Danville, Indiana Building Permit Guide

To get a building permit in Danville, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Town of Danville’s Building Department at Town Hall, 49 North Wayne Street, issues the improvement location permit that doubles as the building permit for every structure in town, taking applications online and charging fees under Ordinance 9-2024.

Authority: Town of Danville Building DepartmentFees: Ordinance 9-2024Phone: 317-745-4180 ext. 3001
Authority
Danville Building DepartmentTown Hall, 49 N. Wayne St.
New house fee
$300 + $0.10/sq ftOrdinance 9-2024
Processing
Up to 10 business daysComplete iWorQ application
Sewer + water taps
$4,500 + $2,5005/8–3/4 in. meter, before permit

In the Town of Danville, the Building Department in Development Services at Town Hall, 49 North Wayne Street, issues permits for all structural improvements to buildings and property in town; call 317-745-4180, extension 3001. Under the 2024 Unified Development Ordinance the improvement location permit (ILP) is the building permit, applications are filed through the town’s iWorQ portal, and processing can take up to 10 business days. Fees come from Ordinance 9-2024, adopted May 1, 2024: a new single-family house is $300 plus $0.10 a square foot, and the builder pays the town’s sewer and water connection charges before the permit is issued.

What requires a building permit in Danville?

Danville’s UDO requires an improvement location permit for the erection, alteration or modification of all structures in the town’s jurisdiction, and says every new structure needs one, including houses, all accessory structures, manufactured homes, temporary structures and signs. No building may be erected, moved, added to or structurally altered, and no structural change in the use of a building or land made, until the Administrator issues it. The Building Department’s own list shows how that applies to homes.

Typical residential permits

  • New home construction and home additions
  • Remodeling projects
  • Roof replacement and solar panel installation
  • New patios and decks
  • Fences and swimming pools
  • Accessory structures such as garages and sheds
  • Demolition

Other ILPs and approvals

  • Signs and temporary storage containers
  • Wireless communication facilities
  • Construction trailers and other temporary uses
  • A land disturbance permit for site work
  • Right-of-way permits, which require a bond
  • A certificate of appropriateness where one applies

The department asks owners to call before any construction or renovation to confirm whether a permit is needed. Accessory structures, pools and fences cannot sit in an easement of any kind, and accessory buildings that need a permit must stand in line with or behind the front of the house. Work started before the permit is issued costs twice the listed fee.

What Danville decides and what the state holds

The town writes and enforces its UDO (adopted by Ordinance 01-2024), sets permit and utility connection fees in Town Code section 35.02, decides plats, rezonings, variances and design review in the Corridor Protection Overlay District, and issues certificates of occupancy. Indiana supplies the building codes through the Fire Prevention and Building Safety Commission. The UDO bars an ILP for a commercial or industrial use until the state approvals it needs are in hand, which for a Class 1 building used by the public or by employees includes the state Construction Design Release, and bars an ILP for a structure served by a septic system until the Hendricks County Health Department has issued the septic permit or the Health Officer has authorized the system.

Short on time to read all of this?

Get a free quote →

Danville building department: who handles permitting

Development Services has two parts. The Building Department oversees all construction in town, reviews permits and enforces the building code. The Planning Department handles land use within the town’s incorporated limits and coordinates the Plan Commission, the Board of Zoning Appeals and the Design Review Committee. The Development Services page sends questions on building permits and fees, inspection scheduling, building code, stormwater quality and impervious surface calculations to the town’s Utility Director. Unincorporated Hendricks County is served by the county’s Planning & Building Department (317-745-9255), which also has its offices in Danville.

Danville permit contacts
DetailInformation
OfficeDevelopment Services, Danville Town Hall, 49 North Wayne Street, Danville, IN 46122
Building Department317-745-4180 ext. 3001
Planning & Zoning317-745-4180 ext. 1101; fax 317-745-3005
Hours8 a.m. to 4 p.m., closed daily from noon to 1 p.m.
ApplicationsiWorQ portal for building permits and for planning and zoning applications
New water serviceClerk-Treasurer’s office, 317-745-4180 ext. 8015

Danville permit types

The Building Department lists what to upload for each kind of project, and the iWorQ application asks for the matching plans. Residential and commercial projects use different plan sets.

