Posey County, Indiana Building Permit Guide

To get a building permit in Posey County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Posey County Building Commissioner in Mount Vernon permits and inspects construction everywhere in the county except Mount Vernon, New Harmony, Poseyville and Griffin, after an improvement location permit from the Area Plan Commission.

Authority: Posey County Building CommissionerZoning: Area Plan CommissionPhone: 812-838-1324
Building
Building Commissioner126 E. Third St., Room 132
New house
$0.08 per sq ftMinimum $150, trades extra
Zoning first
Improvement location permitArea Plan Commission 812-838-1323
Septic
Health Department$75 new residential permit

In Posey County, building permits and inspections come from the Building Commissioner’s Office at 126 East Third Street, Room 132, Mount Vernon (812-838-1324), headed by Building Commissioner Ed Batteiger. It covers the whole county except the city of Mount Vernon and the towns of New Harmony, Poseyville and Griffin. The first stop is usually the Area Plan Commission, in the same office, for an improvement location permit; both offices now take applications through online portals, and a new house is charged $0.08 per square foot with a $150 minimum, plus trade permits.

What requires a building permit in Posey County?

The Building Commissioner’s office issues construction permits and inspects “all residential and commercial structures built or remodeled” in its area, and its fee schedule shows how wide that net is. It prices houses, manufactured and modular homes, garages and pole buildings, pools and spas, remodels and additions, siding, roofing, windows and doors, electrical, plumbing and heating work, signs, moving and wrecking buildings, tank removal, and fire sprinkler and alarm systems.

Building Commissioner permits

  • New houses, two-family and multi-family dwellings
  • Modular homes and mobile homes
  • Detached garages, pole buildings, storage buildings and carports
  • Additions, enclosed porches, open porches and decks
  • Siding, roofing, foundation, window and door replacement
  • In-ground pools, and above-ground pools, spas and hot tubs over 3½ feet deep
  • Electrical, plumbing and heating or air conditioning work
  • Demolition, building moves and underground tank removal

Area Plan Commission approvals

  • Improvement location (land use) permit for new structures and additions
  • Placing a mobile home
  • Special use and variance requests
  • Rezoning
  • Site development plans
  • Subdividing land or starting a business

Agricultural buildings on a farm of at least 50 acres and churches still need every permit but pay no permit fee under the county schedule. Failing to get a required permit can bring a fine of $100 to $500.

What Posey County decides and what the state holds

The county writes its own building ordinance, fee schedule and inspection sequence, and the Area Plan Commission administers a Unified Development Ordinance shared by the City of Mount Vernon, the Town of Cynthiana, the Town of Poseyville and unincorporated Posey County. The state’s building rules set the technical standard, and the Building Commissioner asks for the state design release, where it applies, with the permit application.

Posey County building department: who handles permitting

Two county offices share Room 132 at 126 East Third Street in Mount Vernon. The Building Commissioner’s Office issues building and trade permits, inspects, and answers complaints about unsafe buildings, abandoned vehicles, weeds and nuisances. The Area Plan Commission office, led by Executive Director Jerry Cotner, issues improvement location permits and staffs the Area Plan Commission and Board of Zoning Appeals, whose members are appointed by the county, the City of Mount Vernon, the Town of Poseyville and the school systems.

Short on time to read all of this?

Get a free quote →
Who permits where in Posey County
PlaceBuilding permits
Unincorporated Posey CountyCounty Building Commissioner; zoning by the Area Plan Commission
Cynthiana (town)County Building Commissioner; zoning under the shared Unified Development Ordinance
Mount Vernon (city)Outside the county building area; the city’s permit page sends building permit requests to the Mayor’s Office, 520 Main Street; zoning under the shared ordinance
Poseyville (town)Outside the county building area; zoning under the shared ordinance
New Harmony and Griffin (towns)Outside the county building area and not named in the shared zoning ordinance; ask the town
Posey County permit offices
OfficeContact
Building Commissioner’s Office126 East Third Street, Room 132, Mount Vernon; 812-838-1324; Monday to Friday, 8:00 a.m. to 4:00 p.m.
Area Plan CommissionSame address; (812) 838-1323; areaplancommission@poseycountyin.gov; 8:00 a.m. to 4:00 p.m.
Health Department (septic)100 Vista Drive, Mount Vernon; (812) 838-1328; Environmental Health 812-838-1329
Highway Department1203 O’Donnell Road, Mount Vernon; (812) 838-1334; 7:00 a.m. to 3:30 p.m.
Surveyor300 Main Street, Room 113, Mount Vernon; (812) 838-1340

To tell which office covers an address, check whether the parcel lies inside the corporate limits of Mount Vernon, New Harmony, Poseyville or Griffin; everything else, including Cynthiana, goes to the county Building Commissioner.

