In unincorporated Spencer County, the Plan Commission and Building Inspector office in the Courthouse, 200 Main Street, Room 3, Rockport (812-649-6010), issues one combined building permit and improvement location permit. A permit is needed before new construction costing more than $2,000, remodeling or repairs over $5,000, an in-ground pool, or electrical, plumbing or mechanical work over $750. The office takes cash or checks only, and because it is staffed by one person it asks applicants to call before coming in.
What requires a building permit in Spencer County?
The county’s Building Permits page sets cost thresholds rather than a list of projects. You should get a permit before you begin:
Permit required
- New construction of a building or structure costing more than $2,000
- Alteration, remodeling or repair of a building costing more than $5,000
- Installing an in-ground swimming pool
- Electrical, plumbing or mechanical work costing more than $750
- Upgrading the capacity of an electric or gas service, or installing a permanent electric or gas meter that needs the utility
- Reconnecting electric service after a fire
- Installing any heating, ventilating or air conditioning system
- Installing or modifying an underground storage tank
Extra conditions
- In a floodplain, an elevation certificate showing the new structure at least 2 feet above the base flood elevation
- A septic permit or sewer receipt where the site needs one
- A Construction Design Release from IDHS if employees or the public will use the building
- A notarized statement from the owner if the applicant is not the owner
The improvement location side of the same form reaches further: no building or structure may be erected, rebuilt, remodeled, enlarged or moved until an ILP has been applied for in writing and issued by the Zoning Administrator, and the permit must be posted in a prominent place on the site during the work.
What Spencer County decides and what the state holds
The county sets the permit thresholds, fees, zoning and floodplain rules through its Comprehensive Zoning Ordinance dated September 23, 2000 (with zoning district maps of December 1981), the Spencer County Code of Ordinances adopted September 5, 2023, and later ordinances such as the 2025 Flood Damage Prevention Ordinance; the county’s ordinance list also includes a solar energy ordinance (2023-16), a wind ordinance (2024-06) and an energy ordinance (2024-10). Building standards themselves are the state’s, and buildings used by the public or by employees need the state release before construction.
Spencer County building department: who handles permitting
One office handles zoning, building permits and inspections for the unincorporated county: the Plan Commission and Building Inspector, run by Administrator Kay Erwin. The department page lists the Building Inspector at 812-489-8896; other county pages and the application form print different numbers, so confirm the inspector’s number with the office. In 2023 the Commissioners repealed the old County Advisory Planning Department chapter because the Spencer County Advisory Plan Commission had taken its place; the commission and a Board of Zoning Appeals hear rezonings, variances, special exceptions and contingent uses. The department page lists nine Advisory Plan Commission members, five BZA members and the commission’s attorney.
Short on time to read all of this?
Get a free quote →| Place | Permit office |
|---|---|
| Unincorporated Spencer County | Plan Commission & Building Inspector, Courthouse, 200 Main Street, Room 3, Rockport; 812-649-6010 |
| City of Rockport | City Hall, Deputy Clerk-Treasurer; 812-649-2242 |
| Towns of Santa Claus, Dale, Chrisney, Gentryville, Grandview and Richland | The published sources do not say; ask the town hall |
The office is open Monday to Friday, 8 a.m. to 4 p.m. with an hour for lunch; fax 812-649-6481, email plan@spencercounty.in.gov. It also assigns addresses in the unincorporated county to lots, parcels, farm buildings and other structures on request.
Spencer County permit types
The county uses one paper form, the Spencer County Building Permit and Improvement Location Permit Application, which you bring or mail to the Plan Commission at 200 Main Street, Room 3. It is signed under oath and notarized, and asks for the township, lot and subdivision or the section, township and range, lot size, building dimensions and total floor area, the building, plumbing and electrical contractors, the electrical panel size and type of heat, the water supply and sewage method, the number of rooms, and the structure and foundation type.
Residential permits
- New houses: building plans, the contractor’s name and phone, a septic permit or sewer receipt, the recorded deed, a site plan, the estimated completion date and the estimated cost.
- Additions and remodels: the same form; the site plan shows the lot, existing buildings and anything within 50 feet of the boundaries unless a street separates them.
- Mobile and modular homes: listed on the form as structure types, alongside masonry, wood frame, log and steel.
