White County, Indiana Building Permit Guide

To get a building permit in White County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

White County Building & Planning, on the second floor of the Government Center at 110 North Main Street in Monticello, runs the Area Plan office and the building inspector’s office and takes residential, commercial and ILP applications online.

Authority: White County Building & PlanningFees: Adopted August 21, 2017Phone: 574-583-7355
Authority
Building & Planning110 N. Main St., Monticello
New house fee
$0.14 per sq ft$175 minimum
Plan review
7 business daysAfter a complete application
Zoning area
County, Monticelloand six member towns

In White County, building permits, improvement location permits and inspections are handled by White County Building & Planning: the Area Plan office and the building inspector’s office, both on the second floor of the White County Government Center, 110 North Main Street, Monticello (574-583-7355). Jenilynne Kyburz is the Area Plan Executive Director. A new conventional house costs $0.14 per square foot with a $175 minimum under the construction fee schedule adopted August 21, 2017, and the office promises a plan review within 7 business days of a complete application.

What requires a permit in White County?

The county’s construction fee schedule doubles as its permit list. It covers new homes and additions, remodels, accessory buildings, decks and pools, electrical, mechanical, plumbing and structural upgrades, commercial and industrial buildings, and farm structures, and it names the work that is exempt. The Area Plan fee schedule adds zoning permits for fences, solar systems, signs, antennas, public electric vehicle chargers, temporary uses and other work that needs no building permit.

Building permit needed

  • New conventional, modular and manufactured homes
  • Additions and remodels
  • Detached garages, pole barns, lean-tos, gazebos, pergolas and sheds over 200 square feet
  • Decks, permanent pools, spas, ramps and retaining walls 30 inches above grade
  • Electrical, generator, meter, HVAC, plumbing and structural upgrades
  • Barns, grain bins and confined feeding buildings

Exempt from the building permit

  • Replacing windows with the same size
  • Roof replacement with no change to the roof line or rafters
  • Siding
  • Painting

Starting work before the permit is issued raises the fee by 50% of the calculated amount, up to $300. The zoning ordinance allows only one dwelling on a single tract of land, and fences need a $35 zoning permit.

What White County decides and what the state holds

The county sets its own fee schedules, zoning and subdivision ordinances and flood hazard regulations, and since 2026 its Class 2 handout follows the state deadlines in IC 36-7-2.5. The fee schedule states that a commercial design release is required before a local building permit is issued for commercial work, matching the state rule that a Class 1 structure needs a Construction Design Release before construction unless 675 IAC 12-6-4 exempts it.

White County building department: who handles permitting

The White County Area Plan Commission’s zoning ordinance covers all of White County except any city or town that is not a member; it was adopted by the county, the City of Monticello and the towns of Brookston, Burnettsville, Chalmers, Monon, Reynolds and Wolcott. The Area Plan office handles zoning, improvement location permits and the floodplain program, and the building inspector’s office in the same suite reviews plans and inspects. The county pages show no separate building department for Monticello or the towns, and Monticello’s own site lists only a right-of-way permit; confirm with Building & Planning that your address is in its building permit area.

Short on time to read all of this?

Get a free quote →
White County Building & Planning contacts
DetailInformation
OfficeWhite County Government Center, second floor, 110 N. Main St., Monticello, IN 47960 (mail: P.O. Box 851)
Phone574-583-7355
HoursMonday to Friday, 8:00 a.m. to 4:00 p.m., closed holidays
Area Plan Executive DirectorJenilynne Kyburz
Online applicationsSBS Portals: residential, commercial, ILP and inspections
Health Department (septic)902 Foxwood Ct., Monticello; 574-583-2436
Twin Lakes Regional Sewer District574-583-5649

White County permit types

Residential, commercial and ILP applications, and inspection requests, can be filed through the county’s SBS Portals online service, or on the paper forms posted on the Area Plan and Building and Floodplain pages. Submitted building information is held for 90 days at most; after that it must be resubmitted.

