In Vigo County, building, electrical, plumbing and demolition permits are issued by the Vigo County Building Inspections Department, which works under the County Commissioners from the county annex at 151 Oak Street, Terre Haute (812-462-3365); Terry Bays is the Building Commissioner. New buildings and additions first need an Improvement Location Permit from Vigo County Area Planning at 159 Oak Street. Under Chapter 63 of the county code, adopted January 9, 2018, a new stick-built house costs $125 plus $0.10 per square foot of living space. The City of Terre Haute runs its own permit office.
What requires a building permit in Vigo County?
The county fee ordinance (Chapter 63) applies its building permit fees to any project valued at $500 or more. It counts the full value of the work even when materials were free, and it bars splitting a job into smaller pieces to stay under the threshold. The Building Inspections Department issues four kinds of permit (building, electrical, plumbing and demolition) and inspects all construction it permits, under the county Building Code Ordinance in Chapter 61.
Building Inspections permit
- New stick-built and modular homes, additions, porches, garages and barns
- Roofs and remodels, priced on estimated cost
- In-ground pools, accessory and agricultural structures
- Commercial buildings, additions, remodels and signs
- Electrical work, from a reconnect to a new service
- Plumbing, and demolition of any structure
Area Planning permit first
- New single-family, mobile or modular homes and additions to living space
- Accessory structures: detached garages, decks, porches, patios, non-livable pole barns, sheds, in-ground pools and signs
- Demolitions and remodels, including roofs, gutters, windows and doors
- Duplexes and apartments, commercial and industrial buildings
- Temporary uses and work in a flood zone
Area Planning’s demolition and remodel application is the one for existing structures where walls do not move and no floor area is added. Electrical, heating and cooling or plumbing work on its own goes straight to Building Inspections.
What Vigo County decides and what the state holds
The Board of Commissioners sets the permit fees and fines and adopts the county building, unsafe building and fire prevention ordinances; zoning, subdivision and flood rules come through the Area Plan Commission. Commercial permits need the state-approved plans and the state design release. On October 7, 2025 the Commissioners adopted Ordinance 2025-7, which requires in-building coverage for the Hoosier SAF-T public safety radio system when a multi-family, commercial or industrial building is built, changes use, is significantly renovated or grows by more than 20%. Buildings under 5,000 square feet and single-family homes are exempt.
Vigo County building department: who handles permitting
Two county offices on Oak Street in Terre Haute share the work. Area Planning reviews zoning, setbacks and flood rules and issues the Improvement Location Permit; Building Inspections collects its own fees, issues the building and trade permits and does the inspections. The Health Department, also in the annex, handles septic permits.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Building Inspections Department | 151 Oak Street, Terre Haute, IN 47807; 812-462-3365; fax 812-231-5602; 8:00 a.m. to noon and 1:00 to 4:00 p.m.; Terry Bays, Building Commissioner |
| Area Planning Department | 159 Oak Street; 812-462-3354; areaplan@vigocounty.in.gov; Monday to Friday 8:00 a.m. to 4:00 p.m. |
| Environmental Health (septic) | Vigo County Annex, 147 Oak Street; 812-462-3428; Monday to Friday 8:00 a.m. to 3:45 p.m. |
| Highway Department (county road right-of-way) | 3250 E. Haythorne Avenue; 812-466-9635; Monday to Friday 7:30 a.m. to 4:00 p.m. |
| Surveyor (regulated drains) | 143 Oak Street; 812-462-3380 |
Which office serves your address
| Place | Zoning and appeals | Building permits |
|---|---|---|
| Unincorporated Vigo County | Area Planning; Vigo County BZA | Vigo County Building Inspections |
| City of Terre Haute | City zoning ordinance; Terre Haute City BZA (staffed by Area Planning) | City Department of Engineering, 17 Harding Avenue |
| Towns of Riley, Seelyville and West Terre Haute | Area Plan Commission; Vigo County BZA | Not stated on the county’s pages; ask Building Inspections |
Area Planning’s fee notice marks its Improvement Location Permit fees as “Vigo County only”, separate from the rezoning, subdivision and appeal fees that apply in the county and Terre Haute alike. The Beacon parcel viewer, linked from the permit page, shows where a parcel sits.
Vigo County permit types
Area Planning takes its applications online through six forms and has five business days under Section 5(A)(3) of the Unified Zoning Ordinance to grant a permit; the Health Department or Building Inspections may need more time. Staff email the applicant when more information is needed, and complex projects may not be grantable by email. Building Inspections’ own application asks for the job address, owner, contractor, type of work with square footage, the electrical service work and the valuation.
