Outside the City of Huntington, building permits in Huntington County come from the Huntington Countywide Department of Community Development (DCD), Room 204 of the courthouse at 201 North Jefferson Street ((260) 358-4840). The DCD covers the unincorporated county and the towns of Andrews, Markle, Mount Etna, Roanoke and Warren, licenses electrical contractors, assigns addresses and acts as floodplain administrator. Permits are filed through the Geo Permitting site or at the office, and Ordinance 2026-15 sets a new house at $0.08 a square foot with a $160 minimum.
What requires a building permit in Huntington County?
The DCD publishes its own list of work that needs a permit, and Ordinance 2018-8, the Huntington County Building Code adopted by the Board of Commissioners on July 9, 2018, sets the legal rule. The panels below set the main triggers against the exemptions.
Building permit
- New one-, two- and multi-family homes, and manufactured or mobile homes (a single-wide needs an extra approval)
- Commercial buildings, commercial additions and interior commercial renovations
- Attached or detached garages, pole barns, sheds, carports and pergolas
- Additions, decks, porches (new, rebuilt or enclosed) and in-ground or above-ground pools
- Ponds and structural roof changes
No building permit
- New shingles laid on an existing roof (no roof may carry more than two layers)
- Agricultural buildings on a tract of 10 acres or more
- Livestock buildings where the livestock operation is registered with the DCD, and grain bins
- Accessory structures under 200 square feet
The exemptions in the right-hand panel come from Section 7 of the building code, which adds that an improvement location permit under the county zoning ordinance is still needed where no building permit is. Electrical permits cover upgrades, new or relocated services, branch circuits and the hook-up of a manufactured home; plumbing permits cover new homes, additions, accessory buildings with plumbing and added fixtures. Fences, signs, ponds and any development in a mapped flood hazard area need their own permits.
What the county decides and what the state holds
The county sets its own permit list, fees, inspection rules, electrical licensing and zoning through the building code, the Unified Development Ordinance (UDO) and the subdivision code, and each of the five towns has its own building code that the DCD administers. Nonresidential projects may need a state Construction Design Release from the Indiana Department of Homeland Security before the DCD can issue a local permit. Ordinance 2026-04, adopted February 23, 2026, put a moratorium on data centers, battery energy storage and carbon sequestration projects while the Plan Commission drafts rules; a proposed data center ordinance and a draft UDO rewrite (posted November 16, 2026) are not yet adopted.
Huntington County building department: who handles permitting
The DCD is the building department for every part of the county except the City of Huntington, which runs its own Community Development and Redevelopment Department inside city limits. Kim Hostetler is the DCD’s Executive Director and a Certified Floodplain Manager.
Short on time to read all of this?
Get a free quote →| Place | Permit office |
|---|---|
| Unincorporated county | Huntington Countywide DCD |
| Andrews (pop. 1,062), Mount Etna (114), Roanoke (1,811), Warren (1,209) | Countywide DCD, under each town’s building code |
| Markle (582 people in this county; the town also extends into a neighboring county) | Countywide DCD for the Huntington County part |
| City of Huntington (17,167) | City Community Development and Redevelopment Department |
| Detail | Information |
|---|---|
| Office | Room 204, Huntington County Courthouse, 201 N Jefferson St, Huntington, IN 46750 |
| Phone / fax | (260) 358-4840 / (260) 355-2313 |
| Hours | 8 a.m. to 4:30 p.m., Monday through Friday |
| Online filing | Geo Permitting, jurisdiction “Huntington County, Indiana” |
To find out which office covers an address, look the parcel up on the county GIS site and switch on the County/Town Zoning layer, or call the DCD.
Huntington County permit types
Most permits are filed on the Geo Permitting site: create an account, choose Huntington County, Indiana as the jurisdiction and click apply next to the project type; staff also help at the counter.
Residential permits
- Residential Structure Permit: new dwellings, additions, roof alterations and accessory buildings.
- Deck/Porch/3-Season Room Permit: wood decks and deck roofs, concrete porches and porch roofs.
- Swimming Pool/Pond Permit: pools of either kind and ponds; pool applications must show the safety features.
- Mechanical Permit: the form used for both electrical and plumbing work.
- Fence/Sign Permit: fences and signs.
A manufactured, mobile or modular home also needs its foundation specifications and a copy of the installer’s state license.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings, remodels and commercial accessory buildings go on the Commercial Structure Permit. Signs, billboards and solar or wind systems are priced separately, and multi-family, commercial, industrial and institutional sites need development plan approval from the Development Plan Committee. A new business moving into tenant space must book a certificate of occupancy inspection.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. The UDO sets the districts; a rezoning goes to the Plan Commission, and variances and special exceptions to the Board of Zoning Appeals.
