Henry County, Indiana Building Permit Guide

To get a building permit in Henry County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Henry County’s Planning & Zoning Department at 1201 Race Street in New Castle issues the combined building and zoning permit for unincorporated land and the towns that use the County Planning Commission; New Castle, Knightstown and four other towns permit their own work.

Authority: Henry County Planning & ZoningSeat: New CastlePhone: 765-529-7408
Authority
Planning & Zoning1201 Race St., Suite 210, New Castle
Own permits
6 municipalitiesIncl. New Castle and Knightstown
Issue time
Up to 10 daysAfter a complete application
Before a permit
Stakes on siteStaff visit; allow 3 days

In unincorporated Henry County, and in the towns that have made the County Planning Commission their planning agency, building permits come from the county Planning & Zoning Department at 1201 Race Street, Suite 210, New Castle (765-529-7408). One Building/Zoning Permit Application covers the building, electrical, HVAC and plumbing permits and the certificate of occupancy, after sign-offs from the Health Department, the County Surveyor and the highway authority. The county says it cannot issue permits inside New Castle, Knightstown, Shirley, Greensboro, Kennard or Cadiz, and allows up to 10 days to issue a permit once an application is complete.

What requires a building permit in Henry County?

The county’s Development Code requires an improvement location permit (ILP) before any structure, improvement or use of land is placed, altered or changed, where its value is $500 or more. Agricultural buildings follow the same permit rules but pay no ILP fee. In practice the county combines the ILP with the building permit on one Building/Zoning Permit Application, and its plot plan rules show which projects it expects to see.

Permit needed

  • New houses, including mobile, modular and manufactured homes
  • Additions, and any work that alters a roofline
  • New accessory structures, such as garages and prefab steel carports
  • Exterior remodeling other than new siding or window installation (plot plan rules)
  • Commercial buildings and their alterations
  • Electrical work, on the county electrical permit
  • Demolition of a building

County sign-offs on the form

  • Health Department or sanitary utility approval
  • County Surveyor drain clearance
  • County or state driveway approval
  • Building inspector review
  • State release for buildings the public or employees use
  • Notice of Assessment Registration for the assessor

The plot plan rules leave out new siding and window installation; for other small jobs, ask the office whether the $500 ILP threshold or a building permit applies. The county also expects every new house, garage, commercial building, carport and driveway to be staked on the ground before a permit can issue.

What Henry County decides and what the state holds

The county controls zoning, plot plan standards, the timing of permits, stormwater rules through its Drainage Board, driveway cuts on county roads and its own fees. The building standards are Indiana’s. Its construction checklist warns that a building employees or the public will use may need a design release from the Indiana Department of Homeland Security, and under state rules such a Class 1 project cannot start construction without one unless the work is exempt. One- and two-family homes are Class 2 and are permitted by the county under its ordinance.

Henry County building department: who handles permitting

The county Planning & Zoning Department, which also signs its inspection notices as the Henry County Department of Building, handles permits and inspections in the county’s jurisdiction. Tom Green is the Zoning Administrator, who issues ILPs under the Development Code. To find out which office covers an address, check whether the parcel is inside a town’s corporate limits using the county’s GIS and maps page, then use the table below.

Short on time to read all of this?

Get a free quote →
Who issues building permits in Henry County’s cities and towns (Census 2025 population in brackets)
PlaceWho permits
Unincorporated Henry CountyCounty Planning & Zoning: ILP, building, electrical, HVAC and plumbing permits and county inspections
Dunreith (172) and Middletown (2,248)County Planning Commission jurisdiction; the code’s jurisdiction table also marks the county building inspector as serving them
Blountsville (95), Lewisville (335), Mooreland (341), Mount Summit (353), Spiceland (961), Springport (136), Straughn (267), Sulphur Springs (337)County Planning Commission jurisdiction (zoning and ILPs); the 2004 jurisdiction table marks no county building inspector, so ask the county office which inspections apply
New Castle (17,390)City Building Commissioner, 227 North Main Street, 765-521-6803; see the New Castle guide
Knightstown (2,165), Kennard (447), Cadiz (162), Greensboro (127)Not the county, which says it cannot issue permits inside these towns; its demolition application lists each town’s office to contact
Shirley (223 in Henry County)Not the county; Shirley straddles the Hancock County line, and the county’s list gives the town’s office address in Greenfield
Henry County permit offices
OfficeDetails
Planning & Zoning / building permits1201 Race Street, Suite 210, New Castle, IN 47362; 765-529-7408; fax 765-521-7072; hcpcpermits@henrycounty.in.gov
Surveyor and Drainage Board1201 Race Street, Suite 216; 765-529-4802
Highway Department202 West County Road 50 North, New Castle; 765-529-4100
Health DepartmentEnvironmental Department: on-site sewage (septic) systems

