Terre Haute, Indiana Building Permit Guide

To get a building permit in Terre Haute, confirm which office issues permits for the property’s address, then submit the application through Cityworks Public Access with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Inside Terre Haute, the Department of Engineering issues building, electrical, plumbing, mechanical, demolition and sign permits through its Cityworks portal, and its Building Inspection Division inspects the work and enforces the city zoning ordinance.

Authority: Terre Haute Department of EngineeringPortal: Cityworks Public AccessPhone: 812-244-4903
Authority
Department of Engineering17 Harding Avenue, Room 200
New house
$150 + $0.10/sq ftCity Code Sec. 7-60, per dwelling unit
Contractors
City license or registration$350 first year, $175 renewal
Inspections
Book in CityworksAt least 24 hours ahead

In the City of Terre Haute, permits come from the Department of Engineering at City Hall, 17 Harding Avenue (812-244-4903), which the City Code puts in charge of the building code; Marcus Maurer is Director of Engineering. Applications, payments by card, contractor licensing and inspection requests all run through the city’s Cityworks Public Access portal. Under Section 7-60 of the City Code, a new house or addition costs $150 plus $0.10 per square foot per dwelling unit, and commercial construction $350 plus $0.25 per square foot.

What requires a building permit in Terre Haute?

Section 7-30 of the City Code makes it unlawful to do any construction activity in the city without a Department of Engineering permit, and the code spells out that this includes excavation, fences and other site work. A site that meets the city’s land disturbance criteria also needs a Land Disturbance Permit. Working without a permit carries a fine of at least $200, and each day the offence continues counts separately.

Permit needed

  • New houses, additions and remodels, priced per square foot of the structure
  • Repairs, with separate general, electrical, plumbing and mechanical repair permits
  • Fences, in-ground pools and every type of sign
  • Demolition of a house, garage or commercial building
  • Tree removal or alteration in the city right-of-way, and other right-of-way work
  • Land disturbance of an acre or more, under a separate permit

No permit (one- and two-family homes)

  • Cabinets, shelving, railings, wall and floor coverings and doors attached to walls or floors
  • Storm windows and painting, papering or similar finish work
  • Replacing an attic, bathroom, range hood or whole-house fan
  • Household appliances that need no new electrical circuit
  • Replacing plumbing fixtures, traps and valves, or a water heater with the same venting and fuel
  • Electrical equipment rated under 50 volts and real estate signs within the zoning size limits

What Terre Haute decides and what the state holds

The city sets its permit list, fees, contractor licensing and zoning. A Class 1 project also needs the state design release, and the city’s plan review page adds that such plans need approval from the Indiana Department of Homeland Security and the Terre Haute Fire Department. In March 2026 the Common Council amended the city fire prevention code (General Ordinances 1 to 4, 2026), and on September 10, 2026 it added a groundwater usage restrictions section to the building chapter (General Ordinance 10, 2026).

Terre Haute building department: who handles permitting

The Department of Engineering administers and enforces the city building code (Section 7-3). Its Building Inspection Division has three inspectors who check new construction and existing structures in the city, covering building, electrical, plumbing, mechanical and sewer connection work and also enforce the zoning ordinance. The department’s Permitting Manager is also the floodplain administrator, and the Fire Department inspects fire suppression and alarm systems.

Short on time to read all of this?

Get a free quote →
Terre Haute permit contacts
DetailInformation
OfficeDepartment of Engineering, City Hall, 17 Harding Avenue, Room 200, Terre Haute, IN 47807
Phone812-244-4903
HoursMonday to Friday, 8:00 a.m. to 4:00 p.m.
Department headMarcus Maurer, Director of Engineering
PortalCityworks Public Access: permits, plan review, contractor licenses, inspections and the rental registry
Cash and check paymentsCity Controller’s Office, 17 Harding Avenue, Room 205
Zoning appeals and rezoningVigo County Area Planning, 159 Oak Street, 812-462-3354 (Terre Haute City Board of Zoning Appeals)

Terre Haute permits stop at the city limits. The Vigo County Area Plan Commission plans for the city together with the towns and unincorporated county, but building permits in unincorporated Vigo County come from the separate Vigo County Building Inspections Department.

Terre Haute permit types

All applications go in through Cityworks, which needs an account and password. Room 200 has a public terminal for applicants without internet access. The building permit can be a single permit for all work at a structure when a registered or licensed contractor takes responsibility for every trade and names a licensed subcontractor for each licensed trade it does not hold (Section 7-31).

