Jasper County, Indiana Building Permit Guide

To get a building permit in Jasper County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Jasper County Planning & Development in Rensselaer issues the combined improvement location and building permit for the county’s zoning area, taken online through Geo Permitting, once the driveway, septic and well permits are in hand.

Authority: Jasper County Planning & DevelopmentFiling: Geo Permitting (online)Phone: 219-866-4908
Permit office
Planning & Development115 W Washington St, Suite 109, Rensselaer
New house
$50 + $0.15 per sq ft$220 minimum
First get
Driveway, septic, wellNo permit without them
Hours
8 a.m.–4 p.m. weekdaysCentral time

In Jasper County, improvement location permits and building permits come from Jasper County Planning & Development, 115 West Washington Street, Suite 109, Rensselaer (219-866-4908), whose Director is also the county’s Building Inspector. Applications are filed online through Geo Permitting, and the office will not issue a permit until the driveway permit and the health department’s septic and well permits are obtained. A single-family home costs $50 plus $0.15 per square foot, with a $220 minimum. Rensselaer and DeMotte run their own building permits.

What requires a building permit in Jasper County?

Jasper County combines zoning approval and the building permit in one application, the Application for Improvement Location Permit and Certificate of Occupancy. The department’s fee list shows which structures it permits.

Permit needed

  • Single-family homes, modular homes and manufactured homes
  • Additions and alterations
  • Portable sheds and accessory buildings of 200 square feet and up
  • Temporary structures

Also on the fee list

  • Above-ground and in-ground swimming pools
  • Ponds
  • Signs and accessory towers
  • Private solar installations
  • Commercial buildings (fees on request)

Mailboxes need no permit, but a rural mailbox may not stand closer than five feet to the edge of the road surface, and the owner must provide a drive-off for the carrier; the post office sets the height and placement. Work in a county road right-of-way needs a right-of-way permit from the County Engineer, separate from the building permit.

What the county decides and what the state holds

The county writes its zoning and subdivision rules in the Unified Development Code, published in the online Jasper County Code, and sets its own permit fees. Rezonings start at the Plan Commission and are decided by the Board of County Commissioners. The commissioners have also set conditions on large projects: before an improvement location permit for rough grading could be issued for the Amazon data center site approved in June 2026, the commissioners required a road use agreement, approved on July 6, 2026. Class 1 buildings need the state Construction Design Release in addition to the county permit, and commercial fees are quoted by the office on request.

Jasper County building department: who handles permitting

Planning & Development is a small office: the Director, Mary Scheurich, also serves as Building Inspector, and the same staff support the Plan Commission and the Board of Zoning Appeals. The office now takes credit cards. The cities and towns of Jasper County keep their own permit systems where their own sites show one.

Short on time to read all of this?

Get a free quote →
Permit offices in Jasper County
PlaceWho handles building permits
Unincorporated Jasper CountyJasper County Planning & Development, 219-866-4908
Rensselaer (pop. 5,681)The city; its website links a Cloudpermit building permit portal
DeMotte (4,384)The town’s building department, with online permits since 2023 and its own fee schedule
Wheatfield (931)The town’s site has a building permits and inspections page; ask the town hall
Remington (1,392)Ask the Town of Remington which office issues building permits there

The Plan Commission and Board of Zoning Appeals meet together at 7 p.m. on the dates posted on the department’s calendar (November 16 and December 21 in late 2026), with a Zoom option posted on the department page. Plan Commission members include a county commissioner, a council appointee, the county extension educator and the County Surveyor. Staff prepare a report on each petition before the hearing, measuring it against the Comprehensive Plan and the zoning and subdivision standards; the applicant presents first, then the public speaks, and written comments filed beforehand are read into the record. Plan Commission decisions on site development plans and subdivisions are final unless appealed to court, while rezonings go on to the commissioners.

Jasper County permit types

The improvement location permit and certificate of occupancy application is filed through the county’s Geo Permitting workflow. The department’s “Before You Build” sheet sets out what goes with it.

