To get a building permit in Jay County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The joint Jay/Portland Building & Planning Department in Portland issues zoning and improvement location permits and inspects building work for unincorporated Jay County, Pennville, Salamonia and the City of Portland.

Authority: Jay/Portland Building & Planning DepartmentZoning: Jay County Zoning & Subdivision OrdinancePhone: 260-726-6904
Permit office
Jay/Portland Building & Planning118 S. Meridian St, Ste E, Portland
County area
Unincorporated + 2 townsPennville and Salamonia
Permit lasts
12 monthsOne 6-month renewal
Fees
Not posted onlineCall 260-726-6904

Jay County and the City of Portland share one office for building and zoning permits: the Jay/Portland Building & Planning Department at the Community Resource Center, 118 South Meridian Street, Suite E, Portland (260-726-6904). On the county side it covers Pennville, Salamonia and all unincorporated land, issuing the improvement location permit under the county zoning ordinance and inspecting the work. Fees come from a schedule set under the Portland–Jay County inter-local agreement and are not posted online, so call the department for a figure.

What requires a building permit in Jay County?

The department answers the question project by project on its “Do I Need A Permit For” list. Under the zoning ordinance, no building may be built, rebuilt, enlarged or moved without an improvement location permit from the Zoning Administrator.

Permit required

  • New homes, garages and carports, and new or enlarged basements
  • Additions, structural changes and structural roof changes
  • Porch roofs, lean-tos and decks
  • Accessory buildings of 100 square feet and larger
  • Pools (above or in ground) and ponds
  • Agricultural buildings, structures and grain bins
  • Commercial buildings, towers, merchant and business occupancies, and home occupations
  • Fences, signs and non-residential awnings, but only in Pennville

No permit

  • Replacing windows
  • Replacing vinyl siding
  • Sidewalks
  • Driveways

Confined feeding operations have their own rules in Section 216 of the zoning ordinance, and commercial wind farms, small private wind towers and solar energy systems have separate standards in Sections 217 to 219.

What the county decides and what the state holds

The county zoning and subdivision ordinance, first adopted as Ordinances 1991-4 and 1991-5 and amended most recently in December 2019, applies to all land in Jay County not covered by the ordinances of Portland, Dunkirk, Bryant or Redkey. The county writes its own zoning districts, lot sizes, setbacks and floodplain rules, and the improvement location permit checks a project against them. The ordinance states that an improvement location permit does not replace any building permit the county commissioners require, nor any municipal, state or federal rule. Class 1 buildings need the state Construction Design Release as well as the local permits.

Jay County building department: who handles permitting

The Jay/Portland Building & Planning Department, led by Director and Administrator John Hemmelgarn, issues both city and county building and zoning permits, inspects building and zoning work, runs local plan review and rezonings, administers both flood control ordinances and staffs the city and county Plan Commissions and Boards of Zoning Appeals. Which ordinance applies depends on where the parcel is. The county’s Advisory Plan Commission has members appointed by the county commissioners, the county council, the Purdue Extension board and the County Surveyor, and the Advisory Board of Zoning Appeals has members named by the commissioners, the council and the Plan Commission.

Short on time to read all of this?

Get a free quote →
Building and zoning authority in Jay County
PlaceRules and office
Unincorporated county, Pennville (pop. 614) and Salamonia (149)County zoning ordinance; Jay/Portland Building & Planning Department
Portland (6,237)City zoning and flood ordinances; the same joint department
Dunkirk (1,969 people in Jay County; the city extends into a neighboring county), Redkey (1,071), Bryant (236)Their own ordinances; the county zoning ordinance does not apply. Ask the city or town
Building & Planning contacts
DetailInformation
OfficeCommunity Resource Center, 118 S. Meridian Street, Suite E, Portland, IN 47371
Phone260-726-6904
Courthouse (county offices)120 North Court Street, Portland; (260) 726-7575
MapsZoning, floodway and floodplain layers on the Jay County eGIS

Jay County permit types

One form, the Application for Zoning & Improvement Location Permit, serves both the city and the county. It asks for the project address and township, whether the property is in a flood zone, the front, rear and side setbacks, a description and use of the structure, its size, number of stories and total new square footage, whether there is a basement, whether a septic permit is required, the start date and the estimated construction cost.