Henry County permit types

The 2026 permit packet starts with the Building/Zoning Permit Application. It records the parcel, township, zoning, flood zone, setbacks and lot size; whether the site is staked; whether the driveway is new; whether a state release is needed; and the basement, floor, porch and accessory square footage, the estimated cost and the number of rooms, baths and HVAC units. The packet adds the state’s Notice of Assessment Registration and, for homes, the county assessor’s house questionnaire.

Residential permits

  • New homes: site plan and building plans are required; the form also tracks a septic plan, an IDEM Rule 5 plan where applicable, energy ratings and a stormwater pollution prevention plan for new residential work.
  • Manufactured and modular homes: the form asks whether the home is permanent or temporary and its year of manufacture.
  • Additions, garages and carports: a plot plan and building plans; the structure must be staked before the site visit.
  • Electrical: a separate county Electrical Permit for one- and two-family homes, multi-family, commercial, agricultural buildings and repairs, recording the service type and amperage.
  • Demolition: its own application, with utility disconnection letters, a Health Department letter decommissioning any septic system and a licensed driller’s statement that any well is plugged.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial projects use the same application with the commercial box ticked, a state plan release where the building is Class 1, an IDEM Rule 5 plan where one is required and a stormwater pollution prevention plan for new commercial work. The County Surveyor and Drainage Board review the drainage plans and charge their own review fee, and a major commercial driveway on a county road needs a $150 Highway Department permit.

What comes before the building permit

  • Zoning check. Ask Planning & Zoning about restrictions, covenants or zoning on the site.
  • Septic. The Health Department’s Environmental Health division handles septic systems; the permit, the septic worksheet and a photo of the flagged septic layout must reach the planning office before construction starts.
  • Driveway. A Henry County Highway Department permit for a county road; the state highway department’s Greenfield district for a state highway.
  • Drainage. County Surveyor drain clearance; under the county stormwater ordinance the lowest entrance of a house must be at least 2 feet above the adjacent road, and a 2025 resolution keeps drainage pipe outlets at least 25 feet from property lines.
  • Address. An emergency 911 address request, filed with the application when needed.
  • Staking. Since August 1, 2023 the county visits each staked site before issuing building permits; allow at least 3 days after you report that the stakes are set.

Henry County permit costs and fees

The county does not post its building, electrical or ILP fee amounts online. Its Development Code says filing fees are set by Planning Commission rule and posted in the Planning Commission office, the application has separate fee lines for building, electrical, HVAC, plumbing and the certificate of occupancy, and government agencies pay no ILP fee. The fees the county does publish come from the Surveyor, the Drainage Board and the Highway Department.

Rather talk it over?

Call 1-855-478-4290 →
Published Henry County development fees
ItemFee
Surveyor/Drainage Board review: single-family residence$200
Surveyor/Drainage Board review: multi-family or condominium$250 per building
Commercial or industrial development$1,000 + $10 per acre
Minor subdivision / major subdivision$250 / $500 + $15 per lot
Amendment to a recorded plat, or re-plat$250
Outside engineering reviewActual cost, billed through the Surveyor
Private driveway on a county road$50 (valid 1 year)
Minor / major commercial driveway$75 / $150 (valid 45 days)
Utility work, or open cut in the right-of-way$75 / $50
Credit card payments (demolition application)3% bank service charge

The Surveyor and Drainage Board fees come from Ordinance 2024-08-12 (007), adopted by the Board of Commissioners on August 14, 2024, and must be paid before a permit for development is issued. The driveway and road-cut fees are printed on the Highway Department’s right-of-way permit form, payable to the Henry County Highway Department. Demolition permits are final and the county gives no refunds. For a new house, budget the county building, trade and certificate of occupancy fees (ask 765-529-7408 for the current amounts), the $200 Surveyor review and, on a county road, a $50 driveway permit.

Trade permits and who may pull them

Electrical, HVAC and plumbing permits are lines on the same Building/Zoning Permit Application in the county’s jurisdiction, and stand-alone electrical work uses the county Electrical Permit form, addressed to the Planning & Zoning office. The application lists a general, electrical, HVAC and plumbing contractor for each job, each with a space for a registration number, and the construction checklist asks that the name, address and phone of every contractor be attached to the plans or site plan.

