Jackson County, Indiana Building Permit Guide

To get a building permit in Jackson County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Jackson County Planning & Zoning in Brownstown issues one combined building permit, covering framing, electrical and plumbing, for new homes and additions in unincorporated Jackson County and inspects the work itself.

Authority: Jackson County Planning & ZoningBuilding code: Ordinance No. 6 (2018)Phone: (812) 358-6109
Permit office
Planning & Zoning111 S Main St, Suite 211, Brownstown
New home fee
$0.08 per sq ftCounty building commission schedule
Processing
Up to 10 working daysAfter a full submittal
Not covered
Seymour + 2-mile fringeAnd the three towns

In unincorporated Jackson County, the Jackson County Planning & Zoning office at the Brownstown courthouse, 111 South Main Street, Suite 211 ((812) 358-6109), issues building permits and carries out residential inspections under the county building code adopted in 2018. A single permit covers the building, electrical and plumbing work on a new home or addition, priced at $0.08 per square foot for new residential construction. Seymour and its two-mile fringe, Brownstown, Crothersville and Medora handle their own permits.

What requires a building permit in Jackson County?

Ordinance No. 6 (Commissioners Bill No. 5), the Building Code of Jackson County, is short and broad: construction is prohibited unless it follows a valid building permit obtained from the Building Commissioner before work starts. The fee schedule shows the kinds of work the office actually permits.

Permit needed

  • New homes, duplexes and manufactured homes on permanent foundations
  • Additions, other than cosmetic changes such as new windows, drywall, reroofing or siding
  • Accessory buildings over 200 square feet or on a permanent foundation: storage buildings, garages, pole buildings
  • Placing a mobile home, and in-ground swimming pools
  • Commercial and institutional buildings and additions, towers, commercial solar facilities and signs

Not permitted or not required

  • Fences: no permit in the unincorporated county, but none may sit in a platted easement
  • Cosmetic work such as windows, drywall, reroofing and siding
  • Building permits for mobile homes more than 15 years old: not issued
  • Recreational vehicles as homes: not allowed

Most home sites need about one acre; lots created before the 2008 subdivision control ordinance are grandfathered as building tracts if the home meets zoning and on-site sewage rules. The office suggests calling the Building Commissioner to confirm a lot can be built on before you buy it.

What the county decides and what the state holds

The commissioners adopted the building code on May 1, 2018, by the date on the signed ordinance; the department’s own page gives June 1, 2018 as the adoption date and calls it the first building code in the unincorporated county. A rewritten zoning ordinance and map followed on July 1, 2018. The county sets fees through the County Council, writes the zoning and subdivision rules and decides which local licenses must be on file. Class 1 buildings still need the state Construction Design Release, and the ordinance requires a copy with the application where state rules call for one.

Jackson County building department: who handles permitting

Planning & Zoning issues building permits, inspects homes, administers the floodplain rules and the property maintenance code, runs the county GIS and staffs the Plan Commission and Board of Zoning Appeals. Daulton Anderson is the Building Commissioner. The office serves only the unincorporated county: the county’s own page sends owners in the city and towns to their local offices and states that the City of Seymour’s two-mile fringe falls under Seymour’s zoning and permitting.

Short on time to read all of this?

Get a free quote →
Who handles permits where in Jackson County
PlaceOffice named by the county
Unincorporated county outside Seymour’s fringeJackson County Planning & Zoning, (812) 358-6109
Seymour (pop. 22,450) and its two-mile fringeCity of Seymour Planning & Zoning, (812) 522-4746
Brownstown (3,154)Town of Brownstown, (812) 358-5500
Crothersville (1,506)Town of Crothersville, (812) 793-2311
Medora (641)Town of Medora Planning & Building, (812) 966-2281

The county office is open 8:00 a.m. to 4:30 p.m., Monday to Friday. The Plan Commission meets at 7:30 p.m. at the courthouse; in 2026 it meets on third Tuesdays (October 20 and November 17, for example), while the Board of Zoning Appeals’ 2026 agendas were for second-Tuesday meetings. Use the Jackson County GIS to see a parcel’s zoning and whether it lies in Seymour’s fringe before you file.