Residential permits

Homes, garages, additions, decks, porch roofs, accessory buildings of 100 square feet or more, pools and ponds all go on the same application. List the foundation, building, plumbing, electrical and mechanical contractors and, for a new septic system, the installer. In the Agricultural/Residential (AR) district a lot served by a well and septic system must be at least 2 acres, buildings sit at least 30 feet from the road right-of-way and 5 feet from property lines, and accessory buildings may not exceed 16 feet in height without Board of Zoning Appeals approval.

Not sure this scope needs a permit?

Get a free quote →

Home and farm solar arrays (personal solar energy systems) are allowed as accessory uses for the owner’s own power. A ground-mounted array may stand no more than 20 feet tall at full tilt, keeps 10-foot side and rear setbacks and may sit in the front setback only if at least 100 feet back from the right-of-way with a vegetative buffer toward neighboring homes. A roof-mounted array needs a licensed engineer’s certificate that the structure can carry the panels and a visible disconnect. Before the permit, the Zoning Administrator needs a site plan showing the panels, disconnect, structures and septic field, proof that the electric utility has been told, and proof that the site plan went to the local fire protection district.

Commercial permits

Commercial buildings, towers, merchant and business occupancies and home occupations need the same improvement location permit, with a certificate of compliance before the space is used. A commercial wind farm application carries a $20,000 fee under Section 217, payable on submission, to cover the county’s review costs. Class 1 work also needs the state design release.

A confined feeding operation starts with an Intent to Build/Confined Feeding Application and site plan. The Zoning Administrator sends it to the County Surveyor, County Engineer and Highway Department, who inspect the site and report within two weeks; owners and tenants within half a mile are notified by mail, a legal notice is published at the applicant’s cost, and written comments are taken for 30 days. With the Soil & Water Conservation District, IDEM and health department approvals that apply, the operator can then take out the building permit.

What comes before the building permit

  • Septic. The application asks whether a septic permit is required; ask the Jay County Health Department, 504 West Arch Street, Portland (260-726-8080).
  • Roads and drains. County roads are maintained by the Jay County Highway Department, 1035 East 200 North, Portland (260-726-8701); drainage records are kept by the County Surveyor at the courthouse (260-726-8784), and ponds must follow the Jay County Drainage Ordinance.
  • Floodplain. Floodways and floodplains are regulated by Portland, Jay County, the Indiana DNR and FEMA, and the department asks anyone building near a ditch, waterway or low area to contact it first.
  • Zoning relief. Any decision of the Zoning Administrator on a permit can be appealed to the Board of Zoning Appeals, which also hears variances; rezonings go through the Plan Commission.

Rather talk it over?

Call 1-855-478-4290 →

Jay County permit costs and fees

Jay County does not publish its permit fees. Section 403 of the zoning ordinance says filing fees come from a fee schedule created by the Inter-local Board under the inter-local agreement between the City of Portland and Jay County and adopted by Commission resolution; the schedule is kept outside the ordinance so it can be revised the same way. The department’s page says fees vary with the project and asks applicants to call 260-726-6904.

Fees and penalties written into the Jay County zoning ordinance
ItemAmount
Replacement permit card$5
Commercial wind farm application (Section 217)$20,000, paid on submission
Building, zoning, plat and appeal feesInter-local Board schedule; call the department
Fine for a first violation$500 to $2,500
Continuing or later violations$500 to $7,500 per day

Payment of the permit fee is one of the conditions in the ordinance before the improvement location permit can be issued, so ask for the amount when you first call. Each day a violation continues counts as a further violation.

Trade permits and who may pull them

The county pages show one zoning and improvement location permit per project rather than separate trade permits. The application records each trade contractor, and the plumbing line asks for an Indiana plumbing license number, reflecting the state’s plumbing contractor licensing. The pages list no local license or registration for electricians, HVAC contractors or general contractors, and they do not set out an owner-builder rule, so ask the department before you do your own trade work. Septic installation is listed separately on the application.

Rather not deal with the Jay County building department?

Get a free quote →

How to apply for a Jay County building permit

1. Confirm whose rules apply

Check that the parcel is in the unincorporated county, Pennville, Salamonia or Portland; Dunkirk, Redkey and Bryant handle their own.

2. Check zoning and flood maps

Look up the zoning district and any floodway or floodplain on the eGIS, or call the department.

3. Draw the plot plan

Show the dimensions of the lot, every existing and proposed structure, setbacks and side yards, drawn to scale.

4. Gather plans and contractor details

A complete copy of the blueprints, the estimated cost and each contractor’s name and phone.

5. File with the department

Download the application or pick it up at 118 South Meridian Street, and apply for the certificate of compliance at the same time.

6. Post the permit card

Once issued, keep the card displayed on site, protected from the weather, until the work is done.

Review, corrections and what causes delay

The ordinance asks the Zoning Administrator to try to decide permits within three business days of filing, longer when a project needs more review. A permit expires if work has not begun within 90 days of issue, and the improvement location permit is valid for 12 months; the Zoning Administrator may renew it once for six months on a written reason, and the Board of Zoning Appeals may extend it by up to a year more. Applications that conflict with the zoning ordinance cannot be issued without a written order from the BZA, the Plan Commission or a court.

Inspections and certificates of compliance

The department performs building and zoning inspections in its service area; call 260-726-6904 to arrange them and ask which stages your project needs. The permit card must stay posted on the property throughout construction.

Under the zoning ordinance, Jay County issues a certificate of compliance. No new or enlarged building, change of use of a building or land, or change to a non-conforming use may be occupied until one is issued. Apply with the improvement location permit for new work, or within 10 days of a planned change of use; the certificate is issued within four days if the use conforms. A temporary certificate may cover up to six months while work is completed, and a record of each certificate is kept at the Plan Commission office.

Indiana building code in Jay County

The department applies the statewide building rules through its permits and inspections. FEMA’s Community Status Book lists unincorporated Jay County (community 180440) as participating in the National Flood Insurance Program, with its first flood insurance rate map and current maps both dated March 17, 2014. The zoning ordinance’s flood plain district covers both floodway and fringe areas approved by the DNR, and in it a lot on a well and septic system must be at least 2 acres. Inside Portland the same department applies the city’s own flood control ordinance instead.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Jay County permit search and official resources

Site plans filed with improvement location permits are kept by the Plan Commission as public records, and certificates of compliance are recorded at its office, so ask the Building & Planning Department (260-726-6904) for copies tied to a parcel, giving the address and township.

Jay County building permit FAQs

Where do I get a building permit in Jay County?

At the Jay/Portland Building & Planning Department, 118 South Meridian Street, Suite E, Portland (260-726-6904), for Portland, Pennville, Salamonia and the unincorporated county.

Inspections are where schedules slip.

Get a free quote →

How much does a permit cost?

Fees depend on the project and are not published online; the schedule is set under the Portland–Jay County inter-local agreement, so call the department for a quote.

Do I need a permit for a fence?

In the county’s area, only in Pennville: the department marks fences, signs and non-residential awnings “Pennville only”. Portland follows its own city ordinance, so ask the department about a city lot.

Does a pole barn or grain bin need a permit?

Yes. Agricultural buildings, structures and grain bins are on the permit list, as are accessory buildings of 100 square feet and larger.

How long is a permit good for?

Work must begin within 90 days, and the improvement location permit runs for 12 months, with one six-month renewal by the Zoning Administrator and a possible BZA extension.

What is a certificate of compliance?

Jay County’s sign-off that a new building or changed use meets the zoning ordinance; the building may not be occupied until it is issued.

Can I put solar panels on my house or barn roof?

Yes, with a permit; a licensed engineer must certify that the roof can carry the panels, and the system needs a visible disconnect.

Does the county handle Dunkirk or Redkey?

No. The county zoning ordinance does not apply in Portland, Dunkirk, Bryant or Redkey; Portland uses the same joint department, and the others have their own ordinances.

Simplify Jay County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Jay County sooner?

Let Alliance prepare, file, and track your Jay County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Jay County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.