Inside the City of New Castle, building permits come from the Building Commissioner’s office at City Hall, 227 North Main Street (765-521-6803, weekdays 8 a.m. to 4 p.m.), headed by Building Commissioner Kenny Melton. The office reviews plans, issues building, structural and trade permits, inspects the work, licenses and registers trade contractors under City Ordinance #2864 and serves as the local floodplain administrator. The Unified Development Ordinance in force since February 3, 2025 sets the permit rules, and the posted fee schedule charges $0.30 per square foot of floor area for new buildings, additions and alterations, plus $55 for each inspection.
What requires a building permit in New Castle?
New Castle’s UDO casts a wide net. A building permit is required to erect, construct, install, move, add to or alter any structure unless the UDO says otherwise, and the ordinance names many items that owners often assume are too small to matter. Every accessory structure needs one regardless of size, and so does every paved area.
Building permit required
- New primary structures, additions and alterations
- Accessory structures of any size: pole barns, decks, detached garages, carports, enclosed patios, storage sheds, gazebos and greenhouses
- Above-ground and in-ground pools, bath houses and cabanas
- Accessory solar and wind systems
- Fences and walls, and signs
- Driveways, slabs, parking areas and other paved areas
- Temporary uses and structures, construction trailers and temporary storage containers
- Fully enclosed play structures and treehouses
No building permit (UDO 4.8 F)
- Landscape planting
- Swing sets, play sets and treehouses that are not enclosed and have no roof
- Basketball poles
- Bird baths, lamp posts, mailboxes, name plates and pet housing that is not a kennel
- Cable, fiber and Wi-Fi service installations (not solar or wind)
- Ponds and drainage installations
- Retaining walls
Exempt items still have to meet every UDO standard. Electrical and plumbing work without construction, such as a temporary pole, a change of service, a new HVAC unit or a water heater, is priced on the fee schedule’s “other structures” scale, which starts with jobs of $500.
What New Castle decides and what the state holds
The city sets its own zoning, design and historic rules, licenses trade contractors and enforces the Uniform Housing Code against unsafe or substandard homes. The building codes are the state’s, and the UDO will not let the city issue a commercial or industrial building permit until the state approvals are in hand, including a state Construction Design Release for buildings used by the public or employees. A house or duplex is a Class 2 structure, permitted by the city under its own ordinance.
Short on time to read all of this?
Get a free quote →New Castle building department: who handles permitting
The UDO gives the Administrator, appointed by the Plan Commission, the job of issuing building permits and certificates of occupancy and keeping every permit as a public record, and the city’s Building Commission page says its Building Department reviews plans and issues the permits. Its staff handle permits and inspections, planning and zoning, variance applications and code enforcement. Henry County’s Planning & Zoning office says it cannot issue permits inside the city, so permits for land inside the corporate limits come from the city.
| Detail | Information |
|---|---|
| Office | Building Commissioner, City Hall, 227 North Main Street, New Castle, IN 47362 |
| Building Commissioner | Kenny Melton, 765-521-6803 |
| Permits, inspections, zoning | 765-521-6823 |
| Hours | Monday to Friday, 8 a.m. to 4 p.m. |
| Board of Zoning Appeals | 765-529-7605; 6 p.m. on the second Thursday, City Hall Council Chambers, second floor |
| Plan Commission | 6 p.m. on the third Wednesday, City Hall Council Chambers |
New Castle permit types
The fee schedule sorts permits into licenses and occupancy, inspections and plan review, site improvements and structures, which is a practical map of what the office issues.
Residential permits
- New homes, additions and alterations: charged by the square foot of floor area under roof, plus inspections.
- Accessory buildings: garages, sheds and pole barns use the same building permit; there is no size exemption.
- Fences and walls: 4 feet maximum in front yards and 6 feet in side and rear yards in the residential districts; at least 5 feet from any public right-of-way; not in easements without the holder’s approval; on a property line only with the neighbor’s written approval, otherwise 3 feet back.
- Pools: rear yard only, at least 10 feet from side and rear lines, inside a fence at least 4 feet tall with a locking gate, and built to the state swimming pool code.
- Driveways and slabs: a curb cut and paved-area permit.