Residential permits
- New homes and additions: the single-family, mobile home and modular form at Area Planning, then a building permit priced on living space (stick-built) or a flat $150 (modular).
- Garages, barns, porches and additions are $0.10 per square foot with a $75 minimum.
- Roofs and remodels are priced on estimated cost: $50 for the first $1,000 and $1.50 for each further $1,000.
- Electrical: $50 for a new, temporary or upgraded service and $25 for a reconnection, remodel or addition; residential plumbing is a flat $50.
- Demolition: $75 for a house and $50 for an accessory building, each valid for 14 days.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial jobs start with Area Planning’s commercial or industrial form ($100 Improvement Location Permit) and need the state-approved plans and design release before Building Inspections issues the building permit. Fees run on floor area: $300 plus $0.17 per square foot for new buildings and signs, $200 plus $0.17 for additions, barns and garages, and $150 plus $0.17 for remodels. Commercial electrical and plumbing are $100 for the first $1,000 of cost plus $1.50 per further $1,000, and a commercial demolition permit is $150 for 30 days. Duplexes and apartments use Area Planning’s multi-family form.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Improvement Location Permit. Any construction that adds square footage needs one; the county describes it as a three-step process with Area Planning and the Health Department.
- Site plan. Required for any new structure, or where a parcel has several structures; without a professional plan, Area Planning accepts a Beacon map marked to show the location.
- Septic. Environmental Health issues on-site sewage permits for $150.
- Flood zones. Check the Indiana Floodplain Information Portal and FEMA’s map; the most restrictive zone applies, and flood-zone sites need extra information.
- County roads and drains. Right-of-way permits come from the Highway Department, and the Surveyor oversees the county’s regulated drains.
Vigo County permit costs and fees
Building Inspections fees are set by Chapter 63 of the Vigo County Code, which the Board of Commissioners adopted on January 9, 2018, replacing the fee sections of Chapter 61. Area Planning charges its own fees under a schedule effective May 1, 2026. Health Department fees are separate.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Residential stick-frame dwelling | $125 + $0.10 per sq ft of living space |
| Modular home | $150 flat |
| Garage, barn, addition or porch | $0.10 per sq ft; $75 minimum |
| Roof or remodel | $50 for the first $1,000 of cost + $1.50 per further $1,000 |
| In-ground pool / accessory structure / agricultural structure | $100 / $100 / $75 |
| Commercial new building or sign | $300 + $0.17 per sq ft |
| Commercial addition, barn or garage / remodel | $200 + $0.17 per sq ft / $150 + $0.17 per sq ft |
| Electrical, residential | $50 new, temporary or upgraded service; $25 reconnect, remodel or addition |
| Electrical or plumbing, commercial | $100 for the first $1,000 + $1.50 per further $1,000 |
| Plumbing, residential | $50 flat |
| Demolition | Commercial $150 (30 days); residential $75 (14 days); accessory $50 (14 days) |
| Certificate of occupancy / re-inspection | $15 / $25 |
| Area Planning Improvement Location Permit | $20 single-family or A-1; $50 two-family or multifamily; $100 commercial or industrial |
| Area Planning demo/remodel or temporary use permit | $20 each |
| Elevation certificate review / floodplain compliance certificate | $50 single-family, $150 other / $50 residential, $200 commercial |
Worked example from the two schedules: a new 1,800-square-foot stick-built house on an A-1 or single-family lot is $20 for the Improvement Location Permit plus $125 + (1,800 × $0.10) = $305 for the building permit, before the septic, electrical and plumbing permits. Work started without a permit or without a required inspection is stopped at once and fined $300 for a first offence, $500 for a second and $1,000 for a third in a calendar year, after which the contractor may be barred from permits for a year. A fine can be appealed in writing to the Commissioners within five days, and the hearing is held within ten.
Trade permits and who may pull them
Building Inspections issues the county’s electrical and plumbing permits, and Area Planning’s permit page sends electrical, heating and cooling and plumbing-only jobs straight to that office. Electrical service work is tied to the inspection: the department must green-tag a temporary service before the utility will set a meter. The county’s pages describe no county contractor license or registration; plumbing contractors hold the state license. Chapter 63 places the duty to get a permit on the homeowner in the end, while saying no work may start until a valid permit is on site, and it collects any fines from the contractor.
Rather not deal with the Vigo County building department?