- Trade work alone: electrical, plumbing or HVAC work over $750, service upgrades, new meters and post-fire reconnects.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Any building with employees or public use needs the IDHS Construction Design Release before the county permit, and the release number goes in the office-use block of the form. Underground storage tank installations and changes also need a county permit.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Septic. The Spencer County Health Department, 200 Main Street, Room 1, Rockport, provides permits, consultations and inspections for new and replacement onsite sewage systems, with separate residential and commercial applications and a re-inspection application; the county adopted an Onsite Sewage Systems ordinance on February 21, 2024. Owners who want to know where an existing system is or how it works are asked to contact the department.
- Driveway and roads. The Highway Department issues driveway culvert permits, enclosed storm drain permits and permits to work in county road rights-of-way, all mailed to the Highway Superintendent at 920 E. 800 N, Chrisney (812-362-8331).
- Floodplain. The Flood Damage Prevention Ordinance (Ordinance 2025-08) sets floodplain development permits; the county posts a floodplain map.
- Land divisions. Splitting land must follow the Spencer County Subdivision Ordinance unless an exemption applies, such as lots of at least 1 acre on a well or septic system (or half an acre on municipal or regional sewer) with at least 100 feet of frontage on a maintained public road and no new street.
- Special exceptions. Uses such as kennels, day care, campgrounds, sawmills, manufactured home parks and keeping a recreational vehicle longer than 180 days need a special exception permit from the BZA where the Schedule of Uses requires it.
- Zoning relief. Petitions and fees are due by noon on the first Wednesday of the month to be heard that month; meetings are normally on the fourth Thursday at 6:00 p.m.
- Address. A new address comes from the Plan Commission office. The owner must display it in numbers at least 3 inches tall on both sides of a mailbox in front of the building, in contrasting or reflective material, and also on the house or business or on a sign at the entrance; several volunteer fire departments, including Carter, Jackson, Rockport-Ohio Township and St. Meinrad, make reflective address signs.
- Setbacks. From state or county right-of-way lines: 60 feet on a secondary (county) road, 70 feet on a primary road, 75 feet on an arterial highway and 30 feet on a local residential street. Accessory buildings must be at least 5 feet from the rear and 10 feet from the side property line. A new driveway off a state highway goes through the state highway office in Tell City (812-836-2111).
- Drainage questions. The Surveyor’s Office is in Room 17 of the Courthouse (812-649-6016).
Spencer County permit costs and fees
The county’s Building Permits page says an improvement location permit fee is charged in addition to the building permit fee and that both are figured once all information has been turned in; the application has blanks for them, filled in by the office. The page prints only three flat amounts, shown below. Payment is cash or check only, so call the office (812-649-6010) for your project’s figure before you bring the application.
Rather talk it over?
Call 1-855-478-4290 →| Item | How it is paid |
|---|---|
| Improvement location fee | Figured by the office on the combined application; charged in addition to the building permit fee |
| Building permit fee | Figured by the office once all information is turned in |
| Residential swimming pool, permanent and non-portable | $60 |
| Electrical hook-up on liquid storage tanks | $60 |
| Relocation, addition or modification of gas or electric service | $35 each; no improvement location permit needed |
| Variance (BZA hearing) | $100 filing fee |
| Special exception permit (BZA hearing) | $100 filing fee |
| Rezoning petition by an individual / to I-1 or I-2 | $50 / $200 (Advisory Plan Commission hearing) |
| Petition deadline | Paperwork and filing fee by noon on the first Wednesday of the hearing month |
| Septic permit | Paid to the Spencer County Health Department under its fee ordinance (Section 35.09, amended by Ordinance 2025-03) |
| Driveway culvert or right-of-way permit | County Highway Department; applications by mail |
| State design release (Class 1 only) | Paid to IDHS with the release application |
Because the cost thresholds decide whether a permit is needed at all, the estimated cost you enter on the form matters: new construction over $2,000, remodeling over $5,000 and trade work over $750 all trigger a permit.
Trade permits and who may pull them
Spencer County folds electrical, plumbing and mechanical work into its building permit: the application names the plumbing and electrical contractors, the panel size and the heating type, and the office marks the permit as including no electric, electric or gas. Trade work on its own needs a permit once it costs more than $750, and any service upgrade, new permanent meter or post-fire reconnect needs one regardless of cost.
- Plumbing: plumbers are licensed by the state; the county form asks for the plumbing contractor’s name and phone.
- Electrical and HVAC: the form asks for the electrical contractor; the county pages show no local trade license or contractor registration.
- Septic: systems are permitted and inspected by the Health Department.
The county pages do not describe a separate homeowner rule; the application lets the applicant list the contractors, and a non-owner applicant needs the owner’s notarized permission.
