Johnson County’s Department of Planning and Zoning, at 86 West Court Street in Franklin (317-346-4350), issues building permits and improvement location permits only in the unincorporated parts of the county. You file a paper permit packet with the office, and the department says an average review takes about 10 business days. A new house costs $200 plus $0.10 per square foot under Ordinance 2016-13, in force since January 1, 2017, and inspections are included in that fee.
What requires a building permit in Johnson County?
Outside the cities and towns, two county rules overlap. The 2024 Unified Development Ordinance (UDO) requires an improvement location permit (ILP) to put up, alter or change any structure: houses and other primary buildings, accessory buildings, fences, decks, patios and slabs as the UDO sets out, signs, temporary storage containers and wireless facilities. The county building code, adopted by Ordinance 2008-02, then calls for a building permit for construction.
Permit packet required
- New houses, additions, remodels and repairs
- Garages, sheds and other accessory buildings over 200 square feet or on a permanent foundation
- Pole barns and farm buildings
- Decks and swimming pools, in-ground or above ground, and hot tubs
- Every window replacement, which the department requires under the energy code
- Mobile homes, demolition of a building of 200 square feet or more, and electrical service upgrades
No permit under the fee schedule
- Like-for-like electrical panel changeouts, overhead-to-underground service conversions and storm damage electrical repairs
- Concrete driveways, patios, walks or game courts of 100 square feet or less (stormwater permit)
- Stormwater permits for house lots outside a subdivision, the county MS4 area and White River Township that disturb less than 1 acre
Fences in the SR, DR and MR residential districts may be up to 6 feet tall in side and rear yards and 3.5 feet in front yards, and none may sit in a drainage or utility easement.
What Johnson County decides and what the state holds
Ordinance 2008-02 adopts the Fire Prevention and Building Safety Commission’s rules in 675 IAC by reference, with later amendments as they take effect, and the county has adopted no local amendments of its own. The Director of Planning and Zoning, or staff the director designates, enforces the code in unincorporated areas. The county sets its own fees and its zoning, stormwater and flood rules, and works with the fire districts on fire code review; Class 1 buildings also need the state Construction Design Release.
Johnson County building department: who handles permitting
The county department serves only land outside city and town limits. To check an address, open the county’s Beacon GIS map, find the parcel, turn on the “County Zoning” layer, and look for a light-yellow area labeled “CITY-”, which marks land inside a city or town. Director of Planning and Zoning Michele Hansard heads the department, and Keith Biddlecombe is the Chief Building Official for code questions.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Department of Planning and Zoning, Government West Annex, 86 West Court Street, Franklin, IN 46131 |
| Phone and email | 317-346-4350; building@johnsoncounty.in.gov for permit, fee and inspection questions |
| Hours | Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Covers | Unincorporated Johnson County only |
| Payments | Cash, check or card at the office; the county warns it never collects fees through third-party companies, wire services or apps |
Each city and town in the county issues its own building permits.
| Place | Who issues building permits | Official page |
|---|---|---|
| Greenwood (city) | City Building Commissioner, Department of Community Development Services | Greenwood Building Commissioner |
| Franklin (city) | City Department of Planning and Engineering | Franklin building permits and inspections |
| Bargersville | Town Planning and Zoning and permit administration, with an online permit portal | Bargersville permits and applications |
| Edinburgh (Johnson County part) | Town Planning Department and its Building & Zoning Official | Edinburgh building permit page |
| New Whiteland | Town Planning and Zoning office, which takes permit applications by email or in person | New Whiteland planning and zoning |
| Prince’s Lakes | Town Building Inspections Department | Prince’s Lakes building inspections |
| Trafalgar | Town Planning and Zoning, with its own building inspector | Trafalgar planning and zoning |
| Whiteland | Town Community Development department and Building Commissioner | Whiteland planning and zoning |
Separate guides cover Greenwood and Franklin. Edinburgh lies only partly in Johnson County.
Johnson County permit types
The county works from paper packets rather than an online portal; each bundles the application, checklist and supporting forms.
Not sure this scope needs a permit?
Get a free quote →Residential permits
- New houses, additions and remodels use the Residential Building Permit Packet (updated February 2024). It asks for two scaled site plans, two sets of building plans (elevations, wall section, foundation and floor plans, window and door framing, and mechanical, plumbing and electrical drawings), sealed truss calculations where trusses are used, and energy code compliance by the prescriptive or performance path.
- Garages, sheds, pole barns, decks, pools, windows, mobile homes, demolition and electrical service each have their own packet; an accessory building needs at least elevations, a wall section and foundation and floor plans.
