In St. John, a town of about 24,800 people in Lake County, the Building & Planning Department at the Municipal Building, 10955 West 93rd Avenue (219-365-5301), reviews and issues building permits, and the Building Commissioner signs each one. The town takes applications through its Cloudpermit portal, by email or over the counter, and needs at least two working days to process a minor permit. Flat fees are posted for common projects (a fence or shed is $75, a deck $175), while a new house usually runs to more than $12,000 once water, sewer, park impact and escrow charges are added.
What requires a building permit in St. John?
The Building & Planning page lists the projects the town permits and the rules attached to each. Additions, remodels and roofs all need a building permit, and so do signs. Most small residential jobs carry their own flat fee and their own inspection order.
Building permit required
- New homes and commercial buildings, additions, remodels and roof work
- Decks and enclosed porches, set at least 5 feet in from side and rear lines, with posts below the 42-inch frost line
- Fences, up to 6 feet high in residential areas and kept out of the front yard
- Detached and attached garages
- Sheds, sized to the lot
- Above-ground and in-ground pools, spas and hot tubs
- Signs, with a separate application for temporary signs
Size and siting limits
- Accessory buildings: 400 sq ft on lots under 10,000 sq ft, 800 sq ft up to 20,000, 1,200 sq ft up to one acre and 1,600 sq ft on an acre or more; 14 feet high at most
- Sheds stay 6 feet from the house foundation and behind the house
- All garages on a lot together are capped at 1,100 sq ft, plus 540 sq ft on lots of 30,000 sq ft or more; detached garages need a lot of at least one acre
- Pools sit 10 feet from side and rear lines and 20 feet from a neighbor’s house
- Chain-link fencing only where a solid buffer screens it
A fence placed in an easement needs the town’s easement waiver and must be removed at the owner’s cost when utility work requires it. Subdivision covenants are enforced by the developer or homeowners association, not the town, but the application says association approval must be in hand before a permit is issued where one is needed.
What St. John decides and what the state holds
The town sets its own permit fees, zoning and subdivision rules, contractor registration and electrician exam, and it runs the inspections. A state Construction Design Release is still needed before construction of a Class 1 building such as a shop, an office or a building with three or more tenants, and the town permit does not replace it. A new rulebook may change the local layer: after a Plan Commission hearing on January 21, 2026, Ordinance 1883, which would replace Zoning Ordinance No. 1483, Subdivision Control Ordinance No. 1707 and Building Code Ordinance No. 1719 with one Unified Development Ordinance, came before the Town Council for first reading on April 8, 2026, and the Plan Commission then set a September 16, 2026 hearing to review it against the housing measures listed in IC 36-7-4.3-3.
Short on time to read all of this?
Get a free quote →St. John building department: who handles permitting
The Building & Planning Department coordinates land development, new homes, commercial projects and inspections. Plans are approved by the St. John Building Commissioner, whose signature releases the permit, and the town’s own electrical inspector checks wiring. Permits are paid for and collected at the Clerk-Treasurer’s Office in the same building. Code enforcement, including jobsite erosion control and contractor registration checks, has its own officer at 219-262-7773.
| Detail | Information |
|---|---|
| Office | Building & Planning Department, St. John Municipal Building, 10955 West 93rd Avenue, St. John, IN 46373 |
| Phone | (219) 365-5301 |
| Hours | Monday to Friday, 7:30 a.m. to 4:30 p.m. (the town FAQ gives 4:00 p.m. as the department’s closing time) |
| Online filing | Cloudpermit (us.cloudpermit.com/stjohnin) |
| Email filing | New construction: bpdept@stjohnin.gov; all other permits: permit2@stjohnin.gov |
| Boards | Plan Commission, Board of Zoning Appeals and Contractors Board, all reached through the department |
| Jurisdiction | Town limits only; the application asks for the township (Hanover, St. John or Center) |
St. John permit types
One Building Permit Application covers most work. It asks for the estimated project cost, the flood zone, setbacks on all four sides, the general, electrical and plumbing contractors, and, for new construction, living, basement and garage square footage, footing size, insulation, wall thickness, amperage and water line size. A plat of survey with the drawings goes with every application.
Residential permits
- New houses are filed by email to bpdept@stjohnin.gov or through Cloudpermit with a Contractors Affidavit listing every trade on the job, and the builder signs an escrow acknowledgment.
- Decks and enclosed porches use the secondary permit application with engineered, architectural or manufacturer plans showing the piers or pad and how the structure attaches, a plat of survey and the Indiana 811 ticket number.
