To get a building permit in Avon, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Avon’s Building Department at Town Hall, 6570 East U.S. Highway 36, reviews and issues building permits for work inside town limits, takes applications through the town’s online portal and charges fees set by Ordinance 2026-08.

Authority: Town of Avon Building DepartmentFees: Ordinance 2026-08Phone: 317-272-0948
Authority
Avon Building Department6570 E. U.S. Highway 36
New house fee
$534 + $0.15/sq ft2026 schedule, Ord. 2026-08
Review time
Up to 30 daysPer the application affidavit
Payment
Card or cashier’s checkNo cash accepted

Inside the Town of Avon, building permits come from the town’s own Building Department at Town Hall, 6570 East U.S. Highway 36 (317-272-0948), where Mike Tulli has been Building Commissioner since 1996. Applications go through the town’s online iWorQ portal, and the town code requires a permit before any building or structure is built, altered or repaired when the cost tops $100. Fees come from the 2026 schedule adopted as Ordinance 2026-08 on May 28, 2026: a new single-family house is $534 plus $0.15 a square foot.

What requires a building permit in Avon?

Avon’s rule is broad. Section 7-7 of the town code says a permit must be obtained before construction, alteration or repair of any building or structure whose cost exceeds $100, on forms supplied by the Building Commissioner, with fees paid to the Clerk-Treasurer. The 2026 fee schedule shows how far that reaches in practice: it prices houses, additions, remodels, garages and sheds, pools, fences, roofing, relocation, demolition, temporary mobile homes, signs and stand-alone electrical, plumbing, heating or cooling work.

Permit needed

  • New houses, two-family and multi-family buildings
  • Room additions and remodels, including accessory buildings
  • Garages, storage buildings and other accessory structures
  • Fences and walls, swimming pools and signs
  • Roofing, whether one added layer or a complete tear-off
  • Electrical, plumbing, heating or cooling work on its own
  • Moving or demolishing a building

Separate approvals

  • Development plan review, plats and rezonings before the Advisory Plan Commission
  • Variances and special exceptions before the Board of Zoning Appeals
  • A town driveway access permit for a new or altered driveway approach
  • A sanitary sewer tap-in permit for a new connection
  • An encroachment agreement for a fence inside a drainage easement

The code lists no exemptions by size or type of work, so call the Building Department before assuming a project is too small to need a permit. Fences need a permit too, and a fence planned inside a drainage easement leads to a signed encroachment agreement with the town.

What Avon decides and what the state holds

Avon adopts the Indiana Fire Prevention and Building Safety Commission’s building rules by reference (code section 7-6), so the technical standards are the state’s. The town sets its own fees, runs zoning through its first Unified Development Ordinance, reviews flood safety on new construction and substantial improvements, issues certificates of occupancy and hears building appeals first through the Advisory Plan Commission before they go to the state commission. Projects that need a state Construction Design Release must give the Building Commissioner a copy of it before the town issues a permit, under section 7-26.

Short on time to read all of this?

Get a free quote →

Avon building department: who handles permitting

The Building Department oversees all construction activity in the town, along with permit review and building code compliance. The Planning Department, in the same building, handles zoning, development plans, plats and code enforcement, and staffs the Advisory Plan Commission and the Board of Zoning Appeals. Unincorporated Hendricks County is served by the county’s Planning & Building Department in Danville (317-745-9255), so check the parcel against the town’s corporate limits first.

Avon permit contacts
DetailInformation
OfficeBuilding Department, Avon Town Hall, 6570 East U.S. Highway 36, Avon, IN 46123
Phone / fax317-272-0948 / 317-272-0949
Building CommissionerMike Tulli, state-certified building inspector and plans examiner
ApplicationsBuilding permits through the town’s iWorQ portal; planning cases through a separate planning portal
PaymentCashier’s check or credit card for building permits; the Planning Department takes check or card; no cash
Planning boardsAdvisory Plan Commission, 6:30 p.m. on the fourth Monday; BZA, 6:30 p.m. on the third Tuesday; both at Town Hall

Avon permit types

One Building Permit Application covers new work, additions, remodeling, re-roofing and electrical jobs on principal and accessory structures. It asks for the lot’s subdivision, zoning classification and dimensions, the owner, engineer or surveyor and builder, total and living area, height, rooms and baths, parking spaces, the estimated construction cost and the water, sewer and power suppliers. A second page records flood data where the site lies in the 100-year floodplain: the flood elevation and the first-floor elevation above sea level.

