For land in unincorporated Howard County, the first permit is an improvement location permit (ILP) from the Kokomo-Howard County Plan Commission, a joint city-county office at 224 North Main Street, Kokomo (765-456-2330, weekdays 8 a.m. to 4 p.m.). A new house also needs a septic permit from the Howard County Health Department or a Kokomo sewer tap, an MS4 permit from the County Surveyor and a driveway permit from the County Highway Department. The ILP costs $1 per $1,000 of estimated cost, with a $100 minimum and $1,000 maximum. Kokomo, Greentown and Russiaville handle building permits inside their own limits.
What requires a building permit in Howard County?
Outside the three incorporated places, construction starts with an ILP from the Kokomo-Howard County Plan Commission, which administers the county’s zoning. The Plan Commission’s instructions and application show what it expects for a new home, and its fee categories name houses, duplexes and their additions, swimming pools, accessory structures and signs, as well as commercial, multi-family, institutional and industrial buildings.
ILP needed (county)
- New houses and duplexes, and additions to them
- Accessory buildings such as garages and pole barns
- Swimming pools
- Commercial, industrial, institutional and multi-family buildings
- Signs, including temporary signs
- Temporary mobile homes, which also need BZA approval
Other county permits for a new home
- Septic permit from the Howard County Health Department, or a City of Kokomo sanitary sewer tap permit
- MS4 (stormwater) permit from the County Surveyor
- Driveway permit from the Howard County Highway Department
- Subdivision approval if the lot is not an approved building lot
A further rule sits in the county code. Chapter 150, adopted in 1978, created a county Department of Buildings and requires a construction permit from a county Building Commissioner for building, plumbing, electrical, heating, ventilation or air conditioning work costing more than $100, with painting and cosmetic repairs exempt. The Plan Commission’s current ILP instructions for county parcels name no separate county building permit, and its fee schedule says the certificate of occupancy inspection fee takes effect only when an inspector is appointed. Ask the Plan Commission which of these applies to your project before you build.
What Howard County decides and what the state holds
The county sets zoning districts, lot sizes and setbacks, approves subdivisions and site plans through the Plan Commission, hears variances through its Board of Zoning Appeals, runs a countywide stormwater district and administers the unsafe building law in the unincorporated area. Indiana sets the building codes. Buildings used by the public, by three or more tenants or by employees are Class 1 and need a state Construction Design Release before construction, unless exempt; one- and two-family homes are Class 2 and are permitted locally where an ordinance requires it.
Short on time to read all of this?
Get a free quote →Howard County building department: who handles permitting
The Kokomo-Howard County Plan Commission is a hybrid office that staffs four boards: the City of Kokomo Plan Commission and Board of Zoning Appeals, and the Howard County Plan Commission and Board of Zoning Appeals. It issues ILPs for both the city and the county. Inside Kokomo the ILP is followed by a city building permit from Kokomo Inspection Services; the county code defines the unincorporated area as everything outside Kokomo, Greentown and Russiaville. To check which side of a boundary a parcel sits on, use the county’s property and tax lookup on Beacon, linked from the county home page.
| Place | Who permits |
|---|---|
| Unincorporated Howard County | Kokomo-Howard County Plan Commission (ILP, site plans, BZA), with county Health Department, Surveyor and Highway permits |
| Kokomo (59,999) | ILP from the same Plan Commission, then a building permit from Kokomo Inspection Services, City Hall, 100 South Union Street; see the Kokomo guide |
| Greentown (2,366) | Town of Greentown: building permit application at the utility office, 112 North Meridian Street; Greentown Plan Commission |
| Russiaville (1,312) | Town of Russiaville: its own fence/building permit form, Planning Commission and Zoning Board of Appeals; Town Hall, 250 North Union, 765-883-5739 |
| Office | Details |
|---|---|
| Kokomo-Howard County Plan Commission | 224 North Main Street, Kokomo, IN 46901 (the city’s Plan Commission page lists 120 East Mulberry Street, Suite 114, for county matters); 765-456-2330; khcpc@cityofkokomo.org; Monday to Friday, 8 a.m. to 4 p.m. |
| Howard County Health Department (septic) | 765-456-2403 |
| County Surveyor (MS4 permit) | 765-456-2217 |
| County Highway Department (driveways) | 765-456-2802 |
| County administration | Howard County Administration Center, 220 North Main Street, Kokomo; weekdays 8 a.m. to 4 p.m. |
Howard County permit types
The Plan Commission posts separate county forms for an ILP, rezoning, site plan, special exception, variance and subdivision, plus a county site plan checklist. Every application needs the property owner’s signature.
Residential permits
- ILP for a house or addition. Submit a full legal description (lot number and addition, or metes and bounds; tax codes and short tax descriptions are not accepted) and a scaled plot plan showing every existing and proposed building and all rights-of-way, utility and drainage easements.
- Accessory buildings. At least 5 feet from side and rear lines and 6 feet from the house in the AZ, A1, RS1, RS2 and R1 districts.
- Temporary mobile homes. A $250 BZA permit, with a $250 extension.
- Flood-prone lots. The ILP application asks whether the property is in the floodplain, for the FIRM panel and zone, and for the flood protection grade: the regulation flood grade plus 2 feet.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial, multi-family, institutional and industrial projects take an ILP and usually a development plan or site plan approval ($450) from the Plan Commission. A planned unit development costs $600 plus $25 an acre and may also need subdivision approval. Class 1 buildings need the state design release, and the Plan Commission posts a county site plan checklist for these submissions.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- An approved building lot. Unapproved lots may need subdivision approval first.
- Zoning standards. In the county’s AZ and A1 districts a lot needs 20,000 square feet with sewers or 30,000 on septic; in RS1, 15,000 or 44,000; in RS2, 10,000 or 36,000; in R1, 7,200 or 30,000. Front setbacks are 75 feet from a federal or state highway and 50 feet from an arterial; side yards are 10% of lot width; and lot coverage is capped at 30%.
- Septic or sewer. A Health Department septic permit or a Kokomo sewer tap permit.
- Stormwater. An MS4 permit from the County Surveyor. The Howard County Stormwater Management District, created by Ordinance 2008-BCC-29, covers everything outside Kokomo, Greentown and Russiaville and may levy a stormwater user fee.
- Driveway. A County Highway Department permit on county roads.
Howard County permit costs and fees
Plan Commission fees come from the Kokomo-Howard County Plan Commission fee schedule, effective January 1, 2006 and amended as of February 28, 2012, which has a column for Howard County. An older ILP information sheet still on the county site gives a $15 minimum; the fee schedule sets $100.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Improvement location permit | $1 per $1,000 of estimated cost; $100 minimum, $1,000 maximum |
| After-the-fact surcharge | $10 per $1,000 of estimated cost |
| Temporary sign permit | $75 |
| Certificate of occupancy inspection (once an inspector is appointed) | $50 signs and one- or two-family homes; $75 non-residential |
| Zoning ordinance amendment | $600 |
| Major subdivision, primary / final | $500 + $10 per lot / $250 + $10 per lot |
| Development plan or site plan approval | $450 |
| Planned unit development | $600 + $25 per acre |
| Development standard variance | $250 + $50 for each additional variance |
| Special exception | $250 + $25 per acre |
| Temporary mobile home permit / extension | $250 / $250 |
| Continuance requested by the petitioner | $50, or $100 if Advisory Technical Committee review is needed |
Worked example: a new house with an estimated cost of $300,000 pays an ILP fee of $300 (300 × $1); a $60,000 pole barn would compute to $60 and so pays the $100 minimum; and any project over $1,000,000 pays the $1,000 cap. The after-the-fact surcharge applies when a stop work order is issued at the site or the owner is notified by registered mail that work is under way without an ILP. Fees may be waived for government, religious and non-profit projects, and waivers are reported to the Plan Commission. Septic, MS4 and driveway permit fees are set by the Health Department, Surveyor and Highway Department.
Trade permits and who may pull them
Howard County’s Plan Commission pages describe no county electrical, plumbing or mechanical permit for unincorporated parcels, and no county contractor license or registration. The 1978 building chapter of the county code does cover plumbing, electrical, heating, ventilation and air conditioning work over $100, so ask the Plan Commission about trade permits on your project.
- Plumbing: plumbing contractors hold the state license from the Indiana Plumbing Commission.
- Electrical and HVAC: Indiana licenses neither trade; any rules are local.
- Inside Kokomo: the city issues electrical permits and sewer tap permits, its application asks for the plumbing contractor’s Indiana license number, and the city says it does not license general contractors.
Rather not deal with the Howard County building department?
