In Randolph County, building permits come from the Randolph County Building Commission at 325 South Oak Street, Suite 204, Winchester ((765) 584-0275), where Robert Jessee is Building Commissioner. You first get an improvement location permit from Area Planning in the same suite, and once the paperwork is complete the Building Commission can usually issue the permit in a few minutes. Under Ordinance 2024-10 a conventional new house costs $400 plus $0.04 per square foot, covering all trades.
What requires a building permit in Randolph County?
The Building Commission’s guidance to homeowners puts it simply: building, altering, demolishing or repairing any building, other than maintenance, needs a local permit, and demolition permits are required too. Ordinance 2024-10, adopted by the Board of Commissioners on July 1, 2024, rewrote the exemption list in section 150.07(B) of the county code.
Building permit required
- New houses, manufactured and modular homes
- Additions and structural changes
- Detached garages, pole barns and grain bins
- Decks, unless small, low, detached and not serving an exit
- Electrical, HVAC and plumbing work of $1,500 or more, and new or updated panels
- Swimming pools 2 feet deep or more
- Wind turbines, solar systems and communication towers
- Fire sprinkler systems, signs and demolition
Exempt under s.150.07(B)
- One-story detached structures under 200 sq ft (120 sq ft commercial)
- Normal maintenance: roofing, siding, windows, doors, painting, flooring, cabinets
- Alterations costing less than $1,500 in total for all trades and framing
- Fences 6 feet or under; retaining walls 4 feet or under
- Sidewalks, driveways, ponds and playground equipment
- Prefabricated pools under 2 feet deep, entirely above ground
- Window awnings projecting under 54 inches; solar under 8 sq ft
The list also exempts decks under 200 square feet that are under 30 inches high, detached and not serving the required exit, emergency repairs (permit by the next working day) and micro wind turbines. The ordinance says plainly that these exemptions do not apply to improvement location permits, so a small shed can still need zoning approval. The Building Commission’s web FAQ carries an older list (pools over 36 inches, sheds over 200 square feet and $1,500, fences under 6 feet); where the two differ, Ordinance 2024-10 is the adopted text.
What Randolph County decides and what the state holds
The county sets its own building ordinance and fees, contractor registration, unified zoning, solar and wind rules, and drainage requirements, while the state’s building rules set the technical standard. A commercial (Class I) building, including a wedding or party barn, needs the state Construction Design Release before the local permit, and the county’s venue guidance says public-use buildings need architect-drawn plans; the Building Commission’s non-commercial form is limited to one- and two-family dwellings, agricultural-use buildings, garages and sheds that are not used by the public or by an employee.
Short on time to read all of this?
Get a free quote →Randolph County building department: who handles permitting
The Building Commission issues building and demolition permits, registers contractors and inspects. Area Planning, staff to the Area Planning Commission and Board of Zoning Appeals, issues improvement location permits, and its director serves as the county’s zoning and floodplain administrator. One Unified Zoning Ordinance and zoning map cover the county, the cities of Winchester and Union City, and the towns of Farmland, Losantville, Lynn, Modoc, Parker City, Ridgeville and Saratoga; it replaced each of their own zoning ordinances. The county’s building pages list no city or town with a separate building department, and the zoning ordinance’s plan-review checklist names the county Building Commission among the agencies for projects in Winchester, Union City and the towns. Part of the Town of Albany lies in Randolph County; the zoning ordinance does not name it, so ask the Town of Albany.
| Office | Contact |
|---|---|
| Building Commission | 325 S. Oak St., Suite 204, Winchester, IN 47394; (765) 584-0275; fax (765) 584-0098; bldcomsec@randolph.in.gov; 8 a.m. to 4 p.m., arrive by 3:30 to apply |
| Building Commissioner | Robert Jessee |
| Area Planning (zoning, ILPs, floodplain) | Same suite; (765) 584-8610; 8 a.m. to 4 p.m. |
| Health Department (septic) | (765) 584-1155 |
| Surveyor and Drainage Board | 325 S. Oak St., Room 206; (765) 584-0609 |
| Highway Department | 2256 S. US Hwy 27, Winchester; (765) 584-2601; barn open Monday to Thursday, 7 a.m. to 5 p.m. |
Randolph County permit types
The Building Commission has two building permit applications, non-commercial (form BC-100) and commercial, plus demolition and contractor registration forms. Area Planning has three improvement location permit forms: APC#300 for buildings and additions, APC#301 for swimming pools and ponds, and APC#302 for single-wide manufactured homes.
Residential permits
- New homes. Bring a copy of the blueprints and the septic permit; each contractor (general, plumbing, HVAC, electrical, concrete, excavation) is listed with its cost, and an unrealistically low cost can be adjusted, with penalties. The back of the form records roof truss, floor truss and I-joist types for the fire department, because advanced structural components must be disclosed before the permit issues.