- Well and septic. In the unincorporated county a new home, or an addition that adds bedrooms, needs approved well and septic permits from the Huntington County Department of Health, Courthouse Annex, 1330 S. Jefferson Street ((260) 358-4831).
- Water and sewer taps. New homes inside a town or on city utilities may need tap permits from the City Engineering Department or the town clerk-treasurer of Andrews, Markle, Roanoke or Warren; Mount Etna requires none.
- Drive cuts. A new home with access to a public road needs a drive cut permit from the County Highway Department (1601 Riverside Drive, (260) 358-4881), the city, Andrews, Roanoke or INDOT’s Fort Wayne office; Markle, Mount Etna and Warren require none.
- Drains and floodplain. The site plan must show county regulated legal drains, and work in a flood hazard area needs a floodplain development permit (see below).
- State release. Nonresidential work that needs a Construction Design Release must have it before the local permit is issued.
Huntington County permit costs and fees
The commissioners replaced the DCD fee schedule with Ordinance 2026-15 on June 15, 2026; building fees had last changed in 2004 and zoning fees in 2009. The new fees took effect 90 days after publication, and no earlier than September 15, 2026, for the unincorporated county. The posted ordinance omits its attachment, so the amounts below are the “New Fee (2026)” column of the DCD fee page; ask which fees apply inside a town.
| Permit | Fee |
|---|---|
| Single-family, two-family or multi-family dwelling | $0.08 per sq ft, $160 minimum |
| Residential addition | $0.08 per sq ft, $100 minimum |
| Manufactured home / roof alteration | $100 / $45 |
| Deck, carport or enclosure; accessory building on a permanent foundation | $50 each |
| Accessory building without a permanent foundation / under 200 sq ft | $35 / $20 |
| In-ground pool / above-ground pool | $85 / $50 |
| Residential electrical: new 1-, 2- or 3-family dwelling / addition or other work | $120 / $50 |
| Residential plumbing: new dwelling / addition or accessory building | $85 / $50 |
| Commercial building or remodel (building and electrical, each) | $200 to 1,000 sq ft; $400 to 5,000; $600 to 10,000; $600 + $0.05 per sq ft over 10,000 |
| Commercial plumbing, new structure | $200 to 5,000 sq ft; $300 to 10,000; $300 + $0.03 per sq ft over 10,000 |
| Fence / pond / floodplain development | $10 / $50 / $50 |
| Solar or wind energy system | $750 |
| Re-inspection / missed inspection | $50 / $100 |
| Rezoning / BZA variance or special exception | $500 ($750 for EUD) / $250, plus $200 per added request |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a 2,400-square-foot house pays 2,400 × $0.08 = $192, plus $120 electrical and $85 plumbing, or $397; below 2,000 square feet the $160 minimum applies.
A pond started or finished without a permit costs $250, and building a pond inside a required setback before going to the BZA costs $1,000. Under the building code, starting work that needs a permit before the permit is issued doubles the regular fee, and a change of occupancy made without a certificate of occupancy can carry a $15 penalty.
Trade permits and who may pull them
Electrical and plumbing permits are filed on the DCD’s Mechanical Permit form and inspected by the Building Commissioner, who serves as the county’s electrical and plumbing inspector.
- Electrical: anyone in the business of installing or altering wiring that needs a permit must hold an electrical contractor’s license issued through the DCD for the Board of Electrical Examiners, whose members are appointed by both the mayor of Huntington and the county commissioners. The county ordinance sets two classes, Class I Master Electrician and Class II Journeyman; applicants pay $50, show their experience and sit an ICC or Prometric exam unless the board accepts an outside license. The city code states that this license is valid throughout the county, city included. A person who owns and lives in a single- or two-family home may take out an electrical permit for work in that home or other buildings on the same property.
- Plumbing: plumbing permits go only to holders of an Indiana State Plumbing Contractor License, or someone employed by one, who sign the application. The owner-occupant of a single- or two-family home may take out a plumbing permit for work in that home or on the same property.
- HVAC and general contractors: the county pages show no separate HVAC or general contractor license.
Rather not deal with the Huntington County building department?
Get a free quote →How to apply for a Huntington County building permit
Check that the parcel is outside Huntington city limits and note its zoning district and any flood zone or floodway on the county GIS.
Get the health department’s well and septic approvals, any water or sewer tap permits and the drive cut permit before you file.
Show property lines, roads and alleys, easements and utility lines, legal drains, parking, every existing and proposed structure, setbacks and building sizes.