Residential permits

A new house needs construction drawings with dimensioned floor plans showing window sizes and locations, structural or framing plans or a cross-section noting the size and spacing of members, the electric panel location, at least one elevation, the foundation design and truss drawings. A manufactured home needs a copy of the title in the owner’s name showing it was built in 1981 or later, plus the installation instructions. Every application lists the contractors and subcontractors on the county’s form.

Commercial permits

Commercial work uses the same online application, but the posted schedule gives no commercial fees; the office provides them on request. A commercial or other Class 1 project should have its state design release before construction starts, and larger developments may first need Plan Commission action.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Driveway permit. Any driveway or field entrance onto a county road needs a Highway Department permit, obtained before you apply for the building permit; state highways go through INDOT ((219) 866-5451 on the county sheet).
  • Septic and well permits. From the Jasper County Health Department, 910 S. Sparling Ave., Rensselaer ((219) 866-4917; Environmental Department (219) 866-8523); no building permit is issued without them. The department’s environmental health program permits residential onsite sewage systems and water wells, keeps lists of septic contractors, well drillers and soil scientists, and registers septic installers each year.
  • Regulated drains. Jasper County has 1,162 miles of county regulated drains, overseen by the County Surveyor (2530 N McKinley Ave, Rensselaer, (219) 866-4907) and the Drainage Board, which meets at 1:00 p.m. on the first Monday of the month. The Surveyor also sits on the Plan Commission and votes on subdivisions.
  • Site plan. A survey if available, showing the structure’s size and distances to all property lines or road right-of-way, whichever is more restrictive, existing buildings, the height from grade to peak, a north arrow, the driveway and the road used for access.
  • Zoning approvals. Variances, special exceptions, use variances and appeals of the Director’s decisions go to the BZA; map changes, planned unit developments and subdivisions to the Plan Commission. Neighbors within 300 feet are notified and may file written comments up to the day of the hearing.
  • Floodplain. Development in mapped flood areas falls under the county’s flood rules and FEMA maps; ask the office before grading.

Jasper County permit costs and fees

The county’s fee schedule is printed on the second page of the “Before You Build” sheet. It carries no adoption date, so ask the office to confirm a figure before you budget a large job.

Jasper County Planning & Development fee schedule
PermitFee
Single-family home$50 + $0.15 per sq ft, $220 minimum
Modular home / manufactured home$200 / $150
Addition$50 + $0.10 per sq ft, $200 minimum
Alteration$200
Portable shed / temporary structure$100 / $100
Accessory building, 200–720 sq ft$100
Accessory building over 720 sq ft$150 + $0.05 per sq ft, $500 maximum
Above-ground / in-ground pool$100 / $150
Pond / sign$50 / $90
Accessory tower / private solar$150 / $150
County-road driveway permit (Highway Department)$100, payable to the Jasper County Treasurer
Septic permit, conventional / mound system (Health Department)$250 / $450
Well permit, new or replacement (Health Department)$150
CommercialOn request

Rather talk it over?

Call 1-855-478-4290 →

Worked examples from the schedule: an 1,800-square-foot house is $50 + (1,800 × $0.15) = $320; a 1,000-square-foot pole barn is $150 + (1,000 × $0.05) = $200; a 300-square-foot addition works out to $80, so the $200 minimum applies. The driveway permit is paid separately in cash or by check at the Highway Department. Health department septic and well permits are non-refundable, stay valid for one year and may be paid in cash, by money order, check or card (with a card fee); septic installers pay $250 a year to register.

Trade permits and who may pull them

The county pages describe one permit per project rather than separate electrical, plumbing or HVAC permits, and the application asks for the full list of contractors and subcontractors. The house plans must show the electric panel location.

  • Plumbers: Indiana licenses plumbing contractors, so list the licensed plumbing contractor on the contractor form.
  • Electricians, HVAC and builders: the county pages show no local license or registration for these trades; the contractor list is the record the office keeps.
  • Owner-builders: the county pages do not set out an owner-builder rule; ask Planning & Development before doing your own trade work.

Inside Rensselaer, DeMotte and the other towns, follow the town’s own trade rules.

How to apply for a Jasper County building permit

1. Confirm the jurisdiction

Check that the parcel is outside Rensselaer, DeMotte and the towns, and check its zoning on the county’s GIS and property record cards.