Residential permits

  • Application and record card. The form with the estimated construction value and the contractor’s details, plus the property record card.
  • Site plan. Size of the structure, distances to property lines or road rights-of-way (whichever is more restrictive, not to the road center), distances to other buildings, height to the peak, a north arrow, driveways and road names.
  • Construction drawings. Dimensioned floor plans with window sizes, framing plans or a cross-section, electric panel location, at least one elevation, foundation design and truss drawings, plus the energy code path and a truss and I-joist location form.
  • Manufactured homes. A title in your name showing the home was built in 1981 or later, and its installation instructions.
  • Farm neighbors. On or next to land zoned A-1 or A-2, a signed Notice of Agricultural Operations.

Commercial permits

Commercial and industrial buildings and additions are charged $0.10 per square foot with a $200 minimum, and remodels $0.08 with a $125 minimum. The design release must be issued before the county permit. Non-profits and school corporations pay $0.06 per square foot ($100 minimum) with a tax-exempt number, and range hoods, tanks, pools and sprinkler systems are specialized structures at $125 each.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Sewer or septic. Inside the Twin Lakes Regional Sewer District, a tap permit or a letter that none is needed; elsewhere, a Health Department septic permit or a letter that none is needed. No permit is issued until written confirmation arrives.
  • Drainage. The Area Plan office sends applications to the Surveyor’s Office to decide whether a drainage permit is needed.
  • Driveway. Approval from the county highway department (219-984-5851), the City of Monticello street department (574-583-7033) or the state highway office (574-583-4173), depending on the road; submit the approval to Building & Planning.
  • Covenants. Subdivision covenants and restrictions are the owner’s responsibility; copies are at the Recorder’s Office in the courthouse.
  • Lakes and floods. Waterfront lots may sit in a flood area needing IDNR approval and may carry a Shafer and Freeman Lakes Environmental Conservation Corporation easement along the shore.
⚠️ Data centers. Ordinance 2025-10-20-02 froze all applications and permits for data centers in unincorporated White County from October 20, 2025 until April 20, 2026, or until the comprehensive plan and zoning ordinance were amended. Ask the Area Plan office what rules apply now.

White County permit costs and fees

Building fees come from the White County Building and Planning Construction Permit Fees adopted August 21, 2017, which the 2026 Class 2 handout repeats; zoning fees come from the Area Plan fee schedule effective January 1, 2024. The fee is based on the type of project and its total square footage. The 2017 sheet accepts cash or check only, and no certificate of occupancy is issued until every fee is paid.

Rather talk it over?

Call 1-855-478-4290 →
White County construction permit fees (adopted August 21, 2017)
WorkFee
New conventional house (single or two-family)$0.14 per sq ft; $175 minimum
Modular or manufactured home$0.10 per sq ft; $125 minimum
Addition (larger footprint or height) / remodel$0.14 per sq ft, $75 min / $0.12 per sq ft, $60 min
Primary accessory: garage, pole barn, shed over 200 sq ft$0.10 per sq ft; $35 minimum
Secondary accessory: deck, small shed, pool, spa, ramp$35
Upgrade: electrical, HVAC, plumbing, structural, generator$35 single; $70 for several at once
Multi-family new building$0.14 per sq ft; $400 minimum
Commercial or industrial new building or addition$0.10 per sq ft; $200 minimum
Farm storage building / confined feeding$0.01 per sq ft, $35 min / $0.03 per sq ft, $125 min
Grain bins$75 first bin; $25 each additional built at the same time
Re-inspection or extra inspection$35 each
Failure to request a required inspection$50 per inspection
Permit renewal or extension50% of the original fee; expired permits need a new application

Area Plan fees include $35 for an improvement location permit when no building permit is required, $35 for a fence, $75 for an individual solar system, $200 for a rezoning and $275 for a variance or special exception. Worked example from the 2017 schedule: a 2,000-square-foot conventional house is 2,000 × $0.14 = $280, above the $175 minimum; a 600-square-foot detached garage adds 600 × $0.10 = $60 and a deck $35, for $375. Choosing a private plan reviewer or inspector under IC 36-7-2.5 adds a $100 convenience fee. The schedule lists sheds over 200 square feet as primary accessory structures but sheds under 350 square feet as secondary, so ask which rate applies to a shed between those sizes.

Trade permits and who may pull them

White County prices trade work as upgrades: a single electrical, generator, meter inspection, HVAC, plumbing or structural upgrade is $35, and several done at once are $70. On a new house or addition, the trade inspections run under the building permit, including rough-in electric and plumbing, plumbing pressure tests, temporary and permanent electric service, pool bonding and HVAC.

