Building permits for unincorporated Newton County come from the Newton County Building Department, 4117 S 240 W, Suite 700, Morocco (219-285-6080, ncbuilding@newtoncounty.in.gov, weekdays 8 a.m. to 4 p.m.), which also enforces the county zoning ordinance and fields questions for the Plan Commission and Board of Zoning Appeals. Its application form prices a house at 20 cents per square foot with a $200 minimum and $400 maximum, and anyone other than the owner doing the work must be a contractor registered with the county under Ordinance 96-4.
What requires a building permit in Newton County?
Newton County’s rule is set by size and cost rather than by a long list of project types. Building Code Ordinance 94-2 requires a permit before constructing or altering any building or structure over 160 square feet, and the department’s page sets the repair threshold.
Permit required
- New houses, manufactured and mobile homes, and multi-family buildings
- Additions, remodels, garages, pole barns and other accessory buildings over 160 square feet
- Commercial buildings and towers
- Electrical services, and swimming pools (the ordinance covers pools over 4 feet deep)
- Signs larger than 4 square feet
- Demolition, which is a permit type on the application
- Repair and maintenance above the cost threshold
No permit
- Structures of 160 square feet or smaller
- Repair and maintenance such as roofing and siding that costs no more than $10,000, according to the department’s page
The two posted figures for repairs differ: the department’s page exempts repair and maintenance up to $10,000, while the text of Ordinance 94-2 on the county site sets the line at $5,000. No later amending ordinance is posted, so ask the department which figure it applies before you skip a permit on a re-roof or re-side.
What Newton County decides and what the state holds
The county adopts the state Fire Prevention and Building Safety Commission’s rules by reference in Ordinance 94-2 and enforces the structural, HVAC, electrical, plumbing, sanitation, swimming pool and sign codes through one department. Its own choices are the 160-square-foot threshold, the fees, contractor registration under Ordinance 96-4, the zoning ordinance (Ordinance 94-1) with districts A, R-1, R-1A, R-2, RMH, RMHA, MXD, B-1, B-2, I-1 and I-2, and the flood hazard ordinance (Ordinance 93-8). A Class 1 project must bring a copy of the state design release before the county issues the permit, and the application has a box for its number.
Newton County building department: who handles permitting
The Building Department’s duties are reviewing and issuing residential and commercial building permits, inspecting new construction and alterations, enforcing zoning, and overseeing animal control and the animal shelter. Its permits run under the county Building Commissioner, who may take legal action on violations at the applicant’s expense. The Plan Commission and Board of Zoning Appeals pages send all questions to this department.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Building Department | 4117 S 240 W, Suite 700, Morocco, IN 47963; 219-285-6080; fax 219-285-8304; ncbuilding@newtoncounty.in.gov; Monday to Friday 8 a.m. to 4 p.m. |
| Health Department (septic, wells, soil and water tests) | Same building; 888-663-9866 ext. 2200, or 219-285-2052 ext. 2203 for the environmental specialist |
| Highway Department (driveways) | 3640 S 275 W, Morocco; 219-285-2595; weekdays 6 a.m. to 2 p.m. from November to March, Monday to Thursday 6 a.m. to 4 p.m. from April to October |
| Surveyor and Drainage Board | 310 N Seventh Street, Kentland; 219-474-3101 |
| Recorder (contractor bonds) | 888-663-9866 ext. 1401 |
Towns in Newton County
Ordinance 94-2 is written for the unincorporated areas. The county has five towns: Kentland, Morocco, Goodland, Brook and Mount Ayr. The published sources do not say who issues building permits inside them, and Kentland’s and Goodland’s town websites carry no permit page. Ask the town office first: Kentland Town Hall is at 300 N. Third Street (219-474-5062) and Goodland’s office at 110 N. Benton Street (219-297-4841); for Morocco, Brook and Mount Ayr, call the county department to confirm which office covers the parcel. The county GIS (Beacon) shows each parcel’s zoning and history.
Newton County permit types
One application form covers every type: conventional houses, multi-family, manufactured and mobile homes, additions, remodels, garages, pole barns, accessory buildings, commercial buildings, demolition, pools, signs, electric and towers. It asks for the zoning district, township, parcel and tax ID numbers, whether the site is in a flood plain, the septic and well permit numbers, building dimensions and materials, the electrical service size, heating and fixture counts, setbacks and every contractor by trade with a county registration number. The county also links an online “Building Permit / Contractor Reg. Application” through its GeoPermits portal.