- Manufactured homes: placement on an individual lot is a single permit with the inspection included.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial, industrial, institutional and multi-family projects pay a $150 plan review fee on top of the square-foot building fee. Signs, temporary uses and storage containers have their own permits, and industrial fences may be 8 feet tall. In the Downtown Core district and the Downtown Gateway Overlay District, every primary and accessory structure needs a certificate of appropriateness from the New Castle Historic Preservation Commission, and fences there follow the Historic District Guidelines. In the Downtown Core the certificate must come before a development plan application or any city permit for new structures, exterior changes and demolition, and an addition taller than one story or 15 feet needs the commission’s approval. The Redevelopment Commission offers facade grants and takes a historic preservation certification application.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. Variances and special exceptions go to the Board of Zoning Appeals; rezonings, plats and development plans to the Plan Commission, which advises the City Council. Each board has an application packet on the city website.
- Septic. A parcel served by a septic system needs a permit from the Henry County Health Department, IDEM or the Health Officer before the building permit.
- Erosion control. A project disturbing more than one acre must submit erosion and sediment control plans under the state construction stormwater general permit to the city’s MS4 Coordinator first.
- Platted lots. Public infrastructure must be built and the secondary plat recorded.
- Floodplain. Development in the Floodplain Overlay District must meet the city’s Flood Hazard Ordinance, administered by the Building Commissioner with the Indiana Department of Natural Resources.
New Castle permit costs and fees
The Building Commission page posts one fee schedule covering building permits and Plan Commission and BZA applications; the document names no adopting ordinance or date. Under the UDO, building permit fees are worked out during review and collected when the permit is issued, re-inspection fees are due before the final inspection or certificate of occupancy, and fees are non-refundable.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New building, addition or alteration (primary or accessory) | $0.30 per sq ft of floor area under roof, $100 minimum, plus inspections |
| Inspections: structure, electric, plumbing, HVAC | $55 each |
| Re-inspections | $55 first; $110 second; $220 third and later |
| Commercial, industrial, institutional and multi-family plan review | $150 |
| Pool, fence or wall, cell tower, or electric or plumbing work without construction | $500–$1,000 job: $20; $1,001–$1,499: $35; $1,500 or more: $35 + $4 per $1,000 over $1,500; each plus inspections |
| Demolition | $0.01 per sq ft, $30 minimum |
| Curb cut and paved areas | $3 per sq ft, $40 minimum |
| Certificate of occupancy | $40 single or two-family; $70 all other |
| Manufactured home placement, individual lot | $800, inspection included |
| Contractor license | $90 first application; $30 plumbing; $30 each additional trade |
| Building early or without a permit (signs included) | $50 first offense; $100 second; $2,500 third |
| Development standards variance | $200 (residential, agricultural, accessory) or $400 (other uses) per variance |
Worked example: a new house with 2,000 square feet under roof is 2,000 × $0.30, or $600, for the building permit, plus $55 for each inspection the job needs and $40 for the certificate of occupancy. A $9,500 fence falls in the $1,500-or-more band: $35 plus 8 × $4 for the $8,000 above $1,500, or $67, plus inspections. A new driveway’s paved area is charged separately at $3 a square foot.
Trade permits and who may pull them
New Castle tests, licenses and registers all trade contractors who work inside city limits under City Ordinance #2864, administered by the Building Commissioner’s office. The fee schedule charges $90 for a contractor’s first professional license application, $30 for plumbing and $30 for each additional trade. Electric, plumbing and HVAC work on a building project is inspected at $55 an inspection; stand-alone jobs such as a temporary pole, a change of service, a new HVAC unit or a water heater use the “other structures” permit scale.
- Plumbing: plumbing contractors also need the state license issued through the Indiana Plumbing Commission, and the city’s fee schedule has a separate plumbing license line.
- Electrical and HVAC: Indiana has no state license for these trades; the city’s licensing and registration covers them.
- Owners: the city’s published pages do not describe a homeowner exemption from contractor licensing, so ask the office at 765-521-6823 before doing your own trade work.
Rather not deal with the building department?
Get a free quote →How to apply for a New Castle building permit
Henry County handles land outside the corporate limits.
