m. to 4 p.m., closed 12:30 to 1:30 for lunch; Friday is a remote day, when staff answer by email or cell phone. When the office has to close unexpectedly, permit applications and stamped return envelopes are left in the slots outside its door.
| Office | Details |
|---|---|
| Planning and Zoning Office (Plan Commission) | Courthouse, 116 W. High St., Room 105, Rockville, IN 47872; 765-569-3394; planning@parkecounty.in.gov |
| Health Department (septic) | Courthouse basement, Room 12; office 765-569-6665; sanitarian 765-569-4071, usually 8 a.m. to 3 p.m. |
| Highway Department | 306 N. Lincoln Road, Rockville; 765-569-5321 |
| County Surveyor (regulated drains) | 765-569-4063 |
Towns in Parke County
Parke County has six towns: Rockville, Montezuma, Rosedale, Bloomingdale, Marshall and Mecca. Montezuma’s town code names the Parke County Plan Commission as the town’s own plan commission, so planning and subdivision approvals there go through the county office, while the town issues its own building permits through the Clerk-Treasurer after a call to the town’s building inspector (utility office, 1243 North Jackson Street, 765-245-2759). The town’s fee schedule charges $25 for a new single-family house and $50 for new commercial construction, a town permit is void unless work starts within 120 days, and the town may waive permits for accessory buildings up to 144 square feet not meant for living in and for non-structural work costing $500 or less. For Rockville, Rosedale, Bloomingdale, Marshall and Mecca, the published sources do not say whether the town permits or has joined the county ordinance; ask the town office first (Rockville’s Clerk-Treasurer is at 765-569-6253) and then the county office.
Parke County permit types
One two-page application covers every type. The front asks for the township and map key number, the owner and the contractor or builder, the type of building, the approximate construction cost, the electric supplier, the zoning classification, any subdivision and lot number, the septic and well permit numbers, whether the site is in a floodplain, and whether any covenant or restriction bars the use. Mobile homes add the maker, year, bedrooms, bathrooms, foundation and skirting. The same form can be filed online through the county’s AccessGov page and paid by credit card.
Not sure this scope needs a permit?
Get a free quote →Residential permits
- Houses and mobile homes need a floor plan, since every building meant to be lived in must show one, and proof of an E911 address for a new residence.
- Garages and accessory buildings must sit behind the front line of the house and at least 8 feet from side lines unless a special exception allows otherwise.
- Accessory first: a garage or barn can go on a residential lot before the house only if the house permit is taken out at the same time with plans, and the house reaches 30% completion within the first year; the house then has up to three years to be finished, and if it is not 30% complete at the end of the first year the accessory building must be removed.
- Subdivision lots need the subdivision board’s signature where its covenants require it; covenants can be stricter than county rules but not looser.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial, industrial and public buildings and their accessory buildings take the $100 permit. Data centers are tightly limited by Ordinance 2026-11, adopted on June 15, 2026: one that depends on the local electric grid beyond ordinary office needs is prohibited, cooling water may not come from wells, town water, lakes or streams (only water trucked in and kept in a closed, non-evaporating loop), and every project must petition the Planning and Zoning Commission, with fines of $2,500 a day per parcel. Cell towers follow the county’s placement procedure, and Class 1 buildings need the state design release.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Septic release number. The first step on the county’s list: the Health Department in the courthouse basement permits every new septic system and every repair.
- Well permit. $50 from the Planning and Zoning Office, naming the well driller.
- Site plan. It must show the new improvement, every other building, the well and septic system with distances between them and to buildings, utility easements and the driveway.
- Legal description. A copy of the warranty deed or recorded contract.
- Driveway. A state release for an entrance onto a state or federal highway; the Highway Department maintains about 450 miles of paved county roads.
- Zoning relief. Variances, special exceptions and appeals go to the Board of Zoning Appeals, and rezonings to the Plan Commission and Commissioners.
Parke County permit costs and fees
Permit fees are set by Ordinance 2009-10, which amended the filing fee section of the zoning ordinance and was passed by the Commissioners on August 17, 2009; the Planning and Zoning page and the application still list the same $50 and $100 figures. Fees are paid by check or money order to the Parke County Planning Commission, or by card online, and none is refundable.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| ILP for a house, manufactured home, accessory or agricultural building | $50 |
| ILP for a commercial, industrial or public building or accessory building | $100 |
| ILP applied for after construction has begun | Ten times the fee: $500 residential, $1,000 commercial |
| Certificate of occupancy / temporary certificate | $10 / $10 (ten times if applied for after occupancy) |
| Well permit | $50 |
| Variance | $100 |
| Special exception or contingent use | $25 |
| Appeal of an administrative decision to the BZA | No fee |
| Rezoning or other ordinance amendment, or plat amendment | $50 |
Worked example from Ordinance 2009-10: a new house on a lot that needs a new well takes a $50 ILP, a $50 well permit and a $10 certificate of occupancy, or $110 at the county office, plus the Health Department’s septic permit. Applied for after construction began, the same ILP would be $500.