- Garages need plans with footings and cross sections, a survey and the contractors affidavit; electrical service means a town-licensed electrician.
- Sheds need the maker’s or designer’s plans and two copies of the survey.
- Pools and spas need a survey showing the pool and every outlet, light and meter; the electrical permit is separate.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial buildings follow the same application with a meter count, a $2,000 occupancy escrow and the state design release for Class 1 work. Projects that need neither rezoning nor a plat still go to the Plan Commission for site plan review at a public meeting, without a hearing.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning and site plans. The department confirms the zoning of an address on request. Rezonings and plats go to the Plan Commission, which holds a study session on the first Wednesday and its regular meeting on the third Wednesday of the month at 7:00 p.m.
- Variances and special exceptions. The Board of Zoning Appeals meets on the first Wednesday of each month at 6:00 p.m. in the Town Hall council chambers; notices are posted at least 10 days before a hearing under Ordinance 1841.
- Stormwater and erosion control. Building sites follow Ordinance 1432 of 2006, and the department publishes an Erosion and Sediment Control Packet A; pool and some site permits carry a separate stormwater fee.
- Floodplain. The application asks for the flood zone. St. John takes part in the National Flood Insurance Program, with flood maps dated January 18, 2012.
- Utilities and digging. Call Indiana 811 at 1-800-382-5544 before any digging; new homes pay town water and sewer connection charges with the permit.
St. John permit costs and fees
New construction and additions are priced under the St. John Building Fee Schedule, which the town says is amended from time to time and does not post on its website. The flat fees below are the ones the Building & Planning page and FAQ publish. All fees must be paid in full before a permit is issued, by check, cash or card.
| Work | Fee |
|---|---|
| Deck or enclosed porch | $175, plus electrical fees if wired |
| Fence | $75 |
| Shed | $75, plus electrical fees if wired |
| Residential garage | $85, not counting zoning, electrical or plumbing permits |
| Above-ground or in-ground pool, spa or hot tub | $330, not counting electrical and stormwater fees |
| Additions, remodels, new buildings and signs | Under the Building Fee Schedule |
| Re-inspection after failed work | $75, due at the certificate of occupancy or final approval |
| Occupancy escrow (refundable) | $1,000 new residential; $2,000 new commercial |
| Park impact fee, residential permits | $2,162.45 (January 26, 2026 to January 25, 2027) |
| Contractor registration | $75 new or expired; $50 renewal |
| Permit extension or renewal | 60 days free; 6 months 25% of the building fee; 1 year 50% |
Rather talk it over?
Call 1-855-478-4290 →The FAQ breaks down a new house, which it says averages more than $12,000 in building and zoning permit costs. The total adds the electrical, plumbing (per fixture), sewer, zoning and stormwater permits, the water meter, water and sewer system development charges set by tap size (sewer development is $1,500 for almost every house), a sewer capacity charge, the park impact fee and the escrow. The park fee rises to $2,270.58 on January 26, 2027 and to $2,384.11 a year later, ending on January 25, 2029; the same FAQ still quotes $2,059.48 in its text, an older figure.
The escrow comes back if the builder finishes the driveway, grading, walks, steps and railings, gutters, swales, landscaping and house numbers and nobody moves in before the certificate of occupancy; early occupancy forfeits it.
Trade permits and who may pull them
Electrical, plumbing and HVAC work is listed on the same application and inspected by the town. Every contractor on a St. John job must be registered with the town at the time of application, and registrations lapse on December 31 each year.
- Registration package: a Lake County bond of at least $5,000 recorded at the Lake County Recorder, a certificate of insurance naming the town with at least $500,000 of general liability, and proof of workers’ compensation. Registrations go in by mail or in person.
- Lake County license: general, carpentry, drywall, insulation, awning, glazing, roofing, pool, masonry, fire protection and sprinkler contractors who are new or have lapsed must show a Lake County license.
- Electricians: those new to St. John pass the town’s electrical exam before registering. A homeowner who wants to wire a deck, shed or pool personally must pass the town’s homeowner electrical test first.
- Plumbers: registration needs a copy of the state plumbing license; plumbing fees are charged per fixture.
- General contractors watch two modules of the EPA’s construction inspection training course, and proof is needed for renewal.
The town’s Contractors Board reviews complaints about registered contractors and may revoke a registration when the Building Commissioner finds cause.
Rather not deal with the building department?