  • Application: the residential form asks for the contractor’s name, address and phone.
  • Electrical standard: the 2026 handout asks applicants to state whether the electrical work will follow the 2020 Indiana Residential Code or the 2008 NEC; if not stated, the residential code applies.
  • Plumbing: plumbing contractors hold state licenses; sewer work in the Twin Lakes district must use a TLRSD qualified contractor.
  • Private reviewers: owners may pick a qualifying architect, engineer or certified building official for plan review and inspections, chosen at application and not changed later.

Rather not deal with the White County building department?

Get a free quote →

The county pages set no local contractor license; ask Building & Planning how owner-built work is handled before you file.

How to apply for a White County building permit

1. Gather approvals

Sewer tap or septic confirmation, driveway approval and, on the water, flood and easement information.

2. Mark the site

Physically mark structure corners, property lines, the driveway center and any wetland or floodplain edge.

3. Prepare the package

Application, property record card, site plan, construction drawings, energy path and agricultural notice if needed.

4. Choose the reviewer

County staff, or a qualifying private reviewer and inspector named on the application.

5. Submit online or in person

Use SBS Portals or bring the forms to 110 North Main Street.

6. Pay and book inspections

Pay by cash or check, then call for the required inspections.

Review, corrections and what causes delay

Within 3 business days of submittal the office emails whether the application is complete or lists what is missing; if you do not confirm receipt within 3 business days, the notice is also mailed. Plan review follows within 7 business days of a complete application. No permit is issued without the TLRSD or Health Department letter, site plan distances must be measured to the property line or right-of-way rather than the road center, and the drawings must include the truss drawings. Passing plan review does not waive any variance or approval still needed.

Inspections and certificates in White County

Inspections are requested in writing, using the county’s inspection notification form or the online portal, and staff aim to inspect within 3 business days. The 2026 handout lists the stages that may apply: setback, floodplain and elevation checks, footer, post hole, forms, foundation, basement, underslab, plumbing pressure test, framing, tie-downs, HVAC, rough-in electric and plumbing, temporary and permanent electric service, pool bonding, pre-drywall, siding, roofing, and final.

A re-inspection or extra inspection costs $35, and failing to request a required inspection costs $50. The certificate of occupancy follows the final inspection; failing to obtain one carries a charge of $10 to $300 per day. Call before you dig at 800-382-5544, with 72 hours’ notice.

Indiana building code in White County

The county’s flood hazard area regulations, in their April 24, 2024 form, set the flood protection grade at the base flood elevation plus 2 feet, and construction in a floodway also needs an IDNR permit. FEMA’s Community Status Book lists unincorporated White County (community 180447) as participating in the National Flood Insurance Program, with its current flood map dated January 8, 2014; the office provides FEMA elevation certificate and LOMA forms.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

White County permit search and official resources

The SBS Portals system holds the online permit and inspection requests and the posted APC and BZA minutes. For older files or a property record card, contact Building & Planning at 574-583-7355; zoning certifications cost $100 without an on-site review and $220 with one. The property record card that every residential application needs can be obtained from Building & Planning or through the county’s online property search.

Inspections are where schedules slip.

Get a free quote →

White County building permit FAQs

How much is a building permit for a new house in White County?

$0.14 per square foot with a $175 minimum for a conventional house; modular and manufactured homes are $0.10 per square foot with a $125 minimum.

Do I need a permit to replace my roof or windows?

No, if the roof line and rafters do not change and the windows are the same size; siding and painting are also exempt.

Does a deck or pool need a permit?

Yes. Decks and permanent pools (those left up year round) are secondary accessory structures at $35.

How long does plan review take?

Within 7 business days of a complete application, with a completeness notice within 3 business days.

Can I use a private inspector?

Yes. A qualifying architect, engineer or certified building official can review and inspect, chosen at application, with a $100 convenience fee.

What if I start building without a permit?

The fee rises by 50% of the calculated amount, up to $300.

Do I need anything from the sewer district or health department?

Yes. No building permit is issued until the Twin Lakes Regional Sewer District or the Health Department confirms in writing.

Simplify White County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in White County sooner?

Let Alliance prepare, file, and track your White County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about White County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.