- Manufactured homes need the manufacturer’s footer and foundation set-up specifications; on residentially zoned land outside a licensed mobile home park they also need a BZA special exception.
- Sheds and pole barns. Every outbuilding, including a “portable” prebuilt shed, needs an improvement location permit unless it leaves the property within six months, and needs a building permit unless it is under the 200-square-foot exemption.
- Pools. In-ground pools need an ILP and building permit; an above-ground pool needs an ILP at 18 feet wide and 3 feet deep, must be at least 5 feet from lot lines, may not sit in a required front yard, and must be fenced in an R zone.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial projects file the commercial building permit only after the state design release. The county’s own venue guidance lists what that can involve: a fire protection system for more than 100 guests, a commercial well with enough pressure if there is no city water, a commercial septic system designed by a professional and approved by the Indiana Department of Health, architect-drawn plans, and a drainage plan approved by the Drainage Board when the building, lane and parking cover more than 20,000 square feet. Most such uses start with a conditional use from the BZA.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Improvement location permit. Required any time square footage is added: a new home, manufactured home, addition, detached structure, pool, patio, pond or deck. Area Planning prints a GIS aerial of the lot, checks setbacks, floodplain and easements, and sends the application to the Surveyor’s Office to confirm the structure is at least 75 feet from a legal county ditch.
- Septic or sewer. A Health Department septic permit for new homes and added bedrooms, or a sewer tap permit from the city or town.
- Driveway. No zoning permit is needed for a driveway on your own property, but the Building Commission tells applicants to contact the County Highway Department about its placement.
- Fences. No ILP, but the zoning ordinance rules apply and fences may be built on the property line.
- Floodplain. A floodplain development permit from the floodplain administrator for any development in a mapped flood area; the ordinance sets its flood protection level, for the lowest floor including any basement, at 2 feet above the regulatory flood.
Randolph County permit costs and fees
Fees are set by section 150.09 of the county code as amended by Ordinance 2024-10 (adopted July 1, 2024) and posted as form BC5. Square footage is measured on the main structure including basements, attached garages and covered porches, and every fee is rounded to the nearest dollar. “All crafts” means electrical, plumbing and HVAC are included.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New house, conventional (all crafts) | $400 + $0.04 per sq ft |
| New duplex or barndominium (all crafts) | $400 + $0.06 per sq ft |
| Addition / renovation (all crafts) | $300 + $0.04 per sq ft / $175 + $0.04 per sq ft |
| Detached garage / accessory structure | $150 + $0.04 per sq ft / $50 |
| Deck, covered porch or balcony | $0.04 per sq ft; $50 minimum |
| Manufactured home, new / used pre-1976 | $0.15 per sq ft / $0.10 per sq ft |
| Modular home, new / used | $400 + $0.04 per sq ft / $200 + $0.04 per sq ft |
| Residential electrical, HVAC or plumbing, new installation | $0.04 per sq ft; $200 minimum |
| Electric meter only / panel remodel / generator | $40 / $0.04 per sq ft, $75 minimum / $40 |
| Pool above ground over 2 ft / in-ground; signs | $40 / $100; $40 |
| Commercial primary structure (all crafts) | $0.15 per sq ft, $200 minimum; $0.02 per sq ft above 10,000 sq ft |
| Pole barn 1,400 sq ft or less / over 1,400 sq ft | $0.12 per sq ft / $50 + $0.10 per sq ft, maximum $1,000 |
| Solar, non-commercial over 3 kW / commercial | $100 / $500 per MW |
| Demolition / one-year renewal | $35 non-commercial, $100 commercial / $35 |
| Uses not listed | $4.00 per $1,000 of cost |
Worked example from the schedule: a conventional house measuring 2,000 square feet including its basement, attached garage and covered porch costs $400 + (2,000 × $0.04) = $480, with all trades included. Building without a required permit multiplies the fee by two for a first offence, three for a second and four after that, and working through a stop order costs $500 for the first day and $200 for each further day. The Health Department’s septic permit is $85, and contractor registration is $25; the Building Commission does not take credit cards.
Trade permits and who may pull them
Contractors must register with the Building Commission before starting any construction or demolition project in the county, for a $25 fee by mail or in person. No building permit is issued unless a registered contractor or the homeowner is listed as general contractor, and subcontractors count as contractors, so each one registers too. Applications may be filled out and paid for by the owner or the owner’s agent.
- Insurance and bonds. The county does not require contractors to show liability insurance or a license or permit bond, so owners should ask for a certificate of insurance and any bond themselves.