- New homes get an address 30 to 45 days after the permit issues, where one is needed.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial, multifamily, industrial and institutional buildings use the Commercial Building Permit Packet and the non-residential fee rates, which also cover agricultural structures. Expect a non-residential stormwater permit, Technical Review Committee comments and the state design release for Class 1 work; kitchen hoods, sprinklers and tenant finishes are priced separately.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Land use check. A Land Use Verification form ($50) confirms that a parcel was created properly and can be built on; staff will refuse a permit on a lot that was split improperly.
- Zoning approvals. The Plan Commission hears rezonings and subdivisions, and the Board of Zoning Appeals hears variances and special exceptions; a hearing officer can decide smaller development standards variances.
- Septic. Lots without sewer need a septic permit from the Johnson County Health Department before the building permit.
- Sewer. Where sewer is available, bring the sewer permit from the town, city or conservancy district that serves the lot.
- Driveway. The county Highway Department issues driveway and other right-of-way permits, or verifies an existing driveway.
- Stormwater and erosion control. Lots in a subdivision, the county MS4 area or White River Township need a stormwater permit and a stormwater pollution prevention plan, and some permits carry an erosion control meeting before work starts.
- Floodplain. The application asks whether the lot is in a FEMA flood hazard area or a local flood area; the county’s Flood Control Ordinance (2024-Z-3) applies, and building in a floodway also needs IDNR approval.
Johnson County permit costs and fees
Building and planning fees are set by Ordinance 2016-13, adopted by the Board of Commissioners on November 14, 2016 and in force since January 1, 2017. Stormwater fees are set by Ordinance 2016-14 on the same schedule.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New house, duplex unit or manufactured home (per dwelling unit) | $200 + $0.10 per sq ft |
| Residential alteration, remodel, repair or addition | $150 + $0.10 per sq ft |
| Residential accessory building or addition | $0.10 per sq ft; $50 minimum, $500 maximum |
| Deck / above-ground pool / hot tub | $75 each |
| In-ground pool / mobile home | $150 each |
| Residential electrical upgrade (meter base or service change) | $75 |
| Non-residential new construction | $400 + $0.10 per sq ft |
| Non-residential alteration, remodel or addition / tenant finish | $200 + $0.10 per sq ft / $300 + $0.10 per sq ft |
| Non-residential accessory building | $150 + $0.10 per sq ft; $200 minimum |
| Commercial kitchen hood or sprinkler system / non-residential electrical upgrade | $150 each |
| ILP for non-structural work | $150 residential; $300 non-residential |
| Demolition (per building of 200 sq ft or more) | $150 |
| Re-inspection | $50 first; $200 second; $300 third |
| Missed inspection | $150 per inspection |
| Permit extension | 50% of the original fee |
| Use variance / special exception / development standards variance | $400 / $400 / $200 |
| Rezoning | $500 + $25 per acre |
Worked example from the schedule: a 2,400-square-foot new house is $200 + (2,400 × $0.10) = $440. If the lot is in a subdivision, the county MS4 area or White River Township, the stormwater permit adds 50% of the building permit cost, or $220, for $660 in all. Inspections are included in the building permit fee; only repeat trips are billed. Fees triple when work starts before the permit, and registered 501(c)(3) non-profits pay half.
White River Township has had a road impact fee on new single-family homes and commercial buildings, collected by the planning office with the building permit. The Highway Department’s page shows Ordinance 2020-O-11, in force from August 9, 2021, setting $2,571.64 per new single-family home, and says an impact fee ordinance expires after five years unless a new study and ordinance are adopted. No renewal is posted, so before you file ask the Highway Department (317-346-4630) whether the fee still applies and at what amount.
Trade permits and who may pull them
The county does not issue separate electrical, plumbing or mechanical permits for a building project. The residential fee covers structural, electrical, plumbing and HVAC work, and the application carries a Sub-Contractor Sign-off Sheet naming who will do or oversee each trade. A stand-alone service change uses the Electrical Service Permit Packet.
Rather not deal with the Johnson County building department?
Get a free quote →- Contractor listing. A contractor who pulls a permit for an owner must be on the county’s Contractor Listing: post a $15,000 surety bond payable to Johnson County and/or an unknown third party, and pay $150 for one year, $200 for two or $400 for five (a two- or five-year listing needs a bond of the same length).
- Owners doing their own work. An owner who pulls the permit signs a notarized Contractor Listing Exemption Affidavit, taking on the general contractor’s duties for a building the owner occupies or intends to occupy.
- Plumbers hold the state plumbing contractor license, and the cities and towns set their own contractor rules.
How to apply for a Johnson County building permit
Check the Beacon GIS map with the County Zoning layer turned on; land inside a city or town goes to that unit.
