Inside the City of Richmond, permits come from the Permits and Inspections office of the Department of Infrastructure and Development (765-983-7341), whose department offices are at 50 North 5th Street. Terry Ford is the Building Commissioner. Zoning clearance comes first as an improvement location permit (ILP) under the city’s Unified Development Ordinance, and building, trade and right-of-way permits follow, all filed through BS&A Online. Small projects usually take 5 business days to process and larger ones up to 15, and every new construction or zoning application starts with a pre-planning meeting with staff.
What requires a permit in Richmond?
Richmond uses two layers. The ILP checks zoning and is required before permanent construction, installation, addition, alteration or relocation of a structure, before permanent changes to the land, and before a new land use or a change of use. The building and service permits then cover code work, and the city inspects within its limits for building, heating and air conditioning, air handling, ventilation, electrical, plumbing, water heaters, pools, hoods, fire suppression and extinguishing systems, demolition, footers, foundations and framing.
ILP needed
- A new house or commercial unit, a room addition, a garage, carport or pool house
- Swimming pools, recreation ponds and new driveways
- Decks or patios over 400 square feet
- Any accessory structure over 200 square feet
- New impervious surface, off-street parking, or a change to a building’s height
- Manufactured homes and permanent signs
No ILP (other rules still apply)
- Agricultural accessory structures
- Accessory structures under 200 square feet that are not on a permanent foundation
- Decks or patios under 400 square feet in total on the lot
- Fences, play sets, flag poles and light fixtures
- Landscaping and small accent hardscaping that does not harm drainage
- Maintenance and repairs, which still follow the Chapter 150 building regulations
An ILP exemption is only an exemption from that permit. The work must still meet the UDO, and a building or trade permit may still apply; the online list includes remodel and repair, deck, water heater, plumbing and temporary service permits.
What Richmond decides and what the state holds
The Common Council adopts the UDO, the city code and the fee schedule; the UDO applies to all land within Richmond’s corporate limits. The city code also has its own chapters on housing, floodplain management, historic districts, erosion and sediment control, and stormwater. The state decides which projects are Class 1: the city tells commercial applicants that building and service projects may need a State Construction Design Release and points to 675 IAC 12-6, and no Class 1 construction may start without that release unless the rule exempts the work.
Short on time to read all of this?
Get a free quote →Richmond building department: who handles permitting
The Department of Infrastructure and Development runs planning, zoning, permits and inspections. The Zoning Administrator issues ILPs, and the Building Official reviews projects against the building code. Building code review runs alongside the ILP review, not after it, and the MS4 Coordinator separately reviews stormwater site improvement permits. The UDO applies within Richmond’s corporate limits; for a parcel outside them, check with Wayne County’s planning and building offices.
| Detail | Information |
|---|---|
| Permits and Inspections | 765-983-7341 (permits, inspection requests and pre-planning meetings) |
| Department office | Infrastructure and Development, 50 North 5th Street, Richmond, IN 47374; 765-983-7450 |
| Hours | Monday to Friday, 8:30 a.m. to 4:30 p.m. |
| Building Commissioner | Terry Ford |
| Zoning questions | zoning@richmondindiana.gov |
| Online filing | BS&A Online (homeowners and registered contractors) |
| Code enforcement (housing, trash, weeds) | 765-983-7354 or 765-983-7342 |
Richmond permit types
Online, BS&A takes ILPs, sign ILPs and the building and service permits: building, remodel or repair, accessory structures, additions, decks, water heaters, plumbing, temporary electrical service and curb cuts. Fire suppression, fire alarm and storm water permits (categories 1 to 4) must be filed in person.
Residential permits
- ILP site plan. For a shed or similar structure not on a permanent foundation: a scaled drawing of the lot, the building envelope after setbacks, existing and proposed structures, lot coverage before and after, and an affidavit that the project is not in a floodplain or easement.
- Homes and other inhabitable buildings add mature trees over 9 inches in caliper, the existing ground elevation, drainage tile, utility routes, septic and well locations, adjacent zoning and nearby structures within 50 feet; within 30 feet of a floodplain or wetland, the Planning Director may require an engineer’s or surveyor’s certification.