Residential permits

  • New homes. Single-family, two-family and multi-family dwellings each have a base fee plus a square-foot charge.
  • Additions and remodels. Priced by the number of rooms added; a remodel that adds no rooms has a lower base fee.
  • Fences. A separate Fence Permit Application with two copies of a survey or plot plan showing the fence and every easement, and a sheet showing the material and style. Fences must follow the UDO’s fence and wall standards.
  • Pools, roofing, relocation and demolition. Flat fees on the 2026 schedule.
  • Temporary mobile homes. A $234 permit.

Commercial permits

Commercial and industrial buildings have their own rows on the schedule for principal and accessory uses, additions, remodels, trade work, roofing, relocation and demolition. Signs need a sign permit under the UDO’s sign standards, and a master signage plan carries its own $334 fee. Development plan review applications go to the Plan Commission through the planning portal, and the building application fee does not cover the separate design review and construction management charges billed directly by the engineering firm the town names.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning and plan approvals. The application asks for any variance or Plan Commission case number. Development plan review, plats, PUDs and rezonings use the planning portal.
  • State approvals. The form lists the State release of plans number, IDEM and Department of Natural Resources approvals where they apply.
  • Sewer. A sanitary sewer tap-in permit for a new connection.
  • Driveways. The town code requires a driveway access permit for a new driveway, approach or crossover and for relocating or altering one, reviewed against the INDOT driveway manual within 10 business days, with a bond of at least $5,000 for work in the right-of-way.
  • Floodplain. The Building Commissioner checks that new construction and substantial improvements are reasonably safe from flooding.

Avon permit costs and fees

Building permit fees come from the 2026 Building Permit Fee Schedule, Exhibit A to Ordinance 2026-08, which the Town Council introduced on May 14, 2026 and passed on final reading on May 28, 2026; the posted copy is marked updated August 2026. Most building fees are a flat base fee, and many add $0.15 for each square foot.

Avon building permit fees (Ordinance 2026-08)
WorkFee
Single-family dwelling$534 + $0.15 per sq ft
Two-family dwelling$634 + $0.15 per sq ft
Multi-family$534 + $0.15 per sq ft + $50 per unit
Residential accessory use (garage, storage)$134 + $0.15 per sq ft
Room addition, 1 to 3 rooms / 3 or more rooms$134 / $234, each + $0.15 per sq ft
Fence$234 + $0.15 per sq ft
Residential remodel, principal / accessory (no added rooms)$134 / $84, each + $0.15 per sq ft
Swimming pool$209
Residential electrical, plumbing, heating or cooling$109
Residential roofing, one layer or complete removal$134
Residential demolition, principal / accessory$234 / $134
Commercial or industrial principal use$534 + $0.15 per sq ft
Commercial remodel, principal (no added rooms)$184 + $0.15 per sq ft
Sign permit / master signage plan / temporary sign$334 / $334 / $134
Re-inspections: first / second / third additional$134 / $234 / $434

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a new single-family house counted at 2,400 square feet costs $534 plus 2,400 × $0.15 ($360), or $894, before any re-inspection fees. Ask the Building Department which floor area it measures, since the application records both total area and living area.

Planning fees are separate and took effect on February 12, 2026, the night the council passed Ordinance 2026-01 on planning and engineering fees. A development standards variance is $1,000 plus $500 for each additional variance, a use variance $2,000, a special exception $1,000, an administrative appeal $500, a zoning letter $75 and development plan review $2,000 plus $50 an acre and $500 per waiver; consulting engineer reviews, effective January 2026, are billed by the town’s engineering firm at $175 an hour beyond the hours each fee includes. The town code’s fee appendix, as updated through June 2022, lists $275 for a driveway permit and $200 plus $0.50 per linear foot beyond 100 feet for a right-of-way permit.

Trade permits and who may pull them

Avon prices trade work on the same schedule as building work: a stand-alone residential electrical, plumbing, heating or cooling job is $109, a commercial one $134 plus $0.15 a square foot, and an industrial one $184. The building permit application itself lists electrical work among its types of structural work.