Residential permits
- Houses and additions need footing and foundation plans, floor plans, a cross section, and the manufacturer’s specifications for any engineered trusses or floor joists.
- Site plan or plat of survey with full lot dimensions, every improvement, and labeled distances to property lines, septic system, well and other buildings.
- Pools must meet the state pool safety rules on handholds and access: a wall or fence at least 4 feet high with self-closing, latching gates, a power safety cover, or another approved barrier, all in place at final inspection.
- Agricultural zoning sets a house’s minimum ground floor at 960 square feet, maximum height at 30 feet and minimum lot at one acre (43,560 square feet), with a 35-foot front setback (100 feet on a state or federal highway), 10-foot side yards and ponds kept 35 feet from every line.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial buildings are figured at 40 cents per square foot within a $400 minimum and $1,000 maximum, and each inspection on a commercial or multi-family job adds $30, payable at the final. The fire chief helps the department inspect fire suppression, detection and alarm systems. Towers, wind turbines, meteorological towers and signs have their own county ordinances, and the department has posted a proposed zoning text amendment on large solar and wind projects, which remains a proposal until the Commissioners adopt it.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The department checks the lot’s district and setbacks; a change of land use, variance or special exception goes to the Plan Commission or BZA, which meet on the third Tuesday at the Government Center (Plan Commission 6 p.m., BZA 7 p.m.), with the plat committee on the second Tuesday at 6:30 p.m.
- Septic and well. A new house on a vacant lot needs Health Department septic and well permits, with soil and water tests.
- Driveway. A new structure on a vacant lot needs a driveway permit from the Highway Department, which maintains the county’s more than 660 miles of road outside the towns.
- Drainage. The Surveyor is the technical authority for regulated drains, and the Drainage Board, made up of the three Commissioners, rules on them.
- Floodplain. Ordinance 93-8 governs building in flood hazard areas, and for new construction and substantial improvements the permit review checks that the site will be reasonably safe from flooding.
Newton County permit costs and fees
The fees below are printed on the Building Department’s updated application form. The copy of Building Code Ordinance 94-2 posted beside it still shows an older, lower scale (10 cents per square foot and a $15 re-inspection fee), and no amending fee ordinance is posted, so confirm the figure when you file; the department collects the fee on the form.
Rather talk it over?
Call 1-855-478-4290 →| Permit | Fee |
|---|---|
| Single-family dwelling | $0.20 per sq ft; minimum $200, maximum $400 |
| Manufactured home | $0.20 per sq ft; minimum $200, maximum $400 |
| Mobile home | $0.20 per sq ft; minimum $100, maximum $200 |
| Addition or remodel | $0.20 per sq ft; minimum $100, maximum $200 |
| Garage or post-frame building | $0.20 per sq ft; minimum $100, maximum $200 |
| Accessory building | $0.20 per sq ft; minimum $50, maximum $100 |
| Multi-family dwelling | $100 per unit, plus $30 per inspection |
| Commercial building | $0.40 per sq ft; minimum $400, maximum $1,000, plus $30 per inspection |
| Electric | $50 |
| Swimming pool | $100 |
| Sign larger than 4 sq ft | $100 |
| Re-inspection of work not ready | $30 |
| Change of land use / variance / special exception | $200 / $150 / $150 |
| Subdivision / minor subdivision | $200 / $100 |
| Contractor registration (Ordinance 96-4) | $50 a year, renewed each January 1 |
Worked example from the form: a 1,600-square-foot house is 1,600 × $0.20 = $320, which sits between the $200 minimum and $400 maximum, so the permit is $320. Any house of 2,000 square feet or more reaches the $400 cap. A 2,400-square-foot pole barn would figure at $480 but is capped at $200. Contractors on the job must also hold the $50 yearly registration, with a $5,000 bond on first registration.
Trade permits and who may pull them
Newton County puts the trades on the building permit: one application lists the general, electrical, plumbing and mechanical contractors, each with a county registration number, and the department enforces the electrical, plumbing and HVAC codes on it. A stand-alone electrical job is a $50 electric permit.
- Contractor registration (Ordinance 96-4). No contractor or specialty contractor may build, alter, repair or demolish without a county registration certificate. Registration costs $50 a year, renewed every January 1, and needs a $5,000 bond on first registration, filed with the Building Department (bonds no longer have to be recorded), plus a certificate of insurance for at least $500,000 per occurrence or $1,000,000 aggregate, including workers’ compensation. The department posts a monthly list of registered contractors.