Jackson County permit types

The county keeps one building permit application for all project types, plus petition forms for zoning cases. The application records the work class, use, zone, building area, acreage, flood zone, setbacks, driveway permit number, any manufactured home moving permit and the required inspections.

Residential permits

For a new home or addition, the one permit covers building and framing, electrical and plumbing. Accessory buildings, mobile home placements and in-ground pools are permitted on the same form at flat fees. A mobile home also needs a moving permit from the Jackson County Treasurer’s Office, and a manufactured home installer must give a state license number.

Commercial permits

Commercial, institutional and industrial buildings use the same application and are priced at a base fee plus $0.08 per square foot. Wireless towers, cell tower alterations, commercial solar facilities, golf courses and signs have their own fees, and confined animal feeding operations are covered by Ordinance No. 13. Where the state requires a Construction Design Release, a copy goes in with the application.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Septic. Copies of all septic or sewer permits from the Jackson County Health Department, 801 W 2nd St, Seymour ((812) 522-6474); a new home site needs two approved septic sites. The requirements sheet also lists the Jackson County Regional Sewer District in Freetown ((812) 497-3072).
  • Driveway. A driveway permit from the Jackson County Highway Department (360 S. County Rd. 25 E., Brownstown, (812) 358-2226) or from INDOT’s Seymour office for state roads, issued before the building permit; changing an existing culvert also needs one, and the county charges nothing for it.
  • Deed, survey and site plan. A current recorded deed stamped by the County Recorder, a copy of any split survey, and a site plan showing property lines, distances to the structure, roads and right-of-way, legal drains, easements and setbacks.
  • Zoning. Variances, special exceptions, rezonings and vacations go to the Board of Zoning Appeals or the Plan Commission.
  • Floodplain. In a mapped flood zone, request the Base Flood Elevation from the state’s floodplain portal, have a licensed Indiana land surveyor complete an elevation certificate and set a reference mark at the Flood Protection Grade, and hand in the certificate before the permit issues; the plans must show the raised floor. A floodway also needs an IDNR Division of Water permit.
Residential setbacks in county zoning districts (front measured from the road centerline)
DistrictFront: county road / state roadSide: house / accessoryRear
AG, FR, R1, R2, LR60 ft / 100 ft10 ft / 10 ft10 ft
GB60 ft / 100 ft– / 10 ft– / 10 ft
I100 ft / 200 ft– / 50 ft– / 50 ft

The table follows the county’s FAQ; the older requirements sheet gives 5 feet for pole and accessory buildings, so confirm the side setback for an outbuilding with the office.

Jackson County permit costs and fees

The building ordinance leaves the fee to the Jackson County Council, and the office posts a “Jackson County Building Commission Fee Schedule” with no adoption date. The application requirements add a non-refundable filing fee. The office says county inspections of new homes come at no added cost beyond the permit.

Rather talk it over?

Call 1-855-478-4290 →
Jackson County Building Commission fee schedule
PermitFee
New residential construction (homes, duplexes, manufactured homes on permanent foundations)$0.08 per sq ft
Addition / accessory structure$75 / $75
New mobile home / in-ground pool$25 / $50
New commercial building$150 + $0.08 per sq ft
Commercial addition / institutional building$100 + $0.08 per sq ft
Golf course / structure other than a building$20 per green / $75
Wireless tower or facility / cell tower alteration$1,500 / $500
Commercial solar facility / sign$1,500 / $25
Special exception / variance$300 / $150
Rezone / vacation$300 / $150
Major subdivision preliminary / final plat$150 / $300
Minor subdivision final plat / exempt subdivision$200 / $50

Worked example: a new house of 2,000 square feet is 2,000 × $0.08 = $160 for the combined permit; a 30-by-40-foot pole barn is $75 at the flat accessory rate. Electrician and plumber license numbers that are missing when work starts can bring a fine of at least $100.

Trade permits and who may pull them

Jackson County does not issue separate electrical or plumbing permits for new homes and additions; the trades ride on the one building permit. What the office needs is the right paperwork on file before work starts.