Get a free quote →Inside Terre Haute the rules differ: the city licenses electrical, mechanical, plumbing and fire protection contractors and registers general contractors through its Cityworks portal, so a contractor working on both sides of the city line needs the city license for city jobs.
How to apply for a Vigo County building permit
Look the parcel up on Beacon to confirm it is outside Terre Haute, and check the flood zone on the Indiana Floodplain Information Portal.
For a new home on a septic system, apply to Environmental Health at 147 Oak Street.
Choose the right online form and attach a site plan or marked Beacon map; Area Planning has five business days to act.
Bring the state-approved plans and the design release.
Building Inspections at 151 Oak Street takes its fees and issues the permit, with the electrical and plumbing permits the job needs.
No work may start until the permit is on site.
Review, corrections and what causes delay
Area Planning may need more information, such as a site plan or flood-zone details, and staff email the applicant when it does. Variances need the Vigo County BZA, whose applications must be filed in person; the county’s BZA page notes that under area planning law no variance or special exception of use is permitted. Demolition permits are short: 14 days for houses and 30 days for commercial buildings.
Inspections and certificates in Vigo County
The contractor or the owner books inspections with Building Inspections at 812-462-3365, with as much notice as possible; the county says it will work with builders when a day’s notice is not possible and that additional inspections are always acceptable. The standard sequence is:
- Footers, before concrete is poured.
- Temporary electric, which must be approved with a green tag before the meter is installed.
- Before walls are covered, checking electrical, plumbing and framing before insulation or drywall.
- Final, with a certificate of occupancy where one is required ($15).
A re-inspection costs $25. Copies of every inspection are kept in the Building Inspections office, where owners can view them or get a copy.
Indiana building code in Vigo County
The county enforces the state codes through its Building Code Ordinance (Chapter 61) and its fire prevention ordinance. Its Flood Damage Prevention Ordinance, recommended by the Area Plan Commission (Resolution 1-25, August 6, 2025) and passed by the Commissioners on August 13, 2025, sets the flood protection grade at the base flood elevation plus two feet and, where floodway limits are not mapped and more than one square mile drains to the site, sends the application to the Indiana Department of Natural Resources before a local permit. FEMA’s Community Status Book lists unincorporated Vigo County (community 180263) as participating in the National Flood Insurance Program, with a current map dated February 18, 2011.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Vigo County permit search and official resources
Building Inspections keeps copies of all inspections at 151 Oak Street. For copies of permits or other county files, use the county’s online public records request form, which accepts requests to see records in person or receive copies; making a request is free, and copies may carry a fee. Area Planning holds elevation certificates and flood records.
- Vigo County Building Inspections Department
- Chapter 63 permit fee ordinance (January 2018)
- Building permit application
- How to schedule a building inspection
- Area Planning: apply for a permit
- Area Planning fee schedule, effective May 1, 2026
- Board of Zoning Appeals
- Floodplain information
- Flood Damage Prevention Ordinance (2025)
- Ordinance 2025-7, public safety radio coverage
- Environmental Health (septic permits)
- Public records request
- City of Terre Haute Building Inspection
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Vigo County building permit FAQs
Who issues building permits in Vigo County?
The Vigo County Building Inspections Department at 151 Oak Street, for unincorporated Vigo County; the city’s Department of Engineering issues permits inside its limits.
How much does a permit for a new house cost?
$125 plus $0.10 per square foot of living space for a stick-built house, plus a $20 Improvement Location Permit on a single-family or A-1 lot.
Do I need a permit for a new roof?
Yes. Roofs are on Area Planning’s demolition and remodel form, and Chapter 63 prices a roof at $50 for the first $1,000 of cost plus $1.50 per further $1,000.
How much is a septic permit?
$150, from the Vigo County Health Department’s Environmental Health office at 147 Oak Street.
What happens if I build without a permit?
Work is stopped and may have to be undone, and fines are $300, $500 and $1,000 for first, second and third offences in a year.
Do I need a permit for electrical work only?
Yes, from Building Inspections: $50 for a new or upgraded service and $25 for a reconnection, remodel or addition.
Where do I file a variance?
With Area Planning, in person, for the Vigo County Board of Zoning Appeals; a single-family or agricultural case is $150 plus $10 per additional request.
Simplify Vigo County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Vigo County sooner?
Let Alliance prepare, file, and track your Vigo County permits while your crew stays on the job.
More Indiana permitting guides
Terre Haute
Read guide →Clay County
Read guide →Parke County
Read guide →Vincennes Building Permit Guide
Read guide →Wabash Building Permit Guide
Read guide →Wabash County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Vigo County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.