In the Town of Highland, permits come from the Building & Inspection Department at the Highland Municipal Building, 3333 Ridge Road (219-972-7595), headed by Building Commissioner and Chief Inspector Ken Mika. All contracted work must be done by contractors licensed with the town, and the department’s posted fee sheet charges a building permit at $54 for the first $1,000 of valuation plus $16.50 for each further $1,000.
What requires a building permit in Highland?
Highland’s forms show what the department permits: new construction, additions and remodels on the building application; siding, windows, roofs and fences on a remodeling and fence application; interior remodeling on its own form; and separate electrical, plumbing and heating and cooling permits. Its application tells owners to check building and zoning rules with the department before construction starts.
Building permits
- New houses and buildings, room additions, sunrooms and enclosed porches
- Open decks, with a framing drawing
- Interior remodeling
- Siding, window and roof replacement
- Fences, with a plat of survey
- Above-ground and in-ground swimming pools
- Signs, demolition (razing) and underground tank removal
Trade and other permits
- Electrical: new service, updates, rewiring, repairs, room additions, garage wiring, signs, pools, temporary poles and early service
- Plumbing, including underground work, lawn and fire sprinklers
- Heating and cooling equipment
- Right-of-way cuts and road jacking or sleeving
- Reconnection inspections
- Home occupations, through a notification form signed by the zoning administrator
The department does not post a list of work that is exempt, so a job that is not on one of its forms is a question for the office at 219-972-7595.
What Highland decides and what the state holds
The town sets its permit fees, licenses contractors under Chapter 5.20 of the Highland Municipal Code, runs zoning through its Plan Commission and Board of Zoning Appeals, and requires a certificate of occupancy before any new structure is used. Technical standards are the state’s: the pool packet, for example, cites the Indiana Swimming Pool Code (675 IAC 20) and the National Electrical Code. A commercial or other Class 1 building also needs the state Construction Design Release from the Indiana Department of Homeland Security before construction, unless 675 IAC 12-6-4 exempts the work.
Highland building department: who handles permitting
The Building & Inspection Department issues all building and trade permits inside Highland’s town limits and inspects the work, with associate inspectors for electrical and plumbing and a code enforcement officer on staff. It keeps lists of licensed contractors, plumbers, electricians and lawn maintenance companies so residents can check a firm before hiring it. The Building Commissioner also coordinates the town’s ADA compliance program. Lake County’s Plan Commission covers only unincorporated land and does not issue permits in Highland.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Highland Municipal Building, 3333 Ridge Road, Highland, IN 46322 |
| Phone / fax | 219-972-7595 / 219-972-5097 (Town Hall main line 219-838-1080) |
| Hours | Monday to Friday, 8:30 a.m. to 4:30 p.m. |
| Building Commissioner | Ken Mika, Chief Inspector and Building Commissioner |
| How forms are filed | Download the PDF, then fax or email it to the department, or bring it in |
| Boards | Plan Commission (seven members) and Advisory Board of Zoning Appeals (five members) |
Highland permit types
The Building Permit Application requires a plat of survey, the contract cost and the signatures of both the contractor and the property owner, or a signed copy of their contract. The office section of the form records any BZA or Plan Commission approval, the number of inspections, and the permit, inspection and plan review fees before the Building Commissioner signs it.
Residential permits
- New houses and additions use the Building Permit Application, which asks for the structure size, height, construction type, footing size, foundation walls, floor and ceiling joist spacing, roof rafters and roofing.
- Room additions, sunrooms and enclosed porches follow the Building Commissioner’s guidelines: show on the survey where the addition attaches, with dimensions, and provide a framing drawing of footings, walls, roof and the tie-in to the house, the existing floor plan with doors, windows and vents, and the use of each room. Open decks need a framing drawing of posts, joists, guardrails and handrails.
- Siding, windows, roofs and fences share one form; the contract cost is mandatory and a fence needs a survey showing its location, type and height.
- Pools need a survey showing the pool and any overhead or underground power lines, utility locates before the pre-pool inspection, and an electrical permit issued before the pool permit.
- Home occupations are limited to one room and no more than 25 percent of the ground floor, with at most one employee from outside the family, under the zoning rules in HMC 18.05.060(H).