Rather not deal with the Spencer County building department?
Get a free quote →How to apply for a Spencer County building permit
The Plan Commission is a one-person office; call 812-649-6010 to be sure someone is in.
Get the Health Department septic permit, or a sewer receipt from the utility.
Mail the driveway culvert application to the Highway Department and ask the Plan Commission for an address.
Plans, site plan, recorded deed, contractor details, cost estimate and completion date; an elevation certificate in a floodplain.
Fill in the combined building and ILP application and sign it before a notary.
Bring or mail it to 200 Main Street, Room 3, Rockport, and pay by cash or check.
Review, corrections and what causes delay
The county warns that building permits may not be available the same day the application is filed. The office says there will be times when the administrator is out, which is why it asks for a call before a visit. Missing septic approval, a missing deed or, in a floodplain, an elevation certificate that does not show 2 feet above the base flood elevation will hold the permit. Once it issues, construction must start within 90 days; the permit does not expire while reasonable progress continues on the structure that was permitted, but a long delay or substantial changes to the building or site plans may require a new permit.
Inspections and certificates in Spencer County
Give the Building Inspector (812-489-8896 on the department page; confirm the number with the office) 24 hours’ notice at each stage that applies, and cover no work until it has been inspected. The county lists these steps:
- Footings, before the pour
- Underground plumbing
- Framing, with waterproofing and roofing at the rough stage
- Rough-in electrical, rough-in plumbing and rough-in heating and air conditioning
- Gas meter
- Electrical service
- Final inspection
The permit stays posted on site until the final. The application form groups the stages into three calls: the footing inspection before any concrete is poured, a rough inspection covering waterproofing, framing, roofing and rough-in electrical, and the final. In a floodplain, the elevation certificate showing the 2-foot clearance above the base flood elevation stays with the permit file.
Indiana building code in Spencer County
FEMA’s Community Status Book lists unincorporated Spencer County (community 180237) as participating in the National Flood Insurance Program, with a current map dated May 18, 2015; the county requires new structures in the floodplain to sit at least 2 feet above the base flood elevation, shown on an elevation certificate.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Want this handled start to finish?
Get a free quote →Spencer County building permit FAQs
Do I need a permit for a shed or small project?
New construction needs a permit when it costs more than $2,000, and remodeling or repairs when they cost more than $5,000.
Do I need a permit to replace a furnace or air conditioner?
Yes. The county lists installing any heating, ventilating or air conditioning system as needing a permit.
How do I pay for a Spencer County permit?
Cash or check only, at the Plan Commission office in Room 3 of the Courthouse.
Does the county issue permits in Rockport?
No. Rockport issues its own building permits through the Deputy Clerk-Treasurer at City Hall (812-649-2242).
How high must I build in a floodplain?
At least 2 feet above the base flood elevation, shown on an elevation certificate filed with the permit.
Can I get a permit the same day?
Not always; the county says permits may not be available the day you apply.
How much does a variance or rezoning cost?
A variance or special exception is $100 and needs a BZA hearing; a rezoning petition by an individual is $50, or $200 to rezone to an industrial district, with a hearing before the Advisory Plan Commission.
When does the Plan Commission meet?
Normally the fourth Thursday of the month at 6:00 p.m.; filings and fees are due by noon on the first Wednesday.
Spencer County permit search and official resources
Permit and ILP records for the unincorporated county are kept by the Plan Commission office; ask there with the parcel or address. County ordinances, including zoning amendments and the 2025 flood ordinance, are posted on the county’s ordinances page.
Inspections are where schedules slip.
Get a free quote →- Spencer County Plan Commission & Building Inspector
- When to apply for a building permit
- Building permit and improvement location permit application
- When to notify the Building Inspector
- Filing deadlines and meeting dates
- Addressing for unincorporated areas
- Variances
- Rezoning petitions
- Special exception permits
- Subdivision exemptions
- Floodplain map
- Flood Damage Prevention Ordinance 2025-08
- Spencer County ordinances
- Highway Department permits
- Health Department, onsite sewage
- City of Rockport building permits
- FEMA Community Status Book, Indiana
Simplify Spencer County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Spencer County sooner?
Let Alliance prepare, file, and track your Spencer County permits while your crew stays on the job.
More Indiana permitting guides
Warrick County
Read guide →Dubois County
Read guide →Shelby County
Read guide →St. John Building Permit Guide
Read guide →St. Joseph County Building Permit Guide
Read guide →Starke County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Spencer County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.