Get a free quote →How to apply for a St. John building permit
Call the department with the address to confirm the zoning and that the lot is inside the town.
Every contractor on the job must hold a current St. John registration before the application goes in.
Prepare the plat of survey, plans for the project type, the Indiana 811 ticket and any association approval or easement waiver.
Upload through Cloudpermit, email new homes to bpdept@stjohnin.gov and other work to permit2@stjohnin.gov, or bring a paper copy.
The department phones or emails when the permit is ready and confirms the fee.
Pay at the Clerk-Treasurer’s Office, then post the placard where it can be seen from the street.
Review, corrections and what causes delay
Small permits need at least two working days, and above-ground pools at least five. An application is complete only when every contractor is registered and the survey and plans required for that project type are attached. Under Indiana law in force since January 1, 2026, a unit that permits one- and two-family work must finish plan review within 7 business days of confirming an application is complete, or the applicant may use a qualified private reviewer. A permit is valid for one year from issuance; one extension or renewal is allowed, and a permit expired for more than 30 days is void.
Inspections and certificates in St. John
The permit holder must request every inspection, through the “Schedule an Inspection” form on the town website or by calling the department. Electrical inspections take place after 4:00 p.m. on weekdays, and someone must be home if panels are inside.
A new house moves through 14 stages in order: footing and foundation pre-pours, sewer test, backfill, underground plumbing, concrete pre-pour, plumbing pressure test, rough electric, framing with rough plumbing and HVAC, insulation, drywall, final electric, optional early service (which releases NIPSCO power) and final building. At backfill the builder files a surveyor location report showing the top of the foundation within 6 inches of the approved elevation, and the house must pass that stage before framing. A second survey proving the lot matches the approved drainage or grading plan is needed for the certificate of occupancy.
Smaller jobs have shorter lists, such as pier holes, framing and a final for a deck, and nothing may be used until every mandatory inspection has passed.
Indiana building code in St. John
St. John enforces the state’s codes for houses and commercial buildings through its own Building Commissioner. FEMA’s Community Status Book lists the Town of St. John (community 180141) as participating in the National Flood Insurance Program, with current flood maps effective January 18, 2012.
Want this handled start to finish?
Get a free quote →Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
St. John permit search and official resources
Applicants can track their own permits in Cloudpermit. For older permits, plans or certificates of occupancy, fill in the town’s Access to Public Records Request Form and give it to the Clerk-Treasurer’s Office; spoken requests have to be put on that form, and the town does not create new records to answer questions.
- St. John Building & Planning: permits, fees and forms
- Cloudpermit portal for St. John
- Building Permit Application
- Contractor Registration Form and requirements (2026)
- Contractors Affidavit
- Contractor acknowledgment of escrow and expiration
- Permit extension and renewal request
- Town FAQ: new home fee components and park impact fee
- Registered contractors list
- Plan Commission, BZA and Contractors Board
- Plan Commission and BZA legal notices
- Unified Development Ordinance hearing notice (January 21, 2026)
- Public records requests
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →St. John building permit FAQs
How much does a building permit cost for a new house in St. John?
The town says the building and zoning permit total for an average new house is more than $12,000, because it includes water and sewer charges, a $2,162.45 park impact fee and a $1,000 refundable escrow.
Do I need a permit for a fence?
Yes. A fence permit costs $75, fences in residential areas are limited to 6 feet, and the post holes are inspected before the posts are set.
Can I do my own electrical work?
Only after passing the town’s homeowner electrical test; otherwise the work must be done by an electrician licensed in St. John.
How big can a shed be?
It depends on the lot: 400 sq ft on lots under 10,000 sq ft, rising to 1,600 sq ft on an acre or more, and no taller than 14 feet.
How long does a permit take?
At least two working days for most small permits and five for an above-ground pool; the department calls when it is ready.
How long is a permit valid?
One year from issuance, with one free 60-day extension or a paid renewal. The town lists pool permits as shorter, giving 90 days on its permit page and 60 days in its FAQ.
Does my contractor need to register?
Yes. Every contractor must be registered with the town for the current year, with a recorded $5,000 Lake County bond and insurance; registration costs $75, or $50 to renew.
Simplify St. John permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in St. John sooner?
Let Alliance prepare, file, and track your St. John permits while your crew stays on the job.
More Indiana permitting guides
Lake County
Read guide →Cedar Lake
Read guide →Crown Point
Read guide →St. Joseph County Building Permit Guide
Read guide →Starke County Building Permit Guide
Read guide →Steuben County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about St. John permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.