In Noble County, building permits for the unincorporated townships come from the Noble County Building Department at the county annex, 109 N. York Street, Albion (260-636-2215, Monday to Friday 8 a.m. to 4 p.m.). Albion, Avilla, Kendallville, Ligonier and Rome City issue their own. Applications are filed in person or by email, never online, and come after an improvement location permit from the Plan Commission, a drainage check from the Surveyor and a septic or sewer clearance. Under Ordinance 2024-35, in force since January 1, 2025, a house costs $0.10 per square foot with the electrical, plumbing and HVAC permits included.
What requires a building permit in Noble County?
The Building Department’s homeowner advice puts it simply: building, altering or repairing any building needs a local permit unless the work is maintenance. Its lists cover the county’s area only.
Permit required
- New structures, additions that add square footage, structural changes and foundation work
- Manufactured homes; modular and double-wide homes are permitted like site-built houses
- Storage sheds over 120 square feet, decks and grain bins
- Wind turbine towers, communication towers and signs
- Fire sprinkler systems
- Electrical, plumbing and HVAC work, including a new or updated electrical panel, gas lines and standby generators
- Above-ground pools over 42 inches deep and all in-ground pools
- Residential solar, roof- or ground-mounted
No building permit
- Siding, and doors or windows unless a new header goes in
- Replacing garage doors
- Roofing, unless the roof line or structure changes or trusses are replaced
- Interior finish work that leaves load-bearing walls alone
- Portable sheds of 120 square feet or less that are not in a floodplain
- Fences, sidewalks, driveways, swing sets and play equipment
- Minor electrical and mechanical repairs, and prefabricated pools under 24 inches deep
The county issues no demolition permits; ponds go to the Surveyor. Anything in a mapped floodplain, even a permit-free shed, goes past the floodplain administrator first.
What Noble County decides and what the state holds
The county enforces the codes of the state Fire Prevention and Building Safety Commission through its Building Ordinance 2011-05, which also lets the Building Commissioner hold back a permit when fees are owed or the use breaks the zoning ordinance. Two local rules stand out: air admittance valves only where nothing else works, such as an island sink, and GFCI protection on every laundry-room outlet. Zoning comes from the Unified Development Ordinance, in effect since January 1, 2013 and last amended in May 2025. Work on a Class 1 building also needs the state design release before the county permit is issued.
Noble County building department: who handles permitting
The Building Department issues building permits and inspects; the Plan Commission office issues improvement location permits, runs the zoning ordinance and serves the Board of Zoning Appeals; the Surveyor reviews drainage. Plan Director Teresa Tackett is the Zoning Administrator. The Plan Commission’s zoning area is the unincorporated county plus the Town of Cromwell, whose own zoning ordinance it posts.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Building Department | Noble County Annex, 109 N. York Street, Albion, IN 46701; 260-636-2215; fax 260-636-6957; building@nobleco.gov; Monday to Friday 8 a.m. to 4 p.m. |
| Plan Commission and BZA | Same annex; 260-636-7217; planning@nobleco.gov; 8 a.m. to 4 p.m. weekdays |
| Surveyor and Drainage Board | 2090 N. State Road 9, Suite B, Albion; 260-636-2131 |
| Health Department (septic) | 260-636-2191, extension 2; septic applications taken only at the office |
| Highway Department (driveways) | 1118 E. Main Street, Albion; 260-636-2124; 7:30 a.m. to 3:30 p.m. |
Which office handles an address
| Place | Building permits |
|---|---|
| Unincorporated townships | Noble County Building Department |
| Albion, Avilla, Ligonier and Rome City | Each runs its own jurisdiction, as the county’s page lists them |
| Kendallville | The city’s Building, Planning and Zoning office; see the Kendallville guide |
| Cromwell | Not on the county’s list of self-permitting towns; zoning is enforced by the county Plan Commission office |
| Wolcottville (Noble County part) | On neither county list; ask the Building Department, which offers to point callers to the right office |
The county GIS (Beacon) parcel viewer, linked from the Surveyor page, shows whether a parcel lies inside a town limit.
Noble County permit types
Every county permit starts on the Pre-Application for Building Permit, which carries both the Plan Commission and the Building Department headings and asks for the parcel number, drainage check result, driveway permit number and septic permit number before the building section. The department also wants to know how a structure will be built, such as post sizes and spacing for a deck or post depth and truss specifications for a pole building.
Residential permits
- New houses and additions are charged by area and include the electrical, plumbing and HVAC work. Engineered truss drawings must be filed or kept on site.
- Manufactured homes: a single-wide needs a BZA variance outside a mobile home park.
- Garages, pole buildings and sheds over 120 square feet need a site plan with distances to property lines; plumbing in an outbuilding brings in the Health Department.