  • Electricians: the electrician’s local license number must be on file with Planning & Zoning before construction.
  • Plumbers: the plumber’s state license number must be on file the same way.
  • Homeowners: an owner doing the work signs the county’s Electrical Home Owner Affidavit or Plumbing Home Owner Affidavit, certifying that they are the electrician or plumber of record, will request all inspections and agree not to sell the structure for at least one calendar year. The Building Commissioner attests the form.
  • General contractors: the application asks for the general contractor’s name, phone and email, and a manufactured home installer’s state license number.

Rather not deal with the Jackson County building department?

Get a free quote →

How to apply for a Jackson County building permit

1. Check the lot

Confirm the parcel is outside Seymour’s fringe and the towns, has about an acre and 150 feet of frontage where the home will sit, and can meet setbacks.

2. Get the septic and driveway permits

Obtain the health department’s septic approval (two sites) and the county or INDOT driveway permit first.

3. Gather documents

Recorded deed, any recorded survey, site plan, house plans and the contractors’ names and license numbers.

4. Add flood paperwork if needed

In a flood zone, get the Base Flood Elevation and a surveyor’s elevation certificate.

5. File the application

Submit the building permit application at the Brownstown office with the fee; call or email with questions about the form.

6. Post the permit and book inspections

Once issued, schedule each inspection at least 24 hours ahead.

Review, corrections and what causes delay

The requirements sheet warns that processing can take up to ten working days after a full submittal and that missing or inaccurate information delays review. The Building Commissioner may hold back new permits for anyone who owes fees, and may refuse permits for a property used in breach of the zoning ordinance until it is brought into line. Permits can be revoked for false statements or noncompliance, and stop-work orders are posted on site in writing with the conditions for resuming. Road setbacks are measured from the centerline: 60 feet on county roads and 100 feet on state highways in most districts.

Inspections and certificates of occupancy

The general contractor, or the owner acting as contractor, schedules every inspection and makes sure each is approved. All need 24 hours’ notice; same-day requests are taken only at the Building Commissioner’s discretion.

  • Footers: when footing trenches or basement areas are dug and forms set, or posts and piers placed, before concrete.
  • Foundation: before backfill, covering reinforcing steel, foam seal, sill plates, anchor bolts, sump pit and damp-proofing.
  • Rough-in: after framing and before insulation or wall coverings, covering framing, electrical, plumbing, energy efficiency, heating and ventilation.
  • Final: after construction, including electrical and plumbing fixtures.

A certificate of occupancy is issued once the final inspection is approved, and the home may not be occupied before then. In a flood zone the structure must be raised to the Flood Protection Grade, two feet above the Base Flood Elevation, and an as-built survey is required at completion.

Indiana building code in Jackson County

The county code incorporates the state’s building rules by reference and lets the Building Commissioner work with the fire department, which keeps its own inspection authority. FEMA’s Community Status Book lists unincorporated Jackson County (community 180405) as participating in the National Flood Insurance Program, with current maps dated November 19, 2014. Flood maps can be checked on the state’s floodplain portal.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Jackson County permit search and official resources

The office keeps building permits, code violations and Letters of Map Amendment in its GIS database, and it posts monthly lists of issued permits. For a specific record, call or email Planning & Zoning; recorded surveys are at the Recorder’s and Surveyor’s offices.

Inspections are where schedules slip.

Get a free quote →

Jackson County building permit FAQs

Does the county issue permits in Seymour?

No. Seymour and its two-mile fringe are under the city’s zoning and permitting; call Seymour Planning & Zoning at (812) 522-4746.

How much land do I need to build a house?

Typically one acre, with 150 feet of frontage where the home sits; lots split before 2008 are grandfathered if zoning and septic rules are met.

Do I need a permit for a fence?

Not in the unincorporated county, but fences may not be built in a platted easement and a boundary survey is recommended.

Can I do my own wiring or plumbing?

Yes, by signing the county’s homeowner affidavit for that trade, which includes a promise not to sell the house for at least a year.

How much is a permit for a new home?

$0.08 per square foot under the county schedule, so a 2,000-square-foot house is $160.

Can I place an older mobile home?

Not if it is more than 15 years old; the county does not issue building permits for those.

How far from the road must I build?

In most districts 60 feet from the centerline of a county road and 100 feet from a state highway; industrial districts need more.

Simplify Jackson County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jackson County sooner?

Let Alliance prepare, file, and track your Jackson County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jackson County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.