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects use the same building application with the commercial plan review fee. Larger jobs carry extra license conditions: under Ordinance 1710, contractors on commercial work estimated at $250,000 or more, or on residential buildings of five or more units, must keep workers’ compensation in place, classify workers as employees, hand payroll records to the Building Commissioner within five days of a request, and have no debarment or wage, tax or prevailing-wage violations in the previous three years. If a contractor breaks those conditions, the ordinance treats the permit as temporarily suspended.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning. Variances, special exceptions and conditional uses go to the Board of Zoning Appeals; rezoning, PUDs and subdivisions go to the Plan Commission, which publishes a rezoning outline, application and checklist.
- Flood zones. The building application asks for the flood protection grade of the first floor and whether the lot is in the floodway, flood fringe or flood plain district.
- Right of way. Cuts into the right of way need a right-of-way cut permit, and road jacking or sleeving has its own fee.
- Utilities. Water and sewer taps and meters are priced on the same fee sheet, and every digging job starts with an 811 call.
- State design release. Class 1 projects need the IDHS release before construction.
Highland permit costs and fees
The department posts a single fee sheet headed “Town of Highland Permit Fees and Charges as of July 1, 2020”, with the Plan Commission and BZA fees adopted by Resolution 2019-03 on May 15, 2019. Electrical and plumbing permits each carry a $63 filing fee on top of the work charges.
| Item | Fee |
|---|---|
| Building permit, valuation $100 to $1,000 | $54 |
| Each additional $1,000 of valuation or fraction | $16.50 |
| Plan review | $90 residential; $268.50 commercial |
| Inspections | $54 each ($108 for two, $162 for three, $216 for four) |
| Wrecking (demolition) | $54 up to 500 sq ft; $81.50 for 501–2,500 sq ft; $97.75 for each additional 2,500 sq ft |
| Swimming pool permit / pool pre-inspection | $54 / $54 |
| Electrical | $63 filing fee; single phase $1.10 per amp ($110 at 100 amps, $220 at 200 amps); three phase $1.20 per amp; temporary pole $46; remodeling $89 |
| HVAC permit | $54 |
| Plumbing | $63 filing fee; $11.85 per fixture; $46 minimum inspection; underground $41; remodeling $89 |
| Re-inspections (red tags) | $46 first; $63.25 (building) or $63 (electrical, plumbing) second; $89 after that |
| Water tap / sewer tap | $200 residential, $330 commercial / $300 one- and two-family, $500 three or more units and commercial, $700 industrial |
| Contractor license | $35.50 application plus $70.50 license ($106) |
| BZA variance | $150 residential; $200 business or industrial |
| Rezoning / PUD | $300 / $300 for the first 5 acres plus $60 per additional acre |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the sheet: a project valued at $25,000 pays $54 for the first $1,000 plus 24 × $16.50 ($396) for the remaining $24,000, a building permit of $450, before the plan review, inspection and any trade fees. Highland’s fees for garbage, sanitary service and water use are on separate Clerk-Treasurer schedules.
Trade permits and who may pull them
Highland issues separate electrical, plumbing and heating and cooling permits, and every contracted trade on the building application must be licensed with the town.
- Contractor license. One Contractor License/Registration Application covers general, electrical, HVAC, plumbing and other trades. It needs two Lake County references, a driver’s license copy, the $106 fee, a $5,000 Lake County bond carrying the Recorder’s stamp, insurance of at least $100,000 liability and $50,000 property damage naming the town as holder, and workers’ compensation or a state exemption certificate. Renewals use a separate form.
- Electrical contractors pass the town’s open-book exam, given on the first Wednesday of the month with applicants bringing their own code book; the $48 fee is due by the Monday before, and phones and other devices are not allowed.
- Plumbing contractors give their State of Indiana plumbing license number on the town application.
- Homeowner electrical work. An owner who has lived in the house for at least two years may take the homeowner electrical exam ($48, filed seven days ahead) and do the wiring to approved plans. Work on the service panel, meter socket or raceway requires proof of four consecutive years working for an electrical contractor.
- Pools. The GFCI circuit for a pool filter must be installed by an electrical contractor licensed with Highland.
How to apply for a Highland building permit
Call 219-972-7595 to confirm setbacks and whether the job needs a BZA or Plan Commission approval.
Each contracted trade must hold a current Highland license; check the department’s lists before hiring.
Building, remodeling and fence, interior remodeling, pool, sign, razing or right-of-way, plus electrical, plumbing and heating permits for the trades.