Residential permits

  • New houses, additions and remodels are charged per square foot of structure for each dwelling unit. A new house or addition needs a sketch showing where it sits on the lot and its distances to street and alley centerlines and to the property lines.
  • One- and two-family dwellings skip the plan review permit; their building permit file needs the setback drawing unless all the work is inside the building.
  • Repairs carry flat general, electrical, plumbing and mechanical fees, and a green tag is $50.
  • Demolition needs written statements from each utility that service is cut off plus the owner’s written consent or a demolition order. A homeowner may not demolish a dwelling, but may take down a garage with the building inspector’s prior approval.

Commercial permits

Every building permit except one for a one- or two-family dwelling needs a Plan Review Permit first (Section 7-32). The plan review page applies it to new commercial construction and residential buildings of two or more units, including additions. Submit one set of digital or physical plans in Cityworks with a site plan (unless all work is inside) and the state design release when one is required; outside single-family work, the site plan also shows parking and drainage. Commercial, industrial and multi-family (four or more dwellings) demolition needs IDEM form 44593, completed by an Indiana-licensed asbestos professional, before the permit is issued, and sign drawings must be approved by the Lead Inspector.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. Section 10-259 of the zoning chapter says no permit for the use of land or buildings may issue until the Zoning Administrator in the Bureau of Zoning, part of the building inspector’s department, has checked it against the Comprehensive Zoning Ordinance.
  • Board of Zoning Appeals and rezoning. Variances go to the Terre Haute City Board of Zoning Appeals and rezonings to the Vigo County Area Plan Commission, both staffed by Vigo County Area Planning; BZA applications must be filed in person.
  • Floodplain. Work in a mapped flood area falls under the Unified Floodplain Control Ordinance in Chapter 10.
  • Right-of-way and trees. Work in a sidewalk, tree row, curb, street or alley needs a right-of-way permit and the larger bond; removing or altering a right-of-way tree costs $25 and needs City Forester approval and city registration.

Terre Haute permit costs and fees

Permit fees are set in Section 7-60 of the City Code, as posted in the city’s code update dated February 2026, and are paid before the permit issues. Permit fees are waived for buildings owned by local, state and federal government, though the code still applies to the work. The Engineering FAQ page still describes an older formula of $15 for the first $1,000 of work plus $1 per further $1,000; the table below follows the City Code.

Terre Haute permit fees (City Code Sec. 7-60)
WorkFee
Residential new build, addition or remodel$150 + $0.10 per sq ft of structure, per dwelling unit
Residential repair: general, electrical, plumbing or mechanical$100 each
Residential green tag / in-ground pool$50 / $100
Commercial new build, addition or remodel$350 + $0.25 per sq ft of structure; $175 per floor above the first
Commercial repair: general, electrical, plumbing or mechanical$150; $75 per floor above the first
Commercial green tag / pool$150 / $350
Plan review$250 base up to 1/2 acre; $100 per added 1/2 acre
Land disturbance$250 per acre
Fence$25
DemolitionResidential $125; commercial $250 + $0.05 per sq ft
SignsPortable $25; pole or ground $3 per sq ft (min. $150); wall $3 per sq ft (min. $100); billboard or tall sign $3 per sq ft (min. $350)
Reinspection (Sec. 7-61)$50
Tree removal or alteration in the right-of-way$25

Rather talk it over?

Call 1-855-478-4290 →

Worked examples from the table: a new 2,000-square-foot house is $150 + (2,000 × $0.10) = $350 for the building line, and a one-story 10,000-square-foot commercial building is $350 + (10,000 × $0.25) = $2,850 before plan review. Reinspection fees must be paid before the certificate of occupancy or final approval. The code gives two figures for renewing an expired permit: Section 7-36 sets the renewal fee at 50% of the original permit cost, while Section 7-62 still lists a $20 renewal fee. Rezoning and BZA fees are separate Vigo County Area Planning charges: since May 1, 2026, a BZA case on a single-family or agricultural lot is $150 plus $10 per additional request, and rezonings run $150 to $325.

Trade permits and who may pull them

Terre Haute requires a city license or registration for anyone doing construction work inside the city, applied for online in Cityworks with three to five business days for processing. Licenses and registrations run from January 1 to December 31: the fee is $350 for the first year and $175 to renew, with a pro-rated rate for licenses bought from July ($438 new, $263 renewal) through December ($365 new, $190 renewal) that also covers the following year.

  • General contractors register with a $10,000 bond on the city’s own bond form, an ACORD insurance certificate naming the city ($500,000 combined minimum) and workers’ compensation or a state WCE-1 exemption. Right-of-way work needs a $25,000 bond and $1,000,000 liability cover.
  • Electrical needs a city license. A residential license covers single-family homes with service under 400 amps and needs a passed master, journeyman or residential exam; a commercial license needs the master exam, with a full-time master electrician named as supervisor.
  • Mechanical (HVAC) needs a city license and at least one full-time employee certified by NATE, HVAC Excellence, RSES, Experior or an accepted equivalent.
  • Plumbing licenses follow the Indiana Plumbing Commission; bring a copy of the state license at application and renewal.
  • Fire protection (hoods, sprinklers and alarms) needs its own city license with the same bond and insurance.