Find the zoning district, setbacks and fence heights in the UDO, and whether the site is downtown or in the floodplain overlay.
BZA or Plan Commission decisions, a historic certificate of appropriateness downtown, septic or state approvals where needed.
Each trade contractor must be licensed or registered with the city.
The city website posts no building permit form, so call the permits staff at 765-521-6823 or visit City Hall, 227 North Main Street.
Fees are collected when the permit is issued.
Review, corrections and what causes delay
The Plan Commission and BZA fee schedule lets an applicant resubmit missing information or a non-compliant site plan three times free; the fourth and later resubmittals cost $150 each, and extra public notice signs are $20. Board meetings can be cancelled in months with no petitions or business. A permit is valid for one year, and amendments to an approved permit can add fees. Starting work or moving in without a permit costs $50 the first time, $100 the second and $2,500 the third.
Inspections and certificates in New Castle
The Building Commissioner’s office carries out mandatory field inspections on new construction, renovations and structural repairs, and electric, plumbing and HVAC work is inspected separately at $55 a visit. A failed inspection costs $55 to re-inspect the first time, $110 the second and $220 after that. The permits and inspections staff answer at 765-521-6823.
The Administrator issues a certificate of occupancy only after all work is complete, including site improvements, and after any required driveway has been installed and inspected. The certificate states that the use conforms to the UDO and that the property has been inspected; it costs $40 for a single-family or two-family home and $70 for anything else. Construction trailers are allowed for 12 months, with one 12-month renewal.
Indiana building code in New Castle
New Castle enforces the state building codes through its Building Commissioner, and the UDO adopted on January 21, 2025 governs zoning and permits. FEMA’s Community Status Book lists the City of New Castle (community 180092A) as participating in the National Flood Insurance Program, with flood maps effective March 2, 2015, and the city’s Floodplain Overlay District follows the flood hazard areas on the state’s best available floodplain mapping.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
New Castle permit search and official resources
The UDO requires the Administrator to keep a permanent file of all permits and applications as public records. To see permits, plans or certificates for a property, file the city’s Public Records Request form, posted on the city home page, or ask the Building Commissioner’s office. Plan Commission and BZA minutes are on the city’s agendas and minutes page.
- New Castle Building Commission
- Building permit and PC/BZA fee schedule
- New Castle Unified Development Ordinance (2025)
- Board of Zoning Appeals application packet
- Plan Commission application packet
- Historic preservation certification application
- Agendas and minutes
- Public Records Request form
- Henry County Planning Department (outside city limits)
- IDHS building plan review (Construction Design Release)
- Fire Prevention and Building Safety Commission rules
- Indiana Plumbing Commission
Inspections are where schedules slip.
Get a free quote →New Castle building permit FAQs
Do I need a permit for a shed in New Castle?
Yes. The UDO requires a building permit for every accessory structure regardless of size, including storage sheds, decks and carports.
How much is a permit for a new house?
$0.30 per square foot of floor area under roof, at least $100, plus $55 per inspection; a 2,000-square-foot house is $600 before inspections and the $40 certificate of occupancy.
Does a fence need a permit?
Yes. Residential fences may be 4 feet in front yards and 6 feet in side and rear yards, and the permit fee depends on the project cost, starting at $20.
Do contractors need a city license?
Yes. Trade contractors are tested, licensed and registered by the city under Ordinance #2864; the first application is $90.
Does Henry County issue permits in New Castle?
No. The county says it cannot issue permits inside the city; the Building Commissioner does.
When does the Board of Zoning Appeals meet?
At 6 p.m. on the second Thursday of the month at City Hall, unless there are no petitions; a residential development standards variance is $200.
Do I need a permit for a driveway?
Yes. Paved areas need a building permit, charged at $3 a square foot with a $40 minimum.
Simplify New Castle permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in New Castle sooner?
Let Alliance prepare, file, and track your New Castle permits while your crew stays on the job.
More Indiana permitting guides
Henry County
Read guide →Delaware County
Read guide →Wayne County
Read guide →Newton County Building Permit Guide
Read guide →Noble County Building Permit Guide
Read guide →Owen County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about New Castle permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.