Skip to main content

Morgan County, Indiana Building Permit Guide

To get a building permit in Morgan County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Morgan County Planning and Zoning Department in Martinsville issues improvement location permits, which serve as building permits, for unincorporated Morgan County and the towns of Bethany, Brooklyn and Paragon.

Authority: Morgan County Planning & ZoningFees: Schedule effective Feb. 1, 2022Phone: 765-342-1060
Authority
Planning & Zoning180 S Main St, Suite 204
New house
$200 basePlus $0.10/sq ft over 1,500 sq ft
Sheds
No permit to 200 sq ftUnless on a permanent foundation
Hours
Mon–Fri 7:30–4Closed noon to 1 p.m.

In Morgan County, the Planning & Zoning Department, Suite 204 at 180 South Main Street in Martinsville (765-342-1060), issues the improvement location permit (ILP), which the county’s Unified Development Ordinance says is also the building permit, and carries out the inspections. Laura Parker is Director. The department covers unincorporated land and the towns of Bethany, Brooklyn and Paragon; Martinsville, Mooresville, Monrovia and Morgantown handle their own zoning. Applications go through the online GeoPermits portal, and a new house costs $200 plus $0.10 a square foot over 1,500 square feet under the fee schedule effective February 1, 2022.

What requires a building permit in Morgan County?

Chapter 7 of the Unified Development Ordinance (UDO) requires an ILP, also known as a building permit, to put up, alter or modify any structure in the county’s jurisdiction. No building may be erected, moved, added to or structurally altered until the Plan Commission office issues it.

ILP / building permit required

  • Primary buildings: houses, manufactured and multi-family homes, commercial and industrial buildings
  • Additions and remodels of a primary structure
  • Accessory buildings over 200 square feet, and any accessory structure on a permanent foundation, whatever its size
  • Accessory dwelling units
  • Electrical, plumbing and HVAC work, pools and new or wider driveways
  • Signs, temporary storage containers and wireless facilities
  • Demolition and parking lots (commercial schedule)

No ILP needed

  • Accessory structures of 200 square feet or less without a permanent foundation
  • Fences, trellises, retaining walls, walks and ponds
  • Concrete slabs, patios and paved sports courts
  • Swing sets, treehouses and play structures (not in the front yard)
  • Landscaping, lamp posts, mailboxes and drainage installations
  • Home cable, fiber and Wi-Fi lines (solar and wind excluded)

Exempt items must still meet the accessory structure standards, including setbacks, and may not sit in an easement. An accessory building that does need a permit must stand at or behind the front facade of the house unless the UDO allows otherwise. A temporary use permit covers construction trailers, tents and similar uses for up to 90 days or the length of construction, whichever is longer.

What the county decides and what the state holds

The county adopted its UDO by Ordinance 2021-21 and sets its own fees, technical design standards and thoroughfare plan; the department also administers floodplain protections and assigns addresses. Commercial and industrial ILPs are issued only after any required state approvals, such as the state Construction Design Release for Class 1 buildings.

Morgan County building department: who handles permitting

The Planning & Zoning Department issues ILPs and building permits, inspects the work, enforces zoning and development standards and staffs the Plan Commission, Board of Zoning Appeals and Design Review Board.

Short on time to read all of this?

Get a free quote →
Morgan County permit contacts
OfficeDetails
Planning & Zoning Department180 S Main St, Suite 204, Martinsville, IN 46151; 765-342-1060; fax 765-342-1091
HoursMonday to Friday 7:30 a.m. to 4 p.m., closed noon to 1 p.m.
OnlineGeoPermits portal for building permit applications
Plan Commission6:30 p.m., second Monday of the month; nine members: the County Surveyor, County Council and Commissioner representatives, the county agricultural educator and citizen members
Septic permitsMorgan County Health Department, Septic Division
Driveway culvertsInspected by the Morgan County Highway Department before occupancy

Which office covers each city and town

Zoning and permits by community
CommunityWho handles zoning and permits
Unincorporated countyCounty Planning & Zoning Department
Bethany, Brooklyn, ParagonCounty Planning & Zoning Department; the UDO places these towns in the county’s jurisdiction
MooresvilleTown Building Department: permits and inspections under the town’s own rules
Martinsville, Monrovia, MorgantownOutside the county UDO; each runs its own zoning. Ask the city or town office who issues building permits.