  • Plumbing: plumbing contractors are licensed by the state through the Indiana Plumbing Commission; the town code adds no local plumbing license.
  • Electrical and HVAC: neither the town code nor the application sets up a local license or registration for these trades.
  • Fire protection: the code lets the fire chief or a designee help the Building Commissioner inspect sprinkler, detection and alarm systems and report back.
  • Who signs: the person signing the application takes responsibility for scheduling every inspection, and contractors book them in the portal with a Contractor Access Code.

Rather not deal with the building department?

Get a free quote →

How to apply for an Avon building permit

1. Confirm the parcel is in Avon

Use the town’s list of subdivision zoning classifications inside corporate limits, or ask the Planning Department.

2. Clear planning steps

Get any variance, development plan or plat approval first and note the case number.

3. Gather state and utility approvals

Design release number for Class 1 work, IDEM or DNR approvals and a sewer tap-in permit where they apply.

4. Apply online

File through the Building Department’s iWorQ portal with a plot plan showing lot lines and the plans for the work.

5. Pay the fee

Use a credit card or cashier’s check; cash is not accepted.

6. Post the permit

Display it on site where it can be seen from the street before work starts.

Review, corrections and what causes delay

The application warns that review may take up to 30 days and that an incomplete form will not be reviewed. For fences, staff review the plot plan first and then tell the owner whether a utility location report and an encroachment agreement are needed; a fence placed in a swale must be at least 35% pervious. Any change from the approved application needs a new permit, and a permit is void if work has not started within 12 months of issue. If the posted permit is lost or destroyed, work must stop until a new one is posted.

Inspections and certificates in Avon

The applicant schedules every inspection and needs the permit number to do it; contractors use the portal’s contractor access code. Work found incomplete or not ready costs a re-inspection fee of $134 the first time, then $234 and $434. The Building Commissioner may issue a written stop work order when work is unsafe, proceeds without a permit, or continues more than 30 days after the permit was issued without the other government approvals it needs, such as those for drainage, flood control, access or waste disposal.

Nobody may occupy a building until all inspections have passed and the Building Commissioner has issued a full, partial or temporary certificate of occupancy; the permit holder must request the final inspection. Demolition follows its own article: the written application is copied to the Town Manager, the utilities and the neighbors, the Building Commissioner inspects the site first, and the applicant posts a performance bond from $1,000 for buildings up to 3,000 square feet to $4,000 for buildings up to 100,000 square feet, plus a $1,000,000 liability insurance certificate.

Indiana building code in Avon

Avon enforces the state’s building rules, which it adopts by reference with later amendments, through its own Building Commissioner. FEMA’s Community Status Book lists the Town of Avon (community 180520B) as participating in the National Flood Insurance Program, with flood maps effective June 15, 2022, and the building application asks for flood elevations on floodplain sites.

Want this handled start to finish?

Get a free quote →

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Avon permit search and official resources

Current applications and inspection requests run through the town’s iWorQ portal and its contractor portal. For older files, plans or certificates, Avon asks for public records requests in writing to the Clerk-Treasurer’s office, using the town’s Written Records Request Form. The Building Department also posts a list of residential permits issued from 1996 to 2011.

Inspections are where schedules slip.

Get a free quote →

Avon building permit FAQs

How much is a building permit for a new house in Avon?

$534 plus $0.15 per square foot under Ordinance 2026-08; a 2,400-square-foot house is $894 before any re-inspection fees.

Do I need a permit for a fence?

Yes. File the Fence Permit Application with two copies of a survey or plot plan; the 2026 fee is $234 plus $0.15 per square foot, and a fence in a drainage easement needs a signed encroachment agreement and, if staff ask for one, a utility location report.

Does replacing a roof need a permit?

Yes. The schedule charges $134 for a residential roof, whether one layer is added or the old roof is removed.

How long does review take?

The application says up to 30 days, and a permit lapses if work has not started within 12 months of issue.

How do I pay?

By credit card or cashier’s check for building permits; the Planning Department takes check or card. Neither accepts cash.

Who handles a parcel in unincorporated Hendricks County?

Hendricks County’s Planning & Building Department in Danville, at 317-745-9255, not the town.

When does the Board of Zoning Appeals meet?

At 6:30 p.m. on the third Tuesday of each month at Town Hall; the Advisory Plan Commission meets at 6:30 p.m. on the fourth Monday.

Simplify Avon permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Avon sooner?

Let Alliance prepare, file, and track your Avon permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Avon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.