Orange County’s published permit rules for unincorporated land come from the Orange County Health Department, 205 E Main Street, Suite 9, Paoli ((812) 723-7112, weekdays 8 a.m. to 4 p.m.). Every septic system not connected to a regulated sewer needs its permit before construction, the permit for new construction costs $100, and under county Ordinance 2011-8 anyone requesting a new 911 address must show proof of a septic permit and verify that the site is outside the floodplain. Building and location permits come from the towns: Paoli and Orleans also plan some land outside their limits, and French Lick’s Zoning Department issues residential and commercial building permits.
What requires a permit in Orange County?
The county’s written requirements cover sewage and addressing, while the towns’ zoning ordinances cover buildings in and around them. The septic rule is broad: the Health Department says every residential and commercial sewage disposal system not connected to a regulated sewage facility must have a permit, and every repair and new installation must be inspected and signed off.
Orange County Health Department permit
- Constructing a new septic system
- Repairing, replacing or otherwise altering an existing system
- Commercial sewage systems not on a regulated sewer
- A new 911 address for a house, commercial building, mobile home or RV site: proof of a septic permit, or the sanitarian’s approval based on a pending septic approval
Town or state permit
- Any change to land or structures inside Paoli or its extra-territorial jurisdiction: an improvement location permit (ILP)
- Residential driveways joining a Paoli town street: an ILP
- Building in Orleans or its two-mile fringe: an ILP, which the Orleans ordinance treats as its building permit
- Homes and commercial buildings in French Lick: the town’s building permit
- Class 1 buildings anywhere: the state Construction Design Release
Paoli’s list of small projects
Paoli’s development ordinance spells out which small jobs need an ILP. Accessory buildings need an ILP and may not go up before the main building, unless they serve agriculture. Garages, carports, sheds, gazebos and other structures over 50 square feