Inside the city limits of Huntington, permits come from the Community Development and Redevelopment (CDR) Department, now at the Temporary City Offices, 217 West State Street ((260) 356-5146). Its Building Commissioner administers Chapter 150 of the city code, which covers building, electrical, plumbing, fence, demolition and unsafe building work. Applications start with a visit to the department, a building permit takes three to five days on average, and under Ordinance 6-C-26 a new house costs $0.08 per square foot of gross floor area with a $160 minimum. Land outside the city is handled by the Huntington Countywide Department of Community Development.
What requires a building permit in Huntington?
Title XV of the city code lists the work that needs a CDR permit. The list is broad: an accessory building needs a permit whatever its size and whether it is built on site or delivered ready-made.
Building permit
- New homes, home additions (including enclosing an existing porch or structure), decks and porches
- Garages, sheds, carports, gazebos and pergolas of any size
- Non-residential buildings, their additions and interior renovations, including work that needs a state design release
- New roof projections and structural roof changes (re-shingling is not on the list, but no roof may carry more than two layers)
- Placing a manufactured home, including inside a mobile home park, and temporary structures
- In-ground pools, and on-ground pools able to hold more than 42 inches of water or set inside a home
Other city permits
- Electrical: new, upgraded, relocated or altered services, manufactured home hook-ups and branch circuits
- Plumbing: new homes, additions, commercial buildings and additions, added fixtures, accessory buildings with plumbing
- Demolition of any structure over 200 square feet
- Building a fence, or changing the type or height of an existing one
- Zoning permits for floodplain work, permanent or temporary signs, home occupations, livestock and airport height
Replacing or rebuilding a structure that would need a permit if it were new also needs one. Sewer and water taps and drive cuts are separate permits from the City Engineer’s office, so a new house usually involves both departments.
What the city decides and what the state holds
The city writes its own building, zoning (Chapter 158), historic district (Chapter 153) and fee rules, and the Common Council adopts them by ordinance; zoning in Huntington dates from March 11, 1958 and runs under Indiana’s advisory planning law. The building code takes in the state Fire Prevention and Building Safety Commission’s rules as minimum standards. For a building that needs a state Construction Design Release, the CDR will not issue the local permit until it has a copy of the release and a full set of state-stamped plans.
Huntington building department: who handles permitting
The CDR is a combined planning, zoning, building and redevelopment department, led by Director Bryn Keplinger, with Shad Paul as Building Commissioner. It covers every property within the corporate limits; anything outside them, including the five towns, goes to the Huntington Countywide Department of Community Development at the courthouse. Its contact listing now gives the Temporary City Offices on West State Street, although some older city pages still send visitors to the City Building at 300 Cherry Street.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building permits | Community Development & Redevelopment Department, Temporary City Offices, 217 W State St, Huntington, IN 46750 |
| Phone / fax | (260) 356-5146 / (260) 454-5211 |
| Hours | 8 a.m. to 4:30 p.m., Monday to Friday; closed noon to 1 p.m. |
| Taps, drive cuts, right-of-way | City Engineer’s office (city switchboard (260) 356-1400) |
| Boards | Plan Commission, Board of Zoning Appeals, Historic Review Board, Development Plan and Subdivision Plat Committees |
| Outside city limits | Huntington Countywide DCD, (260) 358-4840 |
Plan Commission, Historic Review Board and Board of Zoning Appeals meeting dates are posted on the department’s calendar; the meetings are held at the Temporary City Offices.
Huntington permit types
The CDR keeps a separate form for each kind of project, and many of them need a site plan or other attachments. Staff will point you to the right one if the project is not obvious.
Residential permits
- Residential Dwelling Permit and Residential Dwelling Addition Permit for new homes and additions.
- Accessory Structure Permit, one form for buildings under 200 square feet and another for larger ones.
- Roof Alteration Permit for structural roof work, and Swimming Pool Permit.
- Deck & Deck Roof Permit (decks, ramps, three-season rooms) and Porch & Porch Roof Permit (open, roofed or enclosed porches).
- Fence Permit, Electrical Permit and Plumbing Permit.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings and additions use the Commercial Structure Permit, with the accessory structure forms for small outbuildings. Commercial fees step up by gross floor area, and larger sites may also need development plan approval. Signs use the Sign Permit, demolitions over 200 square feet the Demolition Permit, and engineered I-joists or trusses are reported on Form 393.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. Staff check the plan against the zoning code and map; variances and special exceptions go to the BZA and rezonings to the Plan Commission and Council.
- Historic review. Fifteen local single sites and the Drover Town district (eleven properties around Henry and South Jefferson Streets) need a Certificate of Appropriateness from the Historic Review Board for changes.
- Floodplain. Building in a Special Flood Hazard Area needs a floodplain development permit and an elevation certificate.
- Utilities and streets. The City Engineer’s office issues water and sewer taps and right-of-way permits; a new house typically needs a right-of-way permit plus drive approach and sidewalk add-ons.
- State release. Class 1 work needs its Construction Design Release and state-stamped plans before the local permit.
Huntington permit costs and fees
The Common Council passed Ordinance 6-C-26 on June 9, 2026, 6-0, replacing building, electrical and plumbing fees it said had not changed in more than 21 years, and the $0 fence fee. It took effect on October 1, 2026; the same night the Council also passed 7-C-26 (demolition fees) and 8-C-26 (zoning fees). Fees are rounded to the nearest whole dollar, and starting work before the permit is issued costs twice the regular fee.
| Work | Building | Electrical | Plumbing |
|---|---|---|---|
| New 1-, 2- or 3-family dwelling (per unit) | $0.08 per sq ft of gross floor area, $160 minimum | $120 | $85 |
| Addition | $0.08 per sq ft, $100 minimum | $50 | $50 |
| Manufactured home | $100 | $50 | – |
| Structural roof change | $45 | – | – |
| Deck, carport, open porch or enclosure | $50 | $50 | – |
| Accessory building, permanent / non-permanent foundation | $50 / $35 | $50 | $50 |
| In-ground / on-ground pool | $85 / $50 | $50 / – | – |
| Service upgrade, new or relocated service | – | $50 | – |
| Demolition 200–1,000 sq ft / over 1,000 sq ft | $25 / $50 | – | – |
| Fence / re-inspection | $10 / $40 | – / $40 | – / $40 |
Rather talk it over?
Call 1-855-478-4290 →| Work | Building | Electrical | Plumbing |
|---|---|---|---|
| New building, addition, accessory building or renovation up to 1,000 sq ft | $200 | $200 | $100 |
| 1,001–5,000 sq ft | $400 | $400 | $200 |
| 5,001–10,000 sq ft | $600 | $600 | $300 |
| Over 10,000 sq ft | $600 + $0.05 per sq ft | $600 + $0.05 per sq ft | $300 + $0.03 per sq ft |
| Demolition 200–1,000 / over 1,000 sq ft | $50 / $100 | – | – |
Worked example: a new house of 2,500 square feet of gross floor area is 2,500 × $0.08 = $200 for the building permit, plus $120 electrical and $85 plumbing, $405 in all; a 1,800-square-foot house works out to $144, so the $160 minimum applies. The department’s land-use table, also updated October 1, 2026, lists $400 for a rezoning, $250 for a variance or special exception ($200 for each extra request), $50 for a floodplain permit issued with a building permit ($35 without one) and $30 for a permanent on-premise sign. City utilities add their own charges: a 3/4-inch water tap is $1,250, a 5/8-inch meter $360 and its water system development fee $1,713, the matching sewer system development fee $2,780, and a new home’s right-of-way, drive approach and sidewalk permits $25 together.
Trade permits and who may pull them
- Electrical: the city’s electrical permit, also an improvement location permit, may be obtained by the property owner, who must be the deeded owner and live at the property, or by a Huntington County licensed electrician showing a valid license (a journeyman needs a master’s authorization). City code says electrical contractor licenses are issued by the Huntington Countywide DCD for the Board of Electrical Examiners and are valid across the county, city included. The form asks for the power company (Duke or REMC) and whether the service is overhead or underground.
- Plumbing: plumbing contractors working in the city need an Indiana State Plumbing Contractor’s license and must show it to the department; a person who owns and lives in a single- or two-family home may take out a plumbing permit for work on that property.
- Building and HVAC: the city pages list no local general contractor or HVAC license.
Rather not deal with the building department?
Get a free quote →How to apply for a Huntington building permit
Check that the parcel lies inside the corporate limits; if not, apply to the county DCD instead.
Visit or call the CDR; staff ask about the scope of the project and tell you which permit forms apply.
Get any BZA decision, Certificate of Appropriateness or floodplain permit the site needs.
Attach a site plan with property lines, easements, utility lines, legal drains, setbacks and building sizes, plus floor plans showing walls, outlets, fixtures, doors and windows.
Several staff members review the form, plans and site plan for building and zoning compliance.
Return to pay the fee and collect the permit and the permit card listing the required inspections.
Review, corrections and what causes delay
The department says a building permit takes about three to five days on average, depending on the project, and that an incomplete form or missing plans slow the review. The code text the city posts asks staff to decide applications within five business days where possible. Separate tap and right-of-way permits from the City Engineer’s office are a common cause of delay on new houses, so apply for them early.
Inspections in Huntington
The Building Commissioner carries out the inspections shown on the permit card, and the department also inspects in response to building and zoning complaints. Call or visit during business hours to book; advance scheduling is encouraged and life-safety inspections take priority.
- Footing, foundation and slab inspections: at least four hours’ notice before the earliest requested time.
- All other inspections: at least 24 hours’ notice.
- If a footing, foundation or slab inspection is not done within an hour of the scheduled time, concrete may be poured provided the work complies with the law.
- A re-inspection fee ($40) applies if a footing, foundation or slab inspection is not cancelled an hour ahead, another inspection three hours ahead, the work is incomplete or it fails; pay it before the re-inspection is booked.
Corrections must pass re-inspection before further work covers them. The electrical application states that a structure may not be used or occupied until a certificate of occupancy has been issued. The City Engineer’s office separately inspects sewer, water and right-of-way work on 24 hours’ notice.
Indiana building code in Huntington
The city’s building code combines six local codes in Chapter 150 and incorporates the state commission’s rules. FEMA’s Community Status Book lists the City of Huntington (community 180094) as participating in the National Flood Insurance Program, with maps effective June 2, 2015 and a Community Rating System class 7 (15% discount) since May 1, 2020; the city’s floodplain page still describes a class 8 rating worth 10% inside the flood zone and 5% outside it, so check the class with your insurer. The CDR Director serves as Floodplain Administrator and CRS Coordinator.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Huntington permit search and official resources
For copies of permits, plans or inspection records, the city takes public records requests through its NextRequest portal; the Clerk-Treasurer’s office ((260) 356-1400, ext. 2019) can help. For a quick status check on an open permit, call the CDR.
- Community Development and Redevelopment Department
- Building permits and application forms
- Permit application process
- CDR fee schedule (updated October 1, 2026)
- Ordinance 6-C-26, permit fee schedules
- Common Council minutes, June 9, 2026
- Building code administration
- Chapter 150 Building Code text
- Electrical permit application
- Inspection policy
- City Engineer permits and utility fees
- Floodplain management
- Historic preservation
- Public records requests
- Huntington Countywide DCD (outside city limits)
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Huntington building permit FAQs
Where do I apply for a building permit in Huntington?
At the Community Development and Redevelopment Department, now in the Temporary City Offices at 217 West State Street; call (260) 356-5146.
How much does a permit for a new house cost?
$0.08 per square foot of gross floor area with a $160 minimum, plus $120 for electrical and $85 for plumbing; a 2,500-square-foot house totals $405.
Do I need a permit for a small shed?
Yes. City code requires a permit for accessory structures regardless of size; the building fee is $50 on a permanent foundation or $35 without one.
Does a fence need a permit?
Yes, for a new fence or a change to an existing fence’s type or height. The fee rose from $0 to $10 on October 1, 2026.
Can a homeowner do electrical work?
The electrical permit form lets the deeded owner who lives at the property obtain the permit; otherwise a Huntington County licensed electrician must pull it.
How long does a permit take?
About three to five days on average, depending on the project; incomplete forms or missing plans add time.
My property is just outside the city. Who handles it?
The Huntington Countywide Department of Community Development at the courthouse, 201 North Jefferson Street.
Simplify Huntington permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Huntington sooner?
Let Alliance prepare, file, and track your Huntington permits while your crew stays on the job.
More Indiana permitting guides
Huntington County
Read guide →Wabash County
Read guide →Wells County
Read guide →Indianapolis Building Permit Guide
Read guide →Jackson County Building Permit Guide
Read guide →Jasper Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Huntington permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.