Rather not deal with the building department?

Get a free quote →

Section 7-31 lets an owner or contract purchaser pull a permit for a home the owner will live in, for work done personally or by unpaid volunteers; licensed-trade work by an owner needs the inspector’s approval that the owner can do it properly. When a contractor is hired, the contractor buys the permit, and Section 7-12 requires a licensed or certified person on site for each licensed trade being performed.

How to apply for a Terre Haute building permit

1. Check the parcel

Confirm the address is inside the city limits and look up its zoning on the city GIS portal.

2. Get licensed or registered

Contractors register or license in Cityworks with bond and insurance; an owner-occupant doing the work can apply as the owner.

3. Clear zoning and land approvals

File any variance with the City BZA in person, and a Land Disturbance Permit if an acre or more will be disturbed.

4. Submit plans if required

Anything other than a one- or two-family dwelling needs a Plan Review Permit with plans, site plan and the state design release where one applies.

5. Apply for the building permit

Enter the work in Cityworks with the setback sketch and any trade permits.

6. Pay the fee

Pay by card in Cityworks, or by cash, check or money order at the Controller’s Office, Room 205.

Review, corrections and what causes delay

Plan review is done by the Lead Building Inspector and a Staff Engineer and generally takes 7 to 10 days. No permit issues while the applicant owes the city past-due fees. Changes after issue must be filed as an amendment in Cityworks and approved before that work starts. A permit lapses if work does not start within 90 days (one extension of up to 60 days) or stops for 180 days, and every building permit ends when the property is sold.

Inspections and certificates in Terre Haute

Book inspections in Cityworks: open the permit, choose the Actions tab, then Schedule Inspection, at least 24 hours ahead. Section 7-52 lists the stages, as applicable:

  • Foundation, after piers are set or trenches dug and any reinforcing steel is in place, before concrete.
  • Rough-in for each of the three crafts (plumbing, electrical and heating or cooling), before anything is covered or fixtures are set.
  • Frame and masonry, once roof, framing, firestopping, bracing, wiring, pipes, chimneys and vents are complete, before interior wall covering.
  • Final, when all work on the structure and site is finished.
  • Fill, after a demolition that leaves a basement or other below-grade space, before it is filled.

Work at each stage must stay open until the end of the next business day after notice, or until inspected. Unless another time is agreed, inspectors visit between 8:00 a.m. and 4:00 p.m. on weekdays. No building may be occupied without a full, partial or temporary certificate of occupancy from the Department of Engineering (Section 7-10). New-construction permits run two years and remodel or repair permits one year.

Want this handled start to finish?

Get a free quote →

Indiana building code in Terre Haute

The Department of Engineering enforces the codes adopted by the Fire Prevention and Building Safety Commission through Chapter 7 of the City Code, with its own fire prevention rules in Article 2. FEMA’s Community Status Book lists the City of Terre Haute (community 180264) as participating in the National Flood Insurance Program, with a current flood map dated February 18, 2011.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Terre Haute permit search and official resources

To get permit files for a property, use the city’s online records request form, choose “Building Permit Records” as the request type and give the property address.

Inspections are where schedules slip.

Get a free quote →

Terre Haute building permit FAQs

How much is a building permit for a new house in Terre Haute?

$150 plus $0.10 per square foot of structure for each dwelling unit, so a 2,000-square-foot house is $350 for the building line.

Can I do my own work on my house?

Yes, if you own the home and live in it; the permit is issued to you, and licensed-trade work needs the inspector’s approval. If you hire a contractor, the contractor buys the permit.

Does a contractor need a Terre Haute license?

Yes. General contractors register, and electrical, mechanical, plumbing and fire protection contractors hold city licenses; the fee is $350 the first year and $175 to renew.

How long does plan review take?

Generally 7 to 10 days for projects that need a Plan Review Permit, which covers everything except one- and two-family dwellings.

How do I schedule an inspection?

In Cityworks, open the permit, choose Actions, then Schedule Inspection, at least 24 hours in advance.

Can a homeowner demolish an old house?

No. The city says a homeowner cannot demolish a dwelling; a homeowner may take down a garage with the building inspector’s prior approval.

Simplify Terre Haute permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Terre Haute sooner?

Let Alliance prepare, file, and track your Terre Haute permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Terre Haute permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.