Residential permits

  • New single-family homes: a dimensioned plot plan, scaled building plans with elevations showing doors and windows, a truss layout, an erosion control plan, an energy compliance plan, and proof the house meets any PUD requirements.
  • Additions, including covered or attached decks and porches, and remodels: a plot plan, dimensioned building plans with elevations, the existing and proposed floor plans, and plumbing, electrical or HVAC plans where those change.
  • Accessory structures: a plot plan showing the height at the peak and dimensioned plans; the department notes that a 10% rule applies.
  • Swimming pools: a plot plan, pool plans, electrical plans, the concrete apron or deck dimensions and any automatic cover.
  • Fences: a plot plan with dimensions and the style and height of the fence, under the town’s fence permit procedure.
  • Roofs and solar panels: the materials and warranty, and for solar a letter stating the roof can carry the panels.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Commercial and industrial principal buildings, accessory buildings, additions, remodels, fences, pools, parking lots, trade work, roofing, demolition and temporary trailers each have a fee line in Ordinance 9-2024. The fee line for demolishing a commercial principal building notes that a COA may be required. The fire section of the same ordinance adds plan review and protection-system fees and a $25 fire department occupancy permit. Inside the Corridor Protection Overlay District, which covers property along Main Street and US 36 between Shady Lane and Warrior Way and around the Courthouse Square, new primary structures other than single- and two-family homes need development plan approval, and the Design Review Committee reviews exterior renovations and new construction.

What comes before the building permit

  • Planning and zoning. Annexation, rezoning, plats, site plans, variances, special exceptions and architectural review are filed in iWorQ and may go to the Plan Commission, BZA, Design Review Committee or Town Council before a building permit can issue.
  • Platted lots. Public improvements must be installed and inspected, and the plat recorded, before an ILP is issued.
  • Septic. A Hendricks County Health Department septic permit for any structure on a septic system.
  • Utility connections. The builder pays the wastewater and water connection charges before the permit is issued; new water service starts with the Clerk-Treasurer’s office.
  • Right-of-way. A $150 right-of-way permit, with a bond, for work in the street.

Danville permit costs and fees

Permit fees are set in Town Code section 35.02 as amended by Ordinance 9-2024, which the Town Council adopted on May 1, 2024; the town’s ordinance page lists no later fee ordinance. Under the UDO, ILP fees are worked out during review and collected when the permit is issued, re-inspection fees are collected before the final inspection or certificate of occupancy, and ILP fees are non-refundable.

Rather talk it over?

Call 1-855-478-4290 →
Danville permit fees (Ordinance 9-2024)
WorkFee
Single-family dwelling$300 + $0.10 per sq ft
Two-family dwelling$400 + $0.10 per sq ft
Multi-family dwelling$400 + $50 per unit + $0.10 per sq ft
Residential room addition or remodel, 1–3 rooms / more than 3$100 / $150, each + $0.10 per sq ft
Garage, shed or similar, under / over 500 sq ft$100 / $150, each + $0.10 per sq ft
Deck / fence$100 / $75
Pool, in-ground / above-ground$150 / $100
Residential electrical, plumbing or mechanical$100 each
Roof, added layer / remove and replace (residential)$75 / $100
Commercial or industrial principal building$400 + $0.10 per sq ft up to 25,000 sq ft; $400 + $0.06 per sq ft above 25,000 sq ft
Commercial addition or remodel, principal$200 + $0.10 per sq ft
Re-inspection / field inspection$100 / $100
Right-of-way permit (bond required)$150
Fire department plan review$0.10 per sq ft, $75 minimum
Wastewater connection, 5/8–3/4 in. / 1 in. meter$4,500 / $8,500
Water connection, 5/8–3/4 in. / 1 in. meter$2,500 / $4,500

Worked example: a 2,000-square-foot single-family house on a 5/8–3/4-inch meter costs $300 plus 2,000 × $0.10 ($200), or $500, for the permit, plus $4,500 for the wastewater connection and $2,500 for the water connection, both paid before the permit is issued: $7,500 in all, before any separate trade permits or re-inspections. Fees double if construction starts before the permit, and rise to ten times the listed amount if work continues after a stop work order. The commercial bands in the ordinance do not say how floor area above 25,000 square feet is split between the two rates, so ask the Building Department for a figure on large buildings. Developers also pay acreage fees for wastewater ($2,000 an acre) and water ($1,500 an acre) before plat approval.