Get a free quote →How to apply for a Howard County permit
Kokomo, Greentown and Russiaville parcels go to those governments; everything else is county.
Check that it is an approved building lot and meets the district’s area, width and frontage rules.
Septic or sewer, MS4 and driveway permits for a new home.
County ILP application signed by the owner, legal description and scaled plot plan with easements.
At 224 North Main Street, Kokomo, or email khcpc@cityofkokomo.org, with the fee.
Confirm whether county inspections apply before work starts.
Review, corrections and what causes delay
Plans that use tax codes instead of a legal description, or plot plans that leave out easements, do not meet the published ILP requirements. Cases that need a Plan Commission or BZA hearing wait for the meeting calendar, and a petitioner who asks to continue a case pays $50 or $100 before it goes back on the agenda; continuances requested by others or recommended by the Advisory Technical Committee carry no extra fee. Rezoning, site plan, special exception and variance applications each have their own county form.
Inspections and certificates in Howard County
The Plan Commission’s fee schedule provides a certificate of occupancy inspection fee of $50 for one- and two-family homes and signs and $75 for non-residential buildings, but says it takes effect only when an inspector is appointed, and the county’s published ILP instructions describe no county inspection schedule. The older county building chapter calls for a $7.50 fee for each required inspection. Ask the Plan Commission at 765-456-2330 which inspections, if any, the county performs on your job.
Inside Kokomo, city building and electrical inspectors inspect each phase of a project after the ILP and city building permit are issued, with 48 hours’ notice. Unsafe buildings in the unincorporated county are handled by the Plan Commission under the state unsafe building law, with the Plan Commission’s Executive Director as the enforcement authority.
Indiana building code in Howard County
The state building codes apply everywhere in the county; who enforces them depends on where the parcel lies. FEMA’s Community Status Book lists unincorporated Howard County (community 180414A) as participating in the National Flood Insurance Program, with flood maps effective February 4, 2015, and the county ILP application asks for the FIRM panel and flood protection grade.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Howard County permit search and official resources
For records of past ILPs, variances or other county files, Howard County takes public records requests through an online Submit a Public Records Request form linked from the county home page. Plan Commission and BZA records are kept by the Kokomo-Howard County Plan Commission at 224 North Main Street.
- Howard County Plan Commission: forms and contacts
- Kokomo-Howard County Plan Commission fee schedule
- Improvement location permit information (city and county)
- Howard County ILP application
- County site plan checklist
- County variance application
- Howard County ordinance document center
- Howard County Code of Ordinances (S-13)
- Kokomo Plan Commission: plan commissions in Howard County
- Kokomo Building Permits Office
- Town of Greentown: building permit FAQ
- Town of Russiaville: permits and applications
- Howard County public records request
- IDHS building plan review (Construction Design Release)
- Fire Prevention and Building Safety Commission rules
- Indiana Plumbing Commission
Inspections are where schedules slip.
Get a free quote →Howard County building permit FAQs
Who issues permits in unincorporated Howard County?
The Kokomo-Howard County Plan Commission issues the improvement location permit, at 224 North Main Street, Kokomo; call 765-456-2330.
How much is an ILP for a new house?
$1 per $1,000 of estimated cost, at least $100 and at most $1,000; a $300,000 house pays $300.
What other permits does a new county home need?
A Health Department septic permit or a Kokomo sewer tap, an MS4 permit from the County Surveyor and a driveway permit from the County Highway Department.
Does the county issue permits in Greentown or Russiaville?
No. Both towns have their own plan commissions and building permit forms; Kokomo issues its own building permits after the joint ILP.
What happens if I build without an ILP?
An after-the-fact surcharge of $10 per $1,000 of estimated cost is added when a stop work order is issued or a registered-mail notice is sent.
How big must a county lot be?
It depends on the district and sewer service: from 7,200 square feet in R1 with sewers to 44,000 square feet in RS1 on septic.
How do I request county permit records?
Use the county’s online public records request form, or ask the Plan Commission for its files.
Simplify Howard County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Howard County sooner?
Let Alliance prepare, file, and track your Howard County permits while your crew stays on the job.
More Indiana permitting guides
Kokomo
Read guide →Tipton County
Read guide →Miami County
Read guide →Huntington Building Permit Guide
Read guide →Huntington County Building Permit Guide
Read guide →Indianapolis Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Howard County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.