- Owners. An owner or occupant of a one- or two-family dwelling doing their own work is exempt from registration, but any contractor or subcontractor the owner hires must be registered. Licensed architects and engineers are also exempt.
- Plumbers. Each permit with plumbing needs the notarized Plumbing Contractor Permit Affidavit, giving the state plumbing license number and signed only by the license holder.
Rather not deal with the Newton County building department?
Get a free quote →How to apply for a Newton County building permit
Look up the zoning district and whether the lot is in a town or a flood area on the county GIS.
Every contractor on the job registers with the county, posting the bond and insurance certificate.
From the Health Department and the Highway Department for a new building on a vacant lot.
Footing, foundation, floor plans, cross section, truss and joist specifications, and a dimensioned site plan.
Submit the updated permit application, plumbing affidavit and plans at the department or through the county’s online link.
Pay the fee figured on the form and keep the permit on site.
Review, corrections and what causes delay
Applications stall on an unregistered subcontractor, a missing septic or well permit, a site plan without setback distances, and a Class 1 project without its state design release number. Zoning relief waits for the monthly Plan Commission or BZA meeting, whose dates the county says may change, and a month may have no agenda. Since January 1, 2026 state law requires a unit that permits one- and two-family work to review the plans within 7 business days.
Inspections and certificates in Newton County
The permit holder must call the department during working hours at least 24 hours before each inspection, and Ordinance 94-2 asks the department to finish an inspection within 16 working hours of the request. The required stages are printed on the back of the application:
- Footing pre-pour, after excavation and forms and any rebar, before concrete
- Foundation, before backfill, to check damp-proofing, drain tile and anchor bolts
- Rough-in, after framing, electrical and plumbing, before insulation
- Insulation, before drywall
- Final, before occupancy
Work that is not ready when the inspector arrives carries a $30 re-inspection fee. No building may be occupied until the Building Commissioner issues a full, partial or temporary certificate of occupancy, and the department links a “What’s Needed for a Certificate of Occupancy” sheet from its page. Pools must have every required safety item in place at the final.
Indiana building code in Newton County
Ordinance 94-2 adopts the state building, residential, plumbing, electrical, mechanical, energy and swimming pool rules by reference, including later amendments as they are published. FEMA’s Community Status Book lists unincorporated Newton County (community 180179) as taking part in the National Flood Insurance Program, with flood maps effective December 16, 2014.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Newton County permit search and official resources
Ask the Building Department at 219-285-6080 or ncbuilding@newtoncounty.in.gov for a permit, inspection or occupancy record, and check its monthly list of registered contractors before hiring. Ordinances, forms, agendas and minutes are in the county’s online document center.
- Newton County Building Department
- Building permit application with fee schedule
- What’s needed for a residential building permit
- GeoPermits: building permit and contractor registration
- Building Code Ordinance 94-2
- Contractor Registration Ordinance 96-4
- Plumbing contractor permit affidavit
- Swimming pool permit requirements
- Zoning and lot use tips
- 2026 Plan Commission and BZA meeting schedule
- Building Department ordinances list
- Newton County Health Department
- Newton County Highway Department
- Newton County Surveyor
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Newton County building permit FAQs
Do I need a permit for a small shed in Newton County?
Not if it is 160 square feet or smaller; anything larger needs a permit.
How much is a permit for a new house?
20 cents per square foot, with a $200 minimum and a $400 maximum, so a 1,600-square-foot house is $320.
Can a homeowner do the work without a registered contractor?
Yes, on a one- or two-family dwelling they own or occupy; anyone they hire must be registered with the county.
What does contractor registration cost?
$50 a year, plus a $5,000 bond on first registration and proof of liability and workers’ compensation insurance.
Do I need a permit to re-roof or re-side?
Not for repair and maintenance under the cost threshold: $10,000 on the department’s page, $5,000 in the posted ordinance text.
How much notice does an inspection need?
At least 24 hours, by calling the department during working hours.
When do the Plan Commission and BZA meet?
Both on the third Tuesday of the month at the Government Center, the Plan Commission at 6 p.m. and the BZA at 7 p.m.
Simplify Newton County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Newton County sooner?
Let Alliance prepare, file, and track your Newton County permits while your crew stays on the job.
More Indiana permitting guides
Jasper County
Read guide →Lake County
Read guide →Morgan County
Read guide →Noble County Building Permit Guide
Read guide →Owen County Building Permit Guide
Read guide →Parke County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Newton County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.