Posey County permit types

The Building Commission has launched an online permitting service to make building permits more convenient to obtain, and the Area Plan Commission has its own portal for improvement location permits; applications can also be picked up at the office.

Residential permits

  • New homes. Single-family and two-family houses are charged by floor area with the mechanical trades billed separately; modular homes on a foundation and single-unit mobile homes have flat fees.
  • Accessory buildings. Detached garages, pole buildings and storage buildings are a flat fee by size band, with carports cheaper again.
  • Remodels and additions. Adding a room, enclosing a porch or building or replacing an attached garage is a flat fee; open porches and decks pay the minimum.
  • Exterior replacement. Siding, roofing, foundation, window and door work is permitted, with a lower fee for jobs up to $5,000.
  • Pools and spas. In-ground pools need fencing or a cover and include their mechanical work; above-ground pools over 3½ feet deep, spas and hot tubs have their own fee.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Buildings other than dwellings are charged on construction value, from warehouses, hangars and light industrial buildings to offices, shopping centers, restaurants, schools, hospitals, apartments and motels, with electrical, plumbing and heating permits added. Large projects that need full-time or part-time on-site inspectors can be set up as special projects with all costs in a site permit approved by the County Commissioners. Service stations pay per tank, and fire sprinkler and alarm work have their own fees.

What comes before the building permit

  • Improvement location permit. Issued by the Area Plan Commission for new structures and additions; work that does not change the building’s footprint usually does not need one. Bring a legal description (deed or tax statement) and a hand-drawn plot plan showing the new structure, existing buildings, any abutting road and the distances to the front, back and side lines.
  • Septic or sewer. Septic and sewer permits from the county come from the Health Department.
  • Special use, variance and rezoning. Filed with the Area Plan Commission by the second Thursday of a month to be heard the following month; the BZA meets at 5:00 p.m. and the Plan Commission at 6:00 p.m. on second Thursdays at the Hovey House, 330 Walnut Street, Mount Vernon.
  • Driveways and road work. County roads are maintained by the Highway Department; state highways are INDOT’s.
  • State release. Class 1 work needs the state Construction Design Release, which the county lists among application items.

Posey County permit costs and fees

The Building Commissioner posts Schedule A, the county’s building permit fee schedule; the posted copy is headed Ordinance 2010-081710 and carries a 2013 adoption line whose date is left blank. “Mechanics excluded” means electrical, plumbing and heating permits are charged on top.

Rather talk it over?

Call 1-855-478-4290 →
Posey County building permit fees (Schedule A, as posted)
WorkFee
Single-family dwelling (mechanics excluded)$0.08 per sq ft; minimum $150
Two-family or multi-family dwelling (mechanics excluded)$0.08 per sq ft; minimum $150, plus $25 per unit
Modular home with foundation / single mobile home / carport$120 / $90 / $40
Detached garage, pole or storage building$90 up to 2,999 sq ft; $100 at 3,000 sq ft and over
Remodel or addition / open porch or deck (minimum)$100 / $50
Siding, roofing, foundation, windows or doors$25 up to $5,000; $50 over $5,000
In-ground pool / above-ground pool over 3.5 ft, spa or hot tub$150 (mechanics included) / $50
Electrical, one- and two-family$30 up to 400 amps; $75 above 400 amps plus $10 per hundred amps
Plumbing / heating or air conditioning, one- and two-family$30 / $30 to $100 (gas meter, furnace, air conditioning)
Nonresidential buildings$6.00 per $1,000 of value; maximum $25,000, plus trades
Signs / moving a building / demolition$50 minimum / $100 minimum / $50 minimum residential (over 150 sq ft), $100 minimum commercial
Reinspection when work is not ready$25, doubled if unpaid after 30 days

The $150 house minimum covers any home up to 1,875 square feet (1,875 × $0.08 = $150); a larger house pays $0.08 for every square foot. Commercial electrical, plumbing and heating work above the residential rows is charged on cost with $100 minimums. Fees at the Area Plan Commission are separate: $125 for a special use, variance or rezoning (plus recording), $100 for a site development plan and $75 for a mobile home. The Health Department charges $75 for a new residential septic permit, $100 for an industrial one and $50 for a repair.

Trade permits and who may pull them

Electrical, plumbing and heating or air conditioning are permitted and inspected by the Building Commissioner’s Office in its area, each with its own fee. Rough plumbing must pass a pressure test (water lines at working pressure or 100 psi air, drain, waste and vent lines by water fill or 5 psi air) and gas lines are tested too, recorded on the county’s gas pressure test form. Electric meters are checked at the final inspection.