- Owner-occupant work. A homeowner doing their own electrical or mechanical work files the Owner Occupant Exemption from Electrical License or Mechanical License application with the permit.
- Garages and other buildings on a foundation also show adjoining rights-of-way and street or alley easements, and any easement on or next to the lot with its holder and terms.
- Sewer taps need the city’s sewer tap application attached to the online request.
Not sure this scope needs a permit?
Get a free quote →Temporary uses need a temporary ILP instead: construction trailers, model homes, tent sales and temporary signs. The application can be filed at any time and shows the lot with its setbacks, the temporary structure, how long it will stay, and an affidavit that it will not block drainage, sight lines, traffic, pedestrians or an emergency exit; the fee is paid when you file.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial building and service projects may need the State Construction Design Release, and new or expanding businesses inside the Aquifer Protection Overlay must file an aquifer protection survey. Permanent signs on non-residential property need a Sign ILP. Commercial and residential wrecking permits require proof that every utility is disconnected and, where it applies, IDEM’s asbestos form.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Pre-planning meeting. Required before any new construction or zoning application; call 765-983-7341 to book it.
- ILP and zoning relief. Variances, special exceptions, rezonings, development plans and plats use the city’s zoning application forms; a denied ILP can be revised or taken to the Board of Zoning Appeals within 30 days. The Board of Zoning Appeals meets on the second Wednesday of each month and the Plan Commission on the fourth Wednesday, both at 5:30 p.m.
- Historic districts. Work in a local historic district may need a certificate of appropriateness from the Historic Preservation Commission, which meets at 5:30 p.m. on the second Monday of the month in the third-floor council chambers of the Municipal Building, 50 North 5th Street; the city posts past certificates online.
- Stormwater and erosion control. Most projects also need a stormwater site improvement permit, and any permanent land alteration needs approval under the erosion and sediment control chapter.
- Right-of-way excavation. City Code 96.10, as amended by Ordinance 28-2013, requires a permit for any excavation of any kind in a public right-of-way, which includes streets, alleys, utility easements and trails. The Utility/Permit Coordinator (765-983-7325, streetcut@richmondindiana.gov) handles these permits, and repairs must follow the city’s excavation repair standards. The application needs a blanket or project bond, a certificate of liability insurance, an excavation report and plans for planned construction.
Rather talk it over?
Call 1-855-478-4290 →Richmond permit costs and fees
Under the UDO, the Common Council adopts the city’s fee schedule. The permits page does not print the amounts; it explains how and when you pay instead.
| Fee | How it works |
|---|---|
| Pre-planning and zoning applications | Charged as application fees when the application is submitted; paying does not guarantee the application will be accepted |
| Improvement location permit | Reviewed only once the application is substantially complete and the application fee is paid |
| Building and service permits | Staff call when the permit is ready to be paid for and picked up |
| Right-of-way excavation | Bond (blanket or project-specific) and liability insurance filed with the application |
| Class 1 projects | State design release fees paid to the state, separate from city permits |
Because the amounts are not on the permits page, ask the Permits and Inspections office for the fee on your project at the pre-planning meeting, before you submit. An ILP must be started within 6 months of issue and finished within 36 months, with one extension of up to 12 months; an ILP that misses either deadline becomes void.
Trade permits and who may pull them
Richmond licenses its own trades. Before a contractor can open a BS&A account to apply online, the firm must hold a city license or prove its license with the city.
- Electrical and mechanical contractors must be licensed by the City of Richmond.
- Plumbing contractors register with the city by showing a valid state plumbing license.
- Homeowners may apply online themselves; for their own electrical or mechanical work they file the matching owner-occupant exemption application.
- Linked accounts in BS&A let another user, such as an office manager or permit agent, apply for permits, schedule inspections and view a contractor’s permit history on the contractor’s behalf.
Water heater, plumbing and temporary electrical service permits are on the online list, so a licensed or registered contractor with a BS&A account can request them without visiting the office. Fire suppression and fire alarm permits are the exception: those applications must be filed in person, as must storm water permits in categories 1 to 4.
Rather not deal with the building department?