Trade permits and who may pull them
The county’s published forms cover land use, wells and occupancy; they include no separate electrical, plumbing or HVAC permit, and the application asks only which utility supplies the power (REMC, the Town of Rockville or PSI, as the form lists them). Ask the Planning and Zoning Office whether any trade inspection applies to a project before relying on that.
- Builders and contractors: the application asks for the contractor or builder’s name, address and phone; the county’s pages describe no local contractor license or registration.
- Plumbing on a new house is still regulated by the state, which licenses plumbing contractors.
- Septic installers and repairs work under a Health Department permit; the department takes card payments by phone.
- Well drillers are named on the county well permit.
- Signatures: owners, contractors and any subdivision board must all sign before the permit issues.
Rather not deal with the Parke County building department?
Get a free quote →How to apply for a Parke County permit
Check that the parcel is in the unincorporated county or a town that uses the county ordinance; Montezuma issues its own building permits.
Obtain the septic release number from the Health Department, and a well permit if a new well is needed.
Show the improvement, all buildings, well, septic, easements, driveway and the distances between them.
Floor plan for any building to be lived in, a copy of the deed or recorded contract, signatures, and the E911 address for a new home.
Bring everything to Room 105, mail it with a check, or file online through AccessGov and pay by card.
Post it where it can be seen, and apply for the certificate of occupancy before moving in.
Review, corrections and what causes delay
Permits are issued the same day when every requested item is supplied, first come, first served; without the requested information the permit is not issued. Before going, check that you have the septic release number, a site plan with the well and septic distances, and a recorded deed or contract. Zoning relief takes longer because it needs a BZA hearing. Since January 1, 2026 state law gives a unit that permits one- and two-family work 7 business days to review plans.
Inspections and certificates in Parke County
The county’s pages and forms publish no schedule of construction inspections. What they do require is a certificate of occupancy: the zoning ordinance bars using a new improvement until the certificate is issued, and Ordinance 2009-10 charges $10 for it, or ten times that if it is applied for after the building is already occupied. A temporary certificate is also $10. The Health Department inspects septic systems it permits.
Flood-prone land carries its own rules in the zoning ordinance’s flood hazard district, which the Plan Commission and BZA administer with the County Surveyor. New flood maps for unincorporated Parke County took effect on July 7, 2026, so check the current map before answering the floodplain question on the application.
Indiana building code in Parke County
Parke County’s permit rules sit in its zoning ordinance, posted as the 1976 amendment, and in later amendments such as the 2009 fee ordinance. FEMA’s Community Status Book lists unincorporated Parke County (community 180192B) as taking part in the National Flood Insurance Program, with its current flood maps effective July 7, 2026.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Parke County permit search and official resources
For a past permit, certificate of occupancy or zoning decision, ask the Planning and Zoning Office at 765-569-3394 or planning@parkecounty.in.gov; septic permits are the Health Department’s. The Auditor keeps a public document center linked from the county site.
- Parke County Planning and Zoning
- Improvement location permit application (updated June 20, 2024)
- Online building permit application (AccessGov)
- Fee schedule, Ordinance 2009-10
- Parke County Zoning Ordinance
- Well permit application
- Data Center Ordinance 2026-11
- Parke County Health Department
- Parke County Highway Department
- Parke County Surveyor
- Town of Montezuma Municipal Code
- Town of Rockville
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Parke County building permit FAQs
How much is a building permit in Parke County?
$50 for a house, garage, mobile home or farm building and $100 for a commercial, industrial or public building, plus $10 for the certificate of occupancy.
What happens if I build before getting the permit?
The permit then costs ten times the normal fee: $500 for residential work and $1,000 for commercial.
Can I apply online?
Yes, through the county’s AccessGov form with a credit card, or on paper at Room 105 of the courthouse.
How fast is a permit issued?
The same day, if every requested item is supplied.
Can I put up a garage before the house?
Only if you apply for the house permit at the same time with plans and reach 30% completion of the house within the first year.
Does the county permit in Montezuma?
The county Plan Commission acts as Montezuma’s plan commission, but building permits there come from the town through its Clerk-Treasurer.
Are data centers allowed in Parke County?
Only under Ordinance 2026-11: they must be independent of the local grid and local water for cooling, and must go through the Planning and Zoning Commission.
Simplify Parke County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Parke County sooner?
Let Alliance prepare, file, and track your Parke County permits while your crew stays on the job.
More Indiana permitting guides
Vermillion County
Read guide →Putnam County
Read guide →Fountain County
Read guide →Peru Building Permit Guide
Read guide →Pike County Building Permit Guide
Read guide →Plymouth Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Parke County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.