Mooresville’s Building Department requires a permit for any project with a permanent foundation and for structural, electrical, HVAC and plumbing projects over 200 square feet, and says a contractor license is not needed to apply. It generally does not permit roofing, siding or window replacement unless roof decking is replaced or a window opening changes size, and needs no permit for fences or temporary structures. Inspections there are called in 48 hours ahead.

Morgan County permit types

Every county permit is an ILP, charged on the residential or the commercial and industrial schedule. Applications go through GeoPermits, together with the application packet the UDO calls for.

Residential permits

  • New houses and additions: a base fee plus a square-foot charge above 1,500 square feet, counting every level, basement, garage, deck and porch.
  • Manufactured homes and relocated dwellings: a flat $200 fee; an ILP for a manufactured home lasts one year.
  • Accessory buildings over 200 square feet: decks, barns and open porches included.
  • Accessory dwelling units: allowed in the AG, RR, R-1 and R-2 districts on a lot with an owner-occupied house under the same ownership; 220 to 800 square feet of living area but no more than half the main house; no taller than 30 feet or the main house; in a side or rear yard; with approved sewage and water and no separate driveway entrance from the road. Short-term rentals do not count, and other districts need a use variance.
  • Trade permits, pools and driveways: electrical, plumbing and HVAC permits, pools and new or expanded driveways each carry their own fee.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

New commercial and industrial buildings are charged at a lower rate per square foot above 500,000 square feet; additions, remodels, accessory buildings and relocations pay a $250 base. Each commercial permit includes 10 inspections, and extra ones cost $50 each. Development plans go to the Plan Commission, which reviews subdivision, development and rezoning petitions in the unincorporated area.

What comes before the building permit

  • Septic. No ILP is issued for a building on a septic system until the Morgan County Health Department has issued a septic permit or approved the system. The Health Department also takes a separate application for remodels, room additions and other changes on septic properties.
  • Subdivision improvements. In a new subdivision, public improvements must be installed and inspected by the County Engineer and the plat recorded before any ILP.
  • State approvals. Commercial and industrial uses need any required state approvals first.
  • Plan Commission and BZA. Rezonings, variances and special exceptions are heard first; Plan Commission rules bar anyone from contacting members to influence their vote before a public hearing.

Morgan County permit costs and fees

The Planning & Zoning Department’s fee schedule is marked effective February 1, 2022. The per-square-foot charge applies to every level, including basements, garages, decks and porches, and houses with basements may owe extra inspection fees.

Residential improvement location permit fees
WorkFee
New one- or two-family dwelling$200 plus $0.10 per sq ft over 1,500 sq ft
New manufactured home / relocation of dwelling$200 / $200
New multi-family dwelling$300 plus $100 per unit
Primary structure addition or remodel$200 plus $0.10 per sq ft over 1,500 sq ft
Accessory structure over 200 sq ft (deck, barn, open porch)$75 plus $0.10 per sq ft over 1,500 sq ft
Electrical / plumbing / HVAC$75 each
Pool, in-ground or above-ground$100
Residential driveway, new or expanded$50

Rather talk it over?

Call 1-855-478-4290 →
Commercial and industrial improvement location permit fees
WorkFee
New construction under 500,000 sq ft$400 plus $0.006 per sq ft
New construction over 500,000 sq ft$400 plus $0.005 per sq ft
Addition or remodel / accessory structure / relocation$250 plus $0.10 per sq ft each
Demolition (per structure)$150
Electrical / plumbing / HVAC$125 each
Commercial pool$150
Commercial or industrial driveway entrance$150 per entrance
Parking lot, new or expanded$50 plus $5 per space over 25
Inspections, penalties and petitions
WorkFee
Additional base inspection$50
Reinspection: 1st / 2nd / 3rd and later$50 / $100 / $200 residential; $100 / $200 / $300 commercial
Work without a permitTwice the permit fee
Temporary construction trailer / storage container$200 / $50
Telecommunications tower: collocation / new$300 / $1,000
Signs$1 per sq ft of sign face, $100 minimum
Rezoning / planned unit development$500 / $1,000 plus $20 per acre
Variance / special exception$400 (plus $50 per additional variance) / $400
Minor subdivision / primary plat / secondary plat$400 / $600 / $400 plus $25 per lot
Zoning verification or research$40 per hour

Rather not deal with the Morgan County building department?