- Decks, pools, generators, gas lines and residential solar each have their own inspection sheet.
- Energy code: new homes, additions and remodels need a third-party energy rater’s letter, a REScheck report, or the county’s prescriptive values (R-10 foundations, R-21 walls, R-38 attics).
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial buildings are charged by area with mechanicals included. Cell towers, wind turbines, advertising structures and commercial solar arrays of 41 kilowatts or more start at the Plan Commission; the building permit can be applied for only once it has approved the project. Class 1 projects bring the state design release to the counter with the plans.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Improvement location permit. The Plan Commission checks setbacks, lot coverage, permitted use and floodplain, and charges $30 for a dwelling or primary structure and $10 for an accessory building. The Plan Commission also completes an agricultural clause form, recorded with the Recorder for $25.
- Drainage check. The Surveyor certifies that the house, septic field and driveway are not within 75 feet of a county regulated drain and meet the storm drainage and erosion control ordinance. Subdivisions, commercial sites, land disturbance over one acre and excavation of more than 1,000 cubic yards need a full stormwater review.
- Septic or sewer. A septic permit or clearance from the Health Department, or a letter from the sewer district confirming a tap, is required for new homes and commercial buildings and for additions or remodels that add a bedroom, including a bathroom added to an accessory building.
- Driveway. Any permit without an existing driveway needs a county highway driveway permit, even where a removed or burned house once stood; driveways onto a state road go to INDOT.
- Floodplain. Development in a mapped floodplain needs a Floodplain Improvement Location Permit ($50) and a recorded Floodplain Acknowledgement Agreement before any permit is issued.
Noble County permit costs and fees
Building Department fees are set by Commissioners’ Ordinance 2024-35, passed on December 16, 2024 and in force since January 1, 2025, which replaced Ordinance 2023-13 of July 10, 2023. The copy posted on the county site is marked as not the official document, so the Auditor’s signed ordinance governs any dispute. Plan Commission fees come from its own schedule, effective April 1, 2022.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| House: living area, and unfinished basement or other non-living area | $0.10 per sq ft, all mechanicals included |
| Detached garage, accessory building over 120 sq ft, deck, porch, patio, gazebo or pavilion | $75 (mechanicals extra) |
| Attached garage | $75 when taken out with the new house (mechanicals included); taken out separately, mechanicals are additional |
| Electrical, plumbing, gas service or heating and cooling improvement | $50 each |
| Structural remodel (roof structure, structural walls, foundation repair) | $50 |
| Agricultural structure | $0.03 per sq ft (mechanicals extra); grain bins $50 |
| Above-ground pool / in-ground pool | $50 / $150, mechanicals included |
| Commercial structure | $0.10 per sq ft, all mechanicals included; commercial foundation $100 |
| Residential solar under 41 kW | $50 |
| Commercial solar, 41 kW to 999 kW | $250 to $1,000 by size band |
| Commercial solar, 1 MW and up | $5,000, $10,000 or $15,000 by size band, plus consultant cost and 5% |
| Minimum permit fee | $50 |
| Renewal of a permit not finished within one year | $50 |
| Item | Fee |
|---|---|
| Improvement location permit: dwelling or primary structure / accessory structure | $30 / $10 |
| Floodplain improvement location permit | $50 |
| Variance, first / each additional application | $250 / $100 |
| Special exception | $250 |
| Zoning verification letter | $30 |
| Septic permit / variance (Health Department) | $100 / $50 |
Worked example from Ordinance 2024-35: a new 2,000-square-foot house with no basement and an attached garage taken out at the same time costs 2,000 × $0.10 = $200 plus $75 for the garage, or $275 at the Building Department, with no separate trade permits. Add the $30 improvement location permit and the $100 septic permit if the lot is not sewered. The ordinance also sets penalties: a $50 fine for each inspection that is missed, and up to $250 added to the permit when work starts before the permit, at the Building Inspector’s discretion.
Trade permits and who may pull them
On a new house or addition the trade work rides on the area-based permit; on its own, each electrical, plumbing, gas or HVAC improvement is a $50 permit from the same Building Department. Gas lines and generators are inspected with a gauge on the line holding 15 pounds of pressure for 20 minutes.
Rather not deal with the Noble County building department?
Get a free quote →- Contractor registration: the Building Department does no contractor registration or licensing, and it does not require a license or permit bond.
- Plumbers: the permit checklist asks for the plumber’s name, phone and license number, which ties to the state plumbing contractor license; the fee ordinance lets the department ask for it on any permit that includes plumbing.
- Insurance: the fee ordinance lets the department ask for proof of liability insurance, but its homeowner page says the county does not require it and tells owners to ask for a certificate themselves.