  • Plumbing: Indiana licenses plumbing contractors through the Indiana Plumbing Commission.
  • Electrical and HVAC: Indiana issues no license for these trades; the county’s forms ask for each contractor’s registration number, so ask the office how to register before the first job.
  • Wells and septic: abandoned wells must be plugged by a licensed water well driller or pump installer, and septic work goes through the Health Department.
  • Inside the six self-permitting towns: their own rules apply; New Castle, for example, licenses and registers trade contractors under its own ordinance.

Rather not deal with the Henry County building department?

Get a free quote →

How to apply for a Henry County building permit

1. Confirm the county has jurisdiction

Check the parcel is not inside New Castle, Knightstown, Shirley, Greensboro, Kennard or Cadiz.

2. Get the outside approvals

Septic permit from the Health Department, driveway permit from the county highway department or INDOT, and any state design release.

3. Draw the plot plan

Follow the April 23, 2026 plot plan rules: scale 1 inch = 20 or 40 feet, at least 11 by 17 inches, two copies, with GPS-based elevations.

4. Complete the packet

Application, building plans (a digital file or a full-size copy to scan), 911 address request and the assessment notice.

5. Stake the site

Stake the structure and driveway, tell the zoning office, and allow 3 days for the site visit.

6. Collect the permit

Pay the fees and receive the permit before work starts.

Review, corrections and what causes delay

Planning & Zoning reviews an application for completeness within 16 working hours, and it is not treated as submitted until every required item is in; from then, issuing the permit can take up to 10 days. If staff find information missing after filing, the submission date is reset to the day the missing item arrives. A written request to leave something off the plot plan needs 5 working days for review. Staff do not make site visits on weekends, Mondays or holidays, and the lowest-entrance elevation rule may call for a certified surveyor.

Inspections and certificates in Henry County

Call the Building Inspector’s office at 765-529-7408 to arrange inspections. The county’s notice to homeowners and builders warns that a footing or hole poured before it is inspected will have to be torn out for inspection, and every inspection must be completed and documented before a certificate of occupancy is issued. A temporary permit may be allowed in special or unforeseen circumstances.

Under the Development Code, work under an ILP must start within six months or the permit lapses, and it must be finished within 18 months unless the Zoning Administrator extends the time for good cause. No new or altered building may be used until the certificate of occupancy is issued. For demolition, the lot must be filled with clean fill to the existing grade and seeded, and debris must go to a licensed disposal facility.

Indiana building code in Henry County

The county enforces the state building rules through its Planning & Zoning office and building inspector in its own jurisdiction. FEMA’s Community Status Book lists unincorporated Henry County (community 180437A) as participating in the National Flood Insurance Program, with flood maps effective March 2, 2015; the permit application asks for the flood zone of every parcel. Towns take part in the flood program separately.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Want this handled start to finish?

Get a free quote →

Henry County permit search and official resources

The Development Code makes every ILP issued by the county a public record kept in the Zoning Administrator’s office, so ask Planning & Zoning at 765-529-7408 or hcpcpermits@henrycounty.in.gov for past permits on a parcel. Permits inside New Castle and the other self-permitting towns are held by those towns.

Inspections are where schedules slip.

Get a free quote →

Henry County building permit FAQs

Does Henry County issue permits in New Castle?

No. The county says it cannot issue permits inside New Castle, Knightstown, Shirley, Greensboro, Kennard or Cadiz. In New Castle the city’s Building Commissioner issues them.

How long does a county permit take?

Completeness review within 16 working hours, then up to 10 days to issue once the application is complete, plus at least 3 days for the staking visit.

Do I need a septic permit first?

Yes, where the site uses a septic system. The Health Department permit, the septic worksheet and a photo of the flagged layout go to the planning office before construction.

How much is a driveway permit on a county road?

$50 for a private driveway, $75 for a minor commercial and $150 for a major commercial driveway, from the Highway Department.

How high must a new house sit?

Under the county stormwater ordinance, the lowest entrance must be at least 2 feet above the road next to the house, shown with GPS-based elevations.

Do agricultural buildings need a permit?

The Development Code applies its permit requirements to agricultural buildings but exempts them from the ILP fee.

How do I book an inspection?

Call 765-529-7408, and never pour footings before the hole is inspected.

Simplify Henry County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Henry County sooner?

Let Alliance prepare, file, and track your Henry County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Henry County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.