2. Get the driveway permit

Visit the Highway Department at 2676 West Clark Street with the property location, township, subdivision and lot if any, your contact details and $100; the garage keeps seasonal hours (5 a.m. to 4:15 p.m. Monday to Thursday from April to October, 6 a.m. to 3:30 p.m. weekdays from November to March).

3. Get septic and well permits

Apply to the Jasper County Health Department in Rensselaer.

4. Prepare drawings and the site plan

Assemble the construction drawings, the site plan and the contractor list.

5. Apply online

File through Geo Permitting, or call 219-866-4908 for help.

6. Pay and keep the permit on site

Pay the fee, now including by credit card, and follow the inspection instructions on the permit.

Rather not deal with the Jasper County building department?

Get a free quote →

Review, corrections and what causes delay

The most common hold-up is the order of steps: the building permit cannot issue until the driveway, septic and well permits exist, and the driveway inspection alone takes two to three business days to decide whether a culvert is needed. If one is, the Highway Department gives the pipe specifications, sells culverts and inspects the installation. For one- and two-family homes, state law since January 1, 2026 sets short local review and inspection deadlines and lets an applicant hire a private reviewer if they are missed.

Inspections in Jasper County

Inspections are arranged through Planning & Development, whose Director holds the Building Inspector title, and the application doubles as the request for a certificate of occupancy once the work is finished. Call the office to book each inspection and to confirm which stages your permit needs. The Highway Department separately inspects new driveways for culvert needs and inspects any culvert after it is installed.

Keep the approved drawings on site and do not cover work before it has been seen. Do not move into a new house or use a new building until the certificate of occupancy has been issued. For a new home on a private well, the health department’s occupancy approval needs the well water test results and a copy of the Record of Water Well; the department does not test water itself and lists testing locations in DeMotte and Rensselaer, and the results must be sent to it.

Indiana building code in Jasper County

Jasper County applies the statewide building rules through its own permit process, while its Unified Development Code, part of the online county code, sets the zoning districts, setbacks and subdivision standards that the improvement location permit checks. FEMA’s Community Status Book lists unincorporated Jasper County (community 180439) as participating in the National Flood Insurance Program, with flood maps effective December 21, 2018. City and town flood rules are separate from the county’s.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Want this handled start to finish?

Get a free quote →

Jasper County permit search and official resources

To find a past permit or certificate of occupancy, call Planning & Development with the address or parcel number; zoning and property record cards are on the county’s GIS. Commissioners’ minutes and agendas for 2026 are posted on the county site.

Inspections are where schedules slip.

Get a free quote →

Jasper County building permit FAQs

Where do I apply for a building permit in Jasper County?

Online through Geo Permitting, or with help from Planning & Development at 115 West Washington Street, Suite 109, Rensselaer (219-866-4908).

How much is a building permit for a new house?

$50 plus $0.15 per square foot, with a $220 minimum; an 1,800-square-foot house is $320. The county-road driveway permit adds $100.

Do I need a driveway permit first?

Yes. The Highway Department’s driveway permit, and the health department’s septic and well permits, must be obtained before the building permit is issued. If the Highway Department calls for a culvert, it must be inspected after installation.

Does a shed need a permit?

Yes. Portable sheds are $100, accessory buildings of 200 to 720 square feet $100, and larger buildings $150 plus $0.05 per square foot, capped at $500.

Does the county issue permits in Rensselaer or DeMotte?

No. Rensselaer uses its own online building permit portal and DeMotte has its own building department.

What do septic and well permits cost?

At the Jasper County Health Department a conventional septic permit is $250, a mound system $450 and a new or replacement well $150; each is good for one year.

Can I place a manufactured home?

Yes, with a permit ($150) if the title shows it was built in 1981 or later and you supply the installation instructions.

Who decides a variance?

The Board of Zoning Appeals, which meets with the Plan Commission at 7 p.m.; neighbors within 300 feet are notified.

Simplify Jasper County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jasper County sooner?

Let Alliance prepare, file, and track your Jasper County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jasper County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.