  • Plumbing. Plumbing contractors need the state plumbing license; the posted county pages and fee schedule set no separate county registration.
  • Electrical and HVAC. The county pages show no local license or registration for electricians or heating contractors, and each trade has its own fee line in Schedule A.
  • Fire protection. Sprinkler and alarm work on nonresidential buildings is permitted separately.

The reinspection bill goes to “the person who bought the permit”, so whoever pulls the permit carries responsibility for having each stage ready. Ask the office whether a homeowner may pull a permit for work on their own home before filing; the county pages do not address it.

Rather not deal with the Posey County building department?

Get a free quote →

How to apply for a Posey County building permit

1. Confirm the jurisdiction

Make sure the parcel is outside Mount Vernon, New Harmony, Poseyville and Griffin; Cynthiana and rural land are county.

2. Get the improvement location permit

Apply to the Area Plan Commission through its portal or at Room 132 with a legal description and plot plan.

3. Get the septic permit

On land without sewer, obtain the Health Department’s sewage permit before building.

4. Prepare plans

A site plan with lot lines, distances and existing structures, and one set of construction plans with cross-section details on 9x11 or 11x17 sheets.

5. Apply to the Building Commissioner

File through the county’s online permitting portal or at the office, with the state release if the building is Class 1.

6. Pay and schedule

Pay the Schedule A fee and book the first inspection.

Review, corrections and what causes delay

The office asks for applications to be filled out completely; incomplete forms, a missing improvement location permit or septic permit, and plans without cross-section details are what stall a permit. Zoning petitions run on a monthly cycle, so a variance or special use adds at least a month. Watch for zoning changes: the Area Plan Commission held hearings on September 24 and October 1, 2026 on Unified Development Ordinance amendments covering data centers, noise and transportation standards in the I-1 and I-2 industrial districts, Tier 3 solar, lot coverage and small contractor facilities, and revised data center and noise drafts were sent to the County Commissioners for their November 4, 2026 meeting.

⚠️ Pending zoning amendments. The UDO changes recommended in October 2026 go to the County Commissioners and the other participating jurisdictions for adoption; ask the Area Plan Commission which version is in force before designing an industrial, solar or data center project.

Inspections in Posey County

Call the Building Commissioner’s Office at 812-838-1324 at least 24 hours ahead, giving the site address, owner, work to be inspected and permit number. The county’s sequence for a house runs: soil and footings (the building official may require a soil evaluation; footings after forms and rebar), foundation walls before pouring or grouting (and before backfill, damp proofing and insulation on basements), underground electrical, underground plumbing, the concrete slab after under-slab work and compacted gravel, rough plumbing, rough electrical with grounded boxes, rough mechanical including ducts, fans, dryer and chimney, rough framing with fire stopping complete, insulation and caulking including the garage separation wall, and final.

The final inspection takes place after finish grading, when the building is complete and ready to occupy. A final inspection and certificate of occupancy are required before anyone moves in, for residential and commercial buildings alike.

Want this handled start to finish?

Get a free quote →

Indiana building code in Posey County

The Building Commissioner enforces the state’s plumbing, electrical, mechanical and structural codes for new and some existing construction in its area and handles the county’s adoption and amendment process for those codes. FEMA lists unincorporated Posey County as participating in the National Flood Insurance Program, with flood maps effective November 5, 2014; that listing covers only unincorporated land.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Posey County building permit FAQs

Does Posey County issue building permits in Mount Vernon?

No. The county office excludes Mount Vernon, New Harmony, Poseyville and Griffin; Mount Vernon’s permit page directs building permits to the Mayor’s Office at 520 Main Street.

How much is a building permit for a new house in Posey County?

$0.08 per square foot with a $150 minimum, with electrical ($30), plumbing ($30) and heating permits added separately.

Do I need an improvement location permit to remodel?

Not if the work does not change the building’s footprint, according to the Building Commissioner; additions and new structures need one from the Area Plan Commission.

Do I need a permit for a new roof or siding?

Yes. Siding, roofing, windows and doors are permitted at $25 for jobs up to $5,000 and $50 above that.

Where do I get a septic permit?

From the Posey County Health Department at 100 Vista Drive, Mount Vernon; a new residential sewage permit is $75.

Do farm buildings need a permit?

Yes, but agricultural buildings on farms of 50 acres or more, and churches, are exempt from the permit fee.

When do the Area Plan Commission and BZA meet?

On second Thursdays at the Hovey House, 330 Walnut Street, Mount Vernon: the BZA at 5:00 p.m. and the commission at 6:00 p.m.

Posey County permit search and official resources

Permit and inspection records for county permits are kept by the Building Commissioner’s Office, and improvement location permits by the Area Plan Commission; older records can be requested from the offices in Room 132. Section corner survey maps can be requested from the County Surveyor online.

Inspections are where schedules slip.

Get a free quote →

Simplify Posey County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Posey County sooner?