Trade permits and who may pull them

Danville charges for electrical, plumbing and mechanical work separately: $100 for each trade on a residential job and $100 each on commercial work. Remodel and addition applications ask for plumbing, electrical and HVAC plans where the work touches them. The fee schedule also lists a $100 patio or slab inspection, a $100 sewer lateral inspection and a water service line installed by directional boring at $1,500 plus $10 a foot.

  • Plumbing: Indiana licenses plumbing contractors through the Indiana Plumbing Commission.
  • Electrical and HVAC: there is no state license; the town’s permit pages do not describe a local license or contractor registration.
  • Fire protection: sprinkler systems are $100 per riser, fire alarm systems $100 per annunciation zone and special hazard systems such as hood suppression $100 per system; first acceptance tests carry no charge, and later ones are $75.

Rather not deal with the building department?

Get a free quote →

How to apply for a Danville building permit

1. Check zoning and overlays

Look the parcel up on the town’s Beacon GIS zoning map and note whether it sits in the Corridor Protection Overlay District.

2. Clear planning approvals

File any rezoning, plat, site plan, variance or architectural review in iWorQ and follow the procedural guideline for that case.

3. Line up outside permits

Septic permit from the Hendricks County Health Department, state approvals for commercial work, and water service through the Clerk-Treasurer.

4. Apply in iWorQ

Create an account, complete the building application and attach the plans listed for your project type.

5. Pay when the permit issues

The ILP fee and connection charges are collected at issue.

6. Build and book inspections

Work under the ILP, which is valid for one year.

Review, corrections and what causes delay

A complete application can take up to 10 business days to process, and the Planning Department warns that incomplete applications delay review. For a new house the upload list includes a truss layout, an erosion control plan and an energy compliance plan as well as the drawings. The Administrator can grant up to two six-month extensions on request; once an ILP expires, a new application and fee are needed. Changes to an approved ILP go in as an amendment, which may carry more fees.

Inspections and certificates in Danville

Every inspection required for an ILP must be completed, and no structure may be used until the final inspection is approved. The Development Services page sends inspection scheduling questions to the town’s Utility Director, and the Building Department answers at 317-745-4180, extension 3001. The fee schedule charges $100 for each re-inspection and $100 for a field inspection. Its fire section lists initial site and construction inspections at no charge, a first fire re-inspection (about 30 days) free, a second $100 and any later ones $250.

The Administrator issues the certificate of occupancy once all work is complete, every inspection has been passed and any required driveway has been installed and inspected. Where weather keeps required landscaping from going in before occupancy, the UDO allows a temporary certificate with a commitment to plant within 120 days. Occupying a building without the fire department occupancy permit costs $250 a day under the fee ordinance.

Indiana building code in Danville

Danville enforces the state building codes through its own Building Department, with the 2024 UDO and Town Code governing everything local. FEMA’s Community Status Book lists the Town of Danville (community 180088B) as participating in the National Flood Insurance Program, with flood maps effective June 15, 2022.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Danville permit search and official resources

Applications are filed through the town’s iWorQ portal. For copies of permits, plans or other town records, Danville takes public record requests through the Public Record Request form in the town’s online Action Center. Research on permits or zoning verification costs $25 under Ordinance 9-2024.

Inspections are where schedules slip.

Get a free quote →

Danville building permit FAQs

Is Danville a city or a town?

A town. Permits come from the Town of Danville’s Building Department at Town Hall, 49 North Wayne Street.

How much is a permit for a new house?

$300 plus $0.10 per square foot under Ordinance 9-2024, so $500 for 2,000 square feet; sewer and water connection charges of $4,500 and $2,500 for a standard meter are paid before the permit issues.

Do I need a permit for a fence or deck?

Yes. A residential fence permit is $75 and a deck $100, and fences may not be placed in easements.

How long does a permit take?

Up to 10 business days to process a complete application. The ILP is then valid for one year.

What happens if I start work without a permit?

The fee doubles, and if work continues after a stop work order the fee is ten times the listed amount.

Does a new roof need a permit?

Yes. Roof replacement is on the town’s list; a residential tear-off is $100, and solar panels need a letter that the roof can carry them.

Who handles a parcel outside Danville?

Unincorporated Hendricks County parcels go to the county’s Planning & Building Department, 317-745-9255.

Simplify Danville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Danville sooner?

Let Alliance prepare, file, and track your Danville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Danville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.