Get the septic permit from the Health Department or the sewer permit from the utility, and the driveway permit or verification from the Highway Department.
Download the residential, accessory, pole barn, deck, pool, window, demolition or commercial packet and fill in the application.
Add the recorded deed, two scaled site plans, two sets of plans, truss calculations, energy code forms and, where required, the stormwater application with two copies of the SWPPP.
Include the contractor’s current county listing, or your notarized exemption affidavit, and the sub-contractor sign-off sheet.
Submit the packet to Planning and Zoning at 86 West Court Street; fees, including any road impact fee, are collected when the permit issues.
Review, corrections and what causes delay
The department’s average review is 10 business days and its packets say 7 to 10, and both warn that the time stretches when more permits than usual come in during a week. An application missing any required item is not issued until the missing material arrives, and a parcel that was split improperly cannot get a permit at all.
Inspections and certificates in Johnson County
Every building inspection is booked with Planning and Zoning staff by phone or in person; voicemail requests are not scheduled. Book residential inspections at least one business day ahead and non-residential inspections at least two, which gives the building official time to coordinate with the fire department. Footing inspections can be set for a time; other inspections are scheduled by the day, and an AM or PM request cannot be promised.
Before work starts, hold the erosion control meeting if your permit requires one. Keep the permit and the stamped “Released for Construction” plans on site, put the permit in a window visible from the road once windows are in, and leave the permit card where the inspector can sign it. Under the UDO, no building may be occupied until the final inspection is complete and a certificate of occupancy is issued where one is required, and re-inspection fees must be paid before the final inspection is booked.
Want this handled start to finish?
Get a free quote →Indiana building code in Johnson County
Johnson County enforces the state rules under Ordinance 2008-02 with no local amendments. FEMA’s Community Status Book lists unincorporated Johnson County (community 180111) as participating in the National Flood Insurance Program, with its current flood map dated January 29, 2021; the cities and towns take part separately.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Johnson County permit search and official resources
For an existing permit or inspection record on unincorporated land, contact Planning and Zoning at 317-346-4350 or building@johnsoncounty.in.gov with the address or parcel number; the UDO requires the department to keep a public record of every ILP. Septic records sit with the Health Department, drainage and legal drain records with the County Surveyor, and permits inside a city or town with that unit.
- Johnson County Department of Planning and Zoning
- Building permit packets and forms
- Planning and Zoning fee schedule, Ordinance 2016-13 (with stormwater Ordinance 2016-14)
- Residential building permit packet (February 2024)
- Inspection information
- Contractor Listing program
- Building Department: code adoption and review time
- 2024 Unified Development Ordinance
- Flood Control Ordinance 2024-Z-3
- Health Department onsite septic information
- Health Department fee Ordinance 2026-O-01
- Johnson County Highway Department (driveway and right-of-way permits)
- Road and Bridge Impact Fee, White River Township
- Johnson County Surveyor and Drainage Board
- FEMA Community Status Book, Indiana
- Indiana Department of Homeland Security: currently effective code rules
Inspections are where schedules slip.
Get a free quote →Johnson County building permit FAQs
Does Johnson County issue permits in Greenwood or Franklin?
No. The county department serves unincorporated land only; Greenwood, Franklin and the six towns each issue their own permits.
How much is a building permit for a new house in unincorporated Johnson County?
$200 plus $0.10 per square foot per dwelling unit, so a 2,400-square-foot house is $440, plus any stormwater, septic and road impact fees.
Do I need a permit to replace windows?
Yes. The county requires a permit for every window replacement under the energy code and publishes a Window Replacement Permit Packet.
Can I pull my own permit as a homeowner?
Yes, for a building you live in or plan to live in, by signing a notarized Contractor Listing Exemption Affidavit; a hired contractor must hold a county listing.
Does a shed need a permit?
A shed or other accessory building over 200 square feet, or on a permanent foundation, needs a building permit, charged at $0.10 per square foot with a $50 minimum.
How long does review take?
About 10 business days on average, longer in busy weeks, and only once every required document is in.
Who issues septic permits?
The Johnson County Health Department’s Environmental Division at 95 South Drake Road, Franklin (317-346-4365); a new system costs a $150 application fee plus a $250 installation permit.
Simplify Johnson County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Johnson County sooner?
Let Alliance prepare, file, and track your Johnson County permits while your crew stays on the job.
More Indiana permitting guides
Franklin
Read guide →Greenwood
Read guide →Morgan County
Read guide →Kendallville Building Permit Guide
Read guide →Knox County Building Permit Guide
Read guide →Kokomo Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Johnson County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.