Inside the City of Crown Point, the Building Department at 103 E. Clark Street (219-662-3239) issues the improvement location (building) permit together with the electrical, plumbing and HVAC permits, and it inspects the work. Applications are filed online by an authorized representative of a general contractor that holds a Crown Point license. Fees are set in Chapter 152 of the city code: additions, remodels and accessory buildings at a house cost $7 per $1,000 of estimated construction value, with a $50 minimum.
What requires a building permit in Crown Point?
Section 152.53 of the city code says a permit is needed before construction, alteration, demolition or repair of any building, structure or improvement, and it names decks, patios and balconies 12 inches or more above lot grade. A fireplace or a wood or coal stove needs a permit whatever it costs. Zoning code section 150.60 also requires one before any structure is built, rebuilt, moved, enlarged or structurally altered.
Permit required
- New houses, commercial buildings, additions and structural alterations
- Remodeling and repair work, including demolition
- Decks, patios and balconies 12 inches or more above grade
- Detached garages, sheds and other accessory structures
- Fireplaces and wood or coal burning stoves
- Swimming pools, including temporary inflatable pools
- Electrical services, plumbing fixtures and HVAC units
- Signs
No improvement location permit
- Patios, landings, balconies and decks under 12 inches above lot grade
- Retaining walls under 4 feet high
- Lawn furniture, play equipment and tree houses
- Essential services as defined in the zoning code
- Fences, which are not structures, but every fence still needs approval from the Planning and Zoning Department
- Minor electrical repairs such as replacing switches, lamps, sockets and receptacles
A permit expires if work has not begun within 180 days of issue, and again if the work is not finished within two years; work then stops until a new permit is issued. Occupying vacant land, a new or altered structure, or changing a use also needs an occupancy permit under Section 150.61.
What Crown Point decides and what the state holds
The city adopts the state’s building, residential, plumbing, electrical, mechanical, energy, pool, fire and fuel gas rules from 675 IAC by reference, along with later amendments as they are published. It sets its own fees, licenses contractors, runs zoning, stormwater, floodplain and historic district review, and inspects the work. For a Class 1 building, such as a shop, office or apartment block with three or more tenants, the state Construction Design Release comes first: the code bars the Building Department from issuing a local permit until it has a copy of the state release, unless 675 IAC 12-6-4 exempts the work. A one- or two-family house is permitted by the city.
Short on time to read all of this?
Get a free quote →Crown Point building department: who handles permitting
The Building Department handles building permits, plan review, inspections and certificates of occupancy for all work inside the city limits, under the Building Commissioner named in the city code. Zoning, fence approvals, plats and historic applications go through the city’s Planning Department, and stormwater plans are accepted by the City Engineer. Fees are paid to the Clerk-Treasurer, which also issues contractor licenses. Lake County’s Plan Commission has its office in Crown Point, but it permits only unincorporated land, not addresses inside the city (see the Lake County guide).
| Detail | Information |
|---|---|
| Office | Building Department, 103 E. Clark Street, Crown Point, IN 46307 |
| Phone and email | 219-662-3239; inspections@crownpoint.in.gov |
| City Hall | 101 N. East Street, 219-662-3250 (Clerk-Treasurer, Plan Commission and BZA meetings) |
| Online filing | City self-service permit portal (EnerGov), linked from the Building Department page |
| Contractor licenses | Clerk-Treasurer, under City Code Chapter 118 |
| Jurisdiction | City of Crown Point limits only |
Crown Point permit types
Crown Point treats the improvement location permit and the building permit as one document, the Improvement Location (Building) Permit. The Building Department’s checklist says that, depending on the job, an application may need a stamped survey drawing as the site plot plan, a site-specific foundation plan, full construction drawings with wall details and an electrical plan, a detailed erosion control plan, notarized affidavits for the general, electrical, HVAC and plumbing contractors, an energy compliance report, a fixture count and a complete list of contractors and subcontractors.
Residential permits
- New houses need the full plan set plus a grading plan certified by a professional engineer or licensed land surveyor showing final elevations, under Section 150.62.
- Additions, remodels and accessory buildings are charged by estimated construction value; pools, fireplaces, demolition and signs have their own fees.
- Fences need administrative approval from the Planning and Zoning Department instead of a building permit.