A plat of survey for new work, fences and pools, framing drawings for additions and decks, and the contract or contract cost.
Send the completed PDF to fax 219-972-5097 or by email, or bring it to 3333 Ridge Road.
Permit, plan review and inspection fees are set from the fee sheet when the Building Commissioner approves the application.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
The Building Commissioner’s own guidance says that complete survey and framing information prevents plan review delays on additions, sunrooms and decks. The forms also set hard requirements: every contracted trade licensed with the town, a bond carrying the Lake County Recorder’s stamp, and, for a pool, an electrical permit issued before the pool permit. Work that needs a variance takes longer, since the BZA meets once a month and its decisions go to the Town Council, which may accept or reject them.
Inspections and certificates in Highland
The number of inspections is set when the permit is approved and is charged at $54 each, so a job needing three inspections adds $162. Electrical and plumbing work is inspected by the department’s associate inspectors, and a red tag means a re-inspection fee before the inspector returns. Pools get a pre-pool inspection of the site after underground utilities are marked.
A certificate of occupancy must be issued before a new structure is occupied. Demolition permits run for only 10 days under HMC 15.35.010, unless the town inspector extends them; the contractor must ask the inspector which barricade to use and get permission from public works and the police before blocking a street, sidewalk or alley.
Indiana building code in Highland
Highland enforces Indiana’s building rules through its Building & Inspection Department, and its local rules sit in the Highland Municipal Code, published online through Code Publishing. FEMA’s Community Status Book lists the Town of Highland (community 185176) as participating in the National Flood Insurance Program, with flood maps effective March 16, 2016.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Highland permit search and official resources
Highland’s permits are handled on PDF forms by fax, email and at the counter, so questions about an open permit, an inspection result or a contractor’s license go to the Building & Inspection Department at 219-972-7595. Plan Commission and BZA agendas, minutes and recordings are posted on each board’s page, and a final draft of the town’s new Comprehensive Plan was posted in November 2026.
Want this handled start to finish?
Get a free quote →- Highland Building & Inspection Department and forms
- Building Permit Application
- Remodeling / Fence Permit Application
- Interior Remodeling Permit Application
- Guidelines for room additions, sunrooms and porches
- Electrical Permit Application
- Plumbing Permit
- Heating and Cooling Permit
- Swimming Pool Installation Application and regulations
- Permit fees and charges as of July 1, 2020
- Contractor License/Registration Application
- Ordinance 1710, contractor license conditions
- Electrical Contractors Exam Application (Nov. 2025)
- Homeowner’s Electrical Exam Application
- Razing instructions (HMC Chapter 15.35)
- Right-of-way Cut Permit Application
- Plan Commission
- Board of Zoning Appeals
- Town of Highland
- Indiana Fire Prevention and Building Safety Commission rules
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Highland building permit FAQs
How much is a building permit in Highland?
$54 for valuation up to $1,000 plus $16.50 for each additional $1,000, so a $25,000 job is $450, plus $90 residential plan review and $54 per inspection.
Do I need a permit for a fence?
Yes. Fences use the Remodeling/Fence Permit Application, and a plat of survey showing the fence location must be submitted with it.
Can I do my own electrical work in Highland?
Only after passing the homeowner electrical exam, open to owners who have lived in the house for at least two years; service panel work needs four years’ employment with an electrical contractor.
What does a contractor license cost?
$106, made up of a $35.50 application fee and a $70.50 license fee, plus a recorded $5,000 Lake County bond and insurance.
Do I need a permit for an above-ground pool?
Yes. A pool needs a survey, a pre-pool inspection and an electrical permit pulled by a Highland-licensed electrician before the pool permit is issued.
When does the Board of Zoning Appeals meet?
On the fourth Wednesday of the month at 6:30 p.m.; November and December dates may move for the holidays, so call 219-972-7595 to confirm.
How long is a demolition permit good for?
Ten days under the town code, unless the town inspector extends it.
Simplify Highland permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Highland sooner?
Let Alliance prepare, file, and track your Highland permits while your crew stays on the job.
More Indiana permitting guides
Lake County
Read guide →Hobart
Read guide →Lake Station
Read guide →Howard County Building Permit Guide
Read guide →Huntington Building Permit Guide
Read guide →Huntington County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Highland permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.