Pick the right form, upload plans and, for a new home, the third-party energy compliance information; the office will help at the counter.
For a new home, flag the final driveway location on site so the DCD can assign an emergency address, and attach the drive cut permit.
Pay online or at the office, then post the permit card where it is protected from the weather until the final inspection.
Review, corrections and what causes delay
The building code asks the DCD to try to decide applications within 72 hours of filing, longer when a project needs more review. Missing tap or drive cut permits hold up a new-home permit, because copies must be in hand before it can issue, and nonresidential work waits for the state release and a full set of plans. A permit expires if the work is not finished within two years. Since January 1, 2026 state law also gives local units deadlines for one- and two-family plan reviews and inspections, with a private reviewer as a fallback.
Inspections and certificates of occupancy
The inspections a job needs are marked on the permit card, and the permit holder calls the DCD to book each one when the work is ready. Notice rules come straight from Ordinance 2018-8:
- Footing, foundation and slab inspections need at least four hours’ notice; all other inspections need 24 hours.
- Framing, fire blocking, bracing, pipes, chimneys, rough electrical, rough plumbing and heating are inspected in one visit, not separately.
- If a footing, foundation or slab inspection has not happened within an hour of the time set by the DCD, concrete may be poured as long as the work complies with the law.
- A $50 re-inspection fee can apply when a footing inspection is not cancelled an hour ahead, another inspection three hours ahead, or the work is unfinished or fails; it is paid before the re-inspection is booked.
No new building, change of use or change of occupancy may be used without a certificate of occupancy, which costs nothing when it follows a building permit. The Building Commissioner can issue a temporary certificate for up to six months when nothing poses an immediate danger.
Indiana building code in Huntington County
Ordinance 2018-8 adopts the state Fire Prevention and Building Safety Commission’s rules by reference, with later amendments. FEMA’s Community Status Book lists unincorporated Huntington County (community 180438) as participating in the National Flood Insurance Program, with maps effective June 2, 2015 and a Community Rating System class 7. The DCD enforces Section 917, the Flood Hazard Area Overlay District, for the county and the five towns; Base Flood Elevations can be requested as an eFARA through the state’s INFIP map, and a floodway site needs an IDNR Division of Water permit first.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Huntington County permit search and official resources
Permit records for county and town properties are kept by the DCD, which must keep a record of every permit it issues. Ask the office about a parcel by phone, or file the county’s online Access to Public Records Request form for copies. Recorded legal drains and drainage questions go to the County Surveyor, Room 203 of the courthouse ((260) 358-4856), whose Drainage Board meets at 8:30 a.m. on scheduled dates.
- Huntington Countywide Department of Community Development
- What requires a permit?
- Building permit submittal requirements
- Applications and permits (online filing instructions)
- Geo Permitting online permit site
- DCD fee schedule (2026 fees)
- Ordinance 2026-15, new DCD fee schedule
- Huntington County Building Code, Ordinance 2018-8
- County and town codes and ordinances
- Floodplain management
- Ordinance 2026-04, data center and battery storage moratorium
- Board of Electrical Examiners
- County Surveyor and Drainage Board
- County public records request form
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Huntington County building permit FAQs
Does the county issue permits inside the City of Huntington?
No. The DCD covers the unincorporated county and Andrews, Markle, Mount Etna, Roanoke and Warren; the city’s own Community Development and Redevelopment Department handles property inside city limits.
How much is a permit for a new house?
The building permit is $0.08 per square foot with a $160 minimum under the 2026 schedule, plus $120 for electrical and $85 for plumbing on a new dwelling.
Do I need a permit to reroof?
Not for new shingles alone, but no roof may have more than two layers. Structural roof changes need a permit, which costs $45 for a house.
Is a small shed exempt?
A building under 200 square feet needs no building permit under the county code, but the zoning ordinance still calls for an improvement location permit; the 2026 schedule lists $20 for an accessory structure under 200 square feet.
Can I wire or plumb my own house?
Yes, if you own and live in the single- or two-family home; you may take out the electrical or plumbing permit yourself for work there.
What do I need from the health department?
In the unincorporated county, approved well and septic permits must come with any new-home application, and with additions that add bedrooms.
Simplify Huntington County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Huntington County sooner?
Let Alliance prepare, file, and track your Huntington County permits while your crew stays on the job.
More Indiana permitting guides
Huntington
Read guide →Wabash County
Read guide →Wells County
Read guide →Indianapolis Building Permit Guide
Read guide →Jackson County Building Permit Guide
Read guide →Jasper Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Huntington County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.