- Owners: the inspection sheets are addressed to “your contractor (or you as the owner)”.
- Septic installers are licensed by the Health Department ($50 a year), and only a licensed installer may install or repair a system.
How to apply for a Noble County building permit
Check that the lot is outside the five self-permitting municipalities, or call 260-636-2215.
Take the site plan and recorded deed to the Plan Commission office, record the agricultural clause form it completes, and in a floodplain get the floodplain permit.
Surveyor’s drainage check, Health Department septic permit or sewer letter, and the driveway permit from the Highway Department or INDOT.
Fill in the pre-application and attach plans with foundation details, truss drawings and the energy compliance choice.
Bring the package to the annex or email it to building@nobleco.gov; email filers must be able to print, sign, scan and return the permit.
Pay the fee set by Ordinance 2024-35 and post the permit at the site.
Review, corrections and what causes delay
Most holdups come before the counter: a missing drainage check, a septic system not yet located before an addition adds bedrooms, or a flood-zone lot that needs NAVD 88 elevations and a surveyor’s benchmark. Plan Commission and BZA cases run on a monthly cycle with filing deadlines about four weeks ahead, at 2 p.m. on the file-by date.
Inspections and certificates in Noble County
Every inspection needs 24 hours’ notice by phone to 260-636-2215. For a house the county sheet lists footer (below the 36-inch frost line), foundation, under-floor plumbing and HVAC, slab, rough frame, rough electrical, rough plumbing (no studor vents except at island sinks), HVAC, garage firewall, insulation, permanent electrical service, gas line and final, plus a crawlspace elevation check in the floodplain.
Two finals come from other offices before the certificate of occupancy: the Health Department’s septic final and the Highway Department’s driveway final. The certificate checklist adds interconnected smoke and carbon monoxide alarms on every level, doors on bedrooms and bathrooms, working utilities and water, handrails on steps of two or more risers, an energy certificate posted on the service panel, and, in a flood hazard area, an as-built elevation certificate. Basements must have at least two exits, one straight to the outside, even with no bedroom downstairs. Floodplain permits from the Plan Commission carry their own three inspections, booked through that office.
Want this handled start to finish?
Get a free quote →Indiana building code in Noble County
Noble County adopts the state commission’s rules by reference in Building Ordinance 2011-05, and an order under it can be appealed to the state Fire Prevention and Building Safety Commission or locally under IC 36-7-8-9. FEMA’s Community Status Book lists unincorporated Noble County (community 180183B) as taking part in the National Flood Insurance Program, with flood maps effective May 2, 2017; the towns enroll separately. Its flood rules ban basements in the floodplain and allow fill only where the same volume is removed from the floodplain on the same lot.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Noble County permit search and official resources
The county has no public online permit search. For an existing permit, inspection record or certificate of occupancy, ask the Building Department at 260-636-2215 or building@nobleco.gov; zoning approvals, variances and addresses are kept by the Plan Commission office, and septic records by the Health Department, whose septic search form is posted on its site. Plan Commission and BZA agendas and the Commissioners’ minutes are posted online.
- Noble County Building Department
- Required permits and inspections by project
- How to obtain a permit
- Building fee Ordinance 2024-35
- Items needed to obtain a building permit
- Required inspections, all project types
- Building Ordinance 2011-05 (posted copy)
- Plan Commission of Noble County
- Plan Commission fee schedule
- Floodplain permits and rules
- Health Department septic and wastewater
- Noble County Surveyor
- Noble County Highway Department
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Noble County building permit FAQs
Does the county issue permits in Kendallville or Ligonier?
No. Albion, Avilla, Kendallville, Ligonier and Rome City issue their own building permits; the county covers the rest of the county.
How much is a permit for a new house?
$0.10 per square foot of living and basement area with all trades included, so a 2,000-square-foot house with an attached garage taken out together is $275, plus the $30 improvement location permit.
Do I need a permit for a shed?
Only over 120 square feet, or in a floodplain at any size, where a portable shed needs a flood permit, flood-resistant materials and flood vents.
Can I apply online?
No. File in person at the Albion annex or email the signed pre-application to building@nobleco.gov.
Do contractors have to register with Noble County?
Not with the Building Department, which does no registration, licensing or bonding; plumbers still give a license number on the application.
Is a permit needed for a new roof?
Not for re-roofing; a permit is needed only when the roof line or structure changes or trusses are replaced.
Simplify Noble County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Noble County sooner?
Let Alliance prepare, file, and track your Noble County permits while your crew stays on the job.
More Indiana permitting guides
Kendallville
Read guide →LaGrange County
Read guide →Whitley County
Read guide →Owen County Building Permit Guide
Read guide →Parke County Building Permit Guide
Read guide →Peru Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Noble County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.