- Trade work is listed on the same permit: amperage for electrical service, fixture counts for plumbing and the number of HVAC units.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial, industrial and multi-family work pays the higher valuation rate and needs the state design release before the city issues its permit. Business and multi-family permits must include a solid waste plan showing how waste will be reduced, reused and recycled, and demolition permits need one for the debris. Commercial jobs estimated at $250,000 or more, and residential buildings with five or more units, carry mandatory conditions on workers’ compensation, worker classification and payroll records, enforced by stop-work orders.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning and plats. Zone changes, primary and secondary plats and site development plans are filed with the Planning Department and heard by the Plan Commission at 7:00 p.m. on the fourth Monday, in the Common Council Chambers at 101 N. East Street. The filing date is the fourth Friday of the month before, but a hearing date is set only after every department signs off.
- Board of Zoning Appeals. Variances follow the same monthly calendar at 5:30 p.m.
- Stormwater. No building permit is issued until the City Engineer accepts the stormwater plans, except for houses in approved subdivisions, buildings or additions under 500 square feet and land disturbance under 7,000 square feet.
- Historic districts. A certificate of appropriateness from the Historic Preservation Commission must accompany a building or demolition permit in a historic district. Applications go to the Planning Department; a certificate is issued if the commission does not act within 30 days, and it expires after 12 months.
- Floodplain. The Building Commissioner reviews new construction and substantial improvements for flood safety under Chapter 153.
Crown Point permit costs and fees
Permit and inspection fees are set by Section 152.55 of the city code, as printed in the 2024 Code of Ordinances posted on the city’s site; the section was last amended by Ordinance 2011-07-14. All fees are paid to the Clerk-Treasurer, and units of city government are exempt.
| Work | Fee |
|---|---|
| Agricultural and one- or two-family: additions, remodeling, alterations, accessory structures | $7 per $1,000 of estimated construction value; $50 minimum |
| Multi-family, condominium, office, commercial, industrial and other uses | $8 per $1,000 of estimated construction value; $100 minimum |
| Occupancy permit | $25 per dwelling unit or per unit |
| Electrical, new home | $100 (100 amp) or $125 (200 amp) plus $100 interior wiring; $0.25 per amp over 200; $50 temporary pole |
| Electrical, remodel or misc. | $75 branch circuit or misc. wiring; $75 NIPSCO inspection; service charges as for new homes |
| Electrical, commercial | Service charge plus $150 interior wiring; $150 interior build-out; $75 per sign hook-up |
| Plumbing | Residential $70 plus $5 per fixture ($30 minimum); commercial $75 plus $5 per fixture ($50 minimum per unit) |
| HVAC | $75 per unit (homes and multi-family); $100 per unit (commercial) |
| Fireplace | $50 each |
| Pools | $150 permanent above-ground; $50 inflatable; in-ground $50 plus $7 per $1,000 of cost |
| Demolition / signs | $25 / $50 plus $0.50 per square foot |
| Re-inspection | $25 each |
| Permit renewal | 10% of the original fee plus $25 per inspection still needed |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a home addition estimated at $40,000 is 40 × $7, or $280, before any separate electrical, plumbing or HVAC fees. City staff estimate the construction value from building valuation data. Water service is billed separately under Chapter 50: the codified connection and meter fee for a 5/8- or 3/4-inch meter is $1,573.10, plus a system development charge of $1,369 or $2,053; sewer connection and system development charges are added by the wastewater utility.
Trade permits and who may pull them
Electrical, plumbing and HVAC work is permitted and inspected by the Building Department, and every contractor and subcontractor on the job must hold a current Crown Point license before the application can be submitted. Chapter 118 requires a city license for any general or specialty contractor who builds, alters, repairs, moves or demolishes a structure.
- License test. Applicants pass a written examination given weekly in the Building Department office, with 76% needed to pass and a 30-day wait after a failure. The licensing board may accept a Lake County license earned by written examination instead.
- License fees. $50 application fee and $200 examination fee, $100 for a retest, and $100 when the license is issued. Renewal is $50 plus a $25 processing fee before December 31, with a $25 late fee after that.
- Insurance and vehicles. Licensed contractors file property damage and personal injury insurance of $500,000 per occurrence and $1,000,000 a year, and must mark vehicles and equipment with the company name and phone number.
- Electricians. Chapter 114 requires a city electrical contractor’s license. Replacing switches, lamps, sockets and receptacles, and repairing drop cords, is outside the permit rules.
- Plumbers. Plumbers hold the state plumbing license; City Code § 118.09(B) also requires state-licensed plumbers to pay the city’s specialty contractor license fee to work in Crown Point, renewed only in person.
- Homeowners. The licensing chapter does not apply to an owner or occupant who alone builds, alters or repairs their own dwelling, but that exclusion can be used for a new house only once every five years.
Rather not deal with the building department?
Get a free quote →Working without a license carries fines of $500 to $2,500 plus costs per day.
How to apply for a Crown Point building permit
Use the city’s GIS maps; land outside the limits goes to the county or another town.