Get a free quote →How to apply for a Richmond building permit
Call 765-983-7341; it is required for new construction and zoning applications.
Contractors first license or register with the city, then create a BS&A account; homeowners can apply directly.
Upload the site plan and supporting details, and pay the application fee so review can begin.
Apply for the building, remodel, deck, plumbing or other service permits, plus right-of-way, sewer tap and stormwater permits as needed.
The office contacts you if anything is missing; BS&A emails status updates.
Staff call when the permit is ready to be paid for and picked up.
Review, corrections and what causes delay
Applications are first checked for completeness, and an ILP is not reviewed until it is substantially complete and paid. The Zoning Administrator may consult the City Engineer, the Building Commissioner or the parks superintendent and may ask for more detail. Common holdups are a missing floodplain or easement affidavit, an incomplete site plan for a new home, and a contractor without a city license or BS&A account. A denial can be fixed by revising the plan without starting over. After an ILP is issued, the Zoning Administrator may approve a change if something found during construction warrants it and you ask before that part of the work begins.
Inspections in Richmond
Request inspections online through BS&A or by calling Permits and Inspections at 765-983-7341; the city posts step-by-step guides for scheduling online. City inspectors cover footers, foundations, framing, building, heating, air conditioning, air handling, ventilation, electrical, plumbing, water heaters, pools, hoods, fire suppression and extinguishing systems, and demolition within the city limits.
Housing code, trash and tall-weed complaints go to code enforcement, a separate inspection service on 765-983-7354 or 765-983-7342. Right-of-way excavations are tracked so the city can check that each cut is repaired properly and on time.
Indiana building code in Richmond
The city code’s Chapter 150 is Richmond’s building code, and Chapter 153 covers flood hazard areas and floodplain management. FEMA’s Community Status Book lists the City of Richmond (community 180287A) as participating in the National Flood Insurance Program, with its current flood map dated April 2, 2015.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Richmond permit search and official resources
Permit and inspection history lives in BS&A Online: a contractor or owner with an account can view it, and linked accounts can see each other’s records. Zoning and parcel details can be checked on the Wayne County Property Search, and the city code and UDO are posted on the city site. For an older or archived permit record, ask Permits and Inspections at 765-983-7341. Common Council agendas and minutes, organized by year, and the Historic Preservation Commission’s certificates of appropriateness are posted in the city’s online document archive, and Board of Zoning Appeals and Plan Commission meetings can be watched on WCTV.
- Richmond permits and inspections
- Department of Infrastructure and Development
- Planning and zoning
- Zoning applications
- Unified Development Ordinance chapters
- Unified Development Ordinance (full PDF)
- Richmond City Code chapters
- Right-of-way excavations
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Richmond building permit FAQs
Do I need a permit for a deck in Richmond?
A deck or patio over 400 square feet needs an ILP, and decks are on the city’s online building permit list; ask at pre-planning whether a smaller deck needs the building permit.
Does a shed need a permit?
An accessory structure under 200 square feet that is not on a permanent foundation needs no ILP; anything over 200 square feet does.
How long does a Richmond permit take?
Small projects typically take 5 business days to process and larger projects up to 15.
Can a homeowner do their own electrical work?
Yes, with the permit and the city’s Owner Occupant Exemption from Electrical License application; mechanical work has a matching form.
Do contractors need a city license?
Electrical and mechanical contractors must be licensed by the city, and plumbing contractors register with proof of a state license, before opening a BS&A account.
Is a fence permit required?
Fences may be installed or changed without an ILP, but they must still meet the UDO.
Do I need a permit to dig in the street or alley?
Yes. City Code 96.10 requires a right-of-way excavation permit for any excavation in a public way, with a bond, liability insurance and an excavation report.
How long is an ILP good for?
Work must start within 6 months and finish within 36 months; one extension of up to 12 months may be granted.
Simplify Richmond permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Richmond sooner?
Let Alliance prepare, file, and track your Richmond permits while your crew stays on the job.
More Indiana permitting guides
Wayne County
Read guide →Randolph County
Read guide →Henry County
Read guide →Ripley County Building Permit Guide
Read guide →Rush County Building Permit Guide
Read guide →Shelby County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Richmond permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.