Get a free quote →

Worked example at the schedule’s rates: a house with 2,400 square feet across all levels, garage and porches included, pays $200 plus 900 × $0.10, or $290. The first renewal of a permit costs 25% of the fee for six more months if work has progressed; later renewals without progress pay the full fee, and Plan Commission petitions can also carry outside consultant charges. Recording a rezoning, PUD, variance or special exception costs $25, and copies are $0.10 a page in black and white or $1 in color.

Trade permits and who may pull them

Electrical, plumbing and HVAC work each have their own ILP line: $75 on a residential job and $125 on a commercial or industrial one. An ILP for electrical work is valid for one year. Plumbing contractors also need the state plumbing contractor license.

The county’s fee schedule and UDO do not list a contractor registration fee, and the department’s pages do not describe a separate homeowner permit; ask the office before you apply if you plan to do your own trade work. Septic systems are a separate trade: the Health Department’s Septic Division takes installer applications for trench and sand-lined systems and publishes lists of registered septic installers and soil scientists, along with the Morgan County Septic Ordinance and pump-and-haul and holding tank applications.

How to apply for a Morgan County building permit

1. Confirm the jurisdiction

Make sure the parcel is outside Martinsville, Mooresville, Monrovia and Morgantown.

2. Check the zoning

Use the UDO and the accessory structure tip sheets for setbacks, size and district rules.

3. Get the septic permit

Apply to the Health Department’s Septic Division online or on paper if the lot is not on sewer.

4. Apply in GeoPermits

File the ILP with plans and the floor area of every level, garage, deck and porch.

5. Pay the fee

The schedule sets the fee; work started without a permit pays double.

6. Start within 60 days

An ILP stays valid for two years only if work begins within 60 days of issue.

Review, corrections and what causes delay

The fee schedule charges $100 to resubmit a Plan Commission or BZA application after the second resubmittal, so incomplete filings cost money as well as time. A permit for a house, commercial building or addition lasts two years; one for a manufactured home, accessory structure or electrical work lasts one year. The Administrator may grant up to two six-month extensions on request; once an ILP expires, a new application and fee are needed.

Inspections and certificates in Morgan County

Every ILP must pass its inspections, and no building may be used until the final inspection is approved. Commercial and industrial permits include 10 inspections, with more at $50 each, and reinspections climb from $50 to $200 on homes and from $100 to $300 on commercial jobs.

Want this handled start to finish?

Get a free quote →

The Administrator issues the certificate of occupancy after inspecting the property. It is not issued until any required driveway culvert has been installed and inspected by the Morgan County Highway Department, and no one may live in a dwelling until its sewage system has been installed and inspected by the Morgan County Health Department.

Indiana building code in Morgan County

FEMA’s Community Status Book lists unincorporated Morgan County (community 180176) as participating in the National Flood Insurance Program, with the current flood map dated April 25, 2024; Martinsville has its own entry. The Planning & Zoning Department administers the county’s floodplain protections.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Morgan County building permit FAQs

Is an ILP the same as a building permit in Morgan County?

Yes. The UDO says the improvement location permit is also known as the building permit.

How much is a permit for a new house?

$200 plus $0.10 per square foot over 1,500 square feet, counting every level, garage, deck and porch.

Do I need a permit for a shed?

Not for one of 200 square feet or less without a permanent foundation; larger sheds, or any on a permanent foundation, need an ILP.

Do I need a permit for a fence or patio?

No. Fences, patios, slabs and retaining walls need no ILP but must meet the accessory structure standards.

Can I build an accessory dwelling unit?

Yes in the AG, RR, R-1 and R-2 districts, from 220 to 800 square feet and no more than half the size of the owner-occupied house, with a building permit.

Does the county issue permits in Mooresville or Martinsville?

No. Those communities, along with Monrovia and Morgantown, handle their own zoning; Mooresville runs its own Building Department.

How long is a permit good for?

Two years for most ILPs if work starts within 60 days, or one year for a manufactured home, accessory structure or electrical work, with up to two six-month extensions.

What happens if I build without a permit?

The permit fee doubles.

Inspections are where schedules slip.

Get a free quote →

Morgan County permit search and official resources

Building permit applications are filed and tracked in the county’s GeoPermits portal, and the UDO requires the Plan Commission Administrator to keep a public record of every ILP, so ask the department for older permits. The Health Department’s septic page also lets owners look up soil evaluations and existing septic permits.

Simplify Morgan County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Morgan County sooner?

Let Alliance prepare, file, and track your Morgan County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Morgan County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.