The general contractor and each subcontractor need a current Crown Point license from the Clerk-Treasurer before filing.
Get any variance, plat or site plan approval, City Engineer stormwater acceptance and a certificate of appropriateness first.
Stamped survey plot plan, foundation and building plans, erosion control plan, notarized trade affidavits, energy report, fixture count and contractor list.
An authorized representative of the licensed general contractor submits through the city’s self-service portal; commercial jobs attach the state design release.
Pay the fees to the Clerk-Treasurer and keep the approved plans on site.
Review, corrections and what causes delay
The Building Commissioner checks each application against the code, the approved site development plan and the flood rules before issuing it. Common hold-ups are an unlicensed subcontractor on the list, a plot plan that is not a stamped survey, a missing certified grading plan on new homes, and stormwater plans not yet accepted by the City Engineer. Send review questions to inspections@crownpoint.in.gov.
Inspections and certificates in Crown Point
The code lists at least 14 inspections for a building permit, in order: footing pre-pour, footing, foundation pre-pour, foundation, rough framing, underground plumbing or electrical, rough plumbing, rough electrical, rough HVAC, gas line, insulation before drywall, electrical service, final HVAC and the final occupancy inspection. No concrete may be poured for foundations, and no electrical, mechanical, plumbing or insulation work covered, before it passes. Buildings other than one- and two-family houses, including any fireplace work, also get a rough and final fire inspection by the city fire inspector or fire chief.
Each inspection beyond those authorized, or one called when the work is not ready, costs $25, and the certificate of occupancy is not issued until all inspection and re-inspection fees are paid. A decision of the Building Commissioner can be appealed in writing to the Board of Public Works and Safety within 10 days through the Clerk-Treasurer, and then to the state Fire Prevention and Building Safety Commission. Book inspections at 219-662-3239 or by email.
Want this handled start to finish?
Get a free quote →Indiana building code in Crown Point
Crown Point’s Building Code (City Code Chapter 152) adopts the state rules of the Fire Prevention and Building Safety Commission by reference, including later amendments, and the Building Commissioner enforces them; a local variance from the fire safety rules takes effect only after the state commission approves it. FEMA’s Community Status Book lists Crown Point (community 180128) as participating in the National Flood Insurance Program, with flood maps effective January 18, 2012.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Crown Point permit search and official resources
For the history of a permit, inspection or certificate of occupancy at a Crown Point address, ask the Building Department by phone or at inspections@crownpoint.in.gov, or check the project in the online portal if you filed it. Plan Commission and Board of Zoning Appeals agendas are posted in the city’s Agenda Center.
- Crown Point Building Department and submittal checklist
- Online permit application portal (self-service)
- 2024 Code of Ordinances (fees in § 152.55; licensing in Chapter 118)
- Clerk-Treasurer (contractor licenses and fees)
- Plan Commission 2026 meeting and filing dates
- Board of Zoning Appeals 2026 meeting and filing dates
- Agenda Center (Plan Commission, BZA, Historic Preservation)
- Crown Point GIS maps
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Crown Point building permit FAQs
Can a homeowner pull a permit in Crown Point?
The Building Department says permits are submitted by an authorized representative of the licensed general contractor. The licensing chapter excludes an owner or occupant who alone works on their own dwelling, used no more than once every five years for a new house, so call the department before filing as an owner.
Do I need a permit for a fence?
Not a building permit, because the zoning code does not treat a fence as a structure, but every fence needs administrative approval from the Planning and Zoning Department before it goes up.
Does a deck need a permit?
Yes if any part is 12 inches or more above lot grade; lower decks, patios and landings are exempt from the improvement location permit.
How much is a permit for a room addition?
$7 per $1,000 of the value estimated by city staff, with a $50 minimum, so a $40,000 addition is $280 plus trade permits.
How do contractors get a Crown Point license?
Apply through the Clerk-Treasurer, pay $50 plus a $200 exam fee, pass the written test with 76%, file insurance and pay $100 when the license is issued.
How long is a permit valid?
Work must start within 180 days and finish within two years; after two years a renewal costs 10% of the original fee plus $25 per remaining inspection.
Does the county issue permits in Crown Point?
No. The Lake County Plan Commission works only in unincorporated areas; inside the city, the Crown Point Building Department issues permits.
Simplify Crown Point permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Crown Point sooner?
Let Alliance prepare, file, and track your Crown Point permits while your crew stays on the job.
More Indiana permitting guides
Lake County
Read guide →East Chicago
Read guide →Gary
Read guide →Danville Building Permit Guide
Read guide →Daviess County Building Permit Guide
Read guide →Dearborn County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Crown Point permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.