- Trades on new work. House, addition and renovation fees include all crafts; stand-alone electrical, HVAC and plumbing work has its own lines, from a $40 meter or replacement to $0.04 per square foot for a new installation.
- Plumbing. Plumbing contractors still need the state plumbing license, and plumbing is listed as its own contractor on the permit.
- Septic installers register separately with the Health Department.
Rather not deal with the Randolph County building department?
Get a free quote →How to apply for a Randolph County building permit
Call (765) 584-8610 with the address and plans; the office checks zoning and setbacks on the county GIS.
File APC#300, #301 or #302; the Surveyor checks legal ditch setbacks and the floodplain is reviewed.
Apply to the Health Department, or to the city or town utility.
Commercial (Class I) work obtains the state design release before applying locally.
Bring the BC-100 or commercial form, plans and septic permit to Suite 204 by 3:30 p.m., with every contractor registered.
Pay the BC5 fee; a complete application can usually be issued the same visit.
Review, corrections and what causes delay
Because a complete non-commercial application can be issued in minutes, most delays come before the counter: a missing improvement location permit, a structure inside the 75-foot legal ditch setback, septic soils that fail, an unregistered subcontractor, or a commercial project still waiting on the state. Septic sites can take longer where recessional moraine soils are found: over 50% clay triggers a modified permeability test, and the site may be rejected.
Inspections in Randolph County
The contractor or owner calls the Building Commission at (765) 584-0275 with 24 hours’ notice when each stage is ready. For non-commercial (Class II) buildings the schedule is: footer (pre-pour, with grade stakes or forms set, or a hole inspection for pole buildings); poured foundation walls with forms and rebar in place; foundation (slab before pouring, crawl space with sump, anchor bolts, perimeter drain and insulation, or basement with waterproofing and drains); rough-in after the building is enclosed, with all plumbing, HVAC and electrical rough-in done, roofing, windows and doors in place and the system ready for a pressure test; wallboard before taping; and final.
At the final, plumbing, HVAC and electrical must be complete, decks, porches, steps and handrails finished, grading done and the dwelling ready to occupy. Insulation may not go in until the rough-in inspection passes.
Indiana building code in Randolph County
Randolph County enforces the state building rules through chapter 150 of its county code, with the Building Commissioner authorized to stop work that breaks it. FEMA lists unincorporated Randolph County as participating in the National Flood Insurance Program, with a current map dated March 4, 2013 that shows no flood elevations, and the Unified Zoning Ordinance carries the floodplain rules.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Randolph County building permit FAQs
How much is a building permit for a new house in Randolph County?
$400 plus $0.04 per square foot of the main structure including basement, attached garage and covered porches, with all trades included; 2,000 square feet is $480.
Do I need a permit for a shed?
Every shed needs an improvement location permit; a building permit is also needed unless it is a one-story detached structure under 200 square feet.
Do I need a permit to replace my roof or siding?
No. Replacing roofing, siding, windows and doors is normal maintenance under the 2024 ordinance, unless the structure changes.
Can a homeowner pull the permit?
Yes. The owner may apply and be listed as general contractor; any contractor or subcontractor working on the job must be registered.
Does the county require contractors to carry insurance?
No. Registration costs $25 and needs no insurance or bond, so homeowners should ask contractors for a certificate of insurance.
How close to a county drain can I build?
The Surveyor’s Office checks every improvement location permit to keep structures at least 75 feet from a legal county ditch.
What happens if I build without a permit?
The fee doubles for a first offence, triples for a second and quadruples after that, on top of any stop-order fines.
Randolph County permit search and official resources
Permit and inspection records for county permits are held by the Building Commission at 325 South Oak Street, and improvement location permits by Area Planning in the same suite; call (765) 584-0275 or (765) 584-8610 for a record or a copy.
Inspections are where schedules slip.
Get a free quote →- Randolph County Building Commission
- How to apply for a building permit
- Building permit fee schedule, Ordinance 2024-10
- Non-commercial building permit application (BC-100)
- Commercial building permit application
- Inspection schedule
- Contractor registration
- Contractor registration application
- Recommendations to the homeowner
- Area Planning and Zoning
- Obtaining an improvement location permit
- Improvement location permit application (APC#300)
- Unified Zoning Ordinance, updated March 2026
- Solar ordinance, updated March 2026
- Health Department septic permits
- County Surveyor
- Drainage Board
- Highway Department
Simplify Randolph County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Randolph County sooner?
Let Alliance prepare, file, and track your Randolph County permits while your crew stays on the job.
More Indiana permitting guides
Jay County
Read guide →Wayne County
Read guide →Delaware County
Read guide →Richmond Building Permit Guide
Read guide →Ripley County Building Permit Guide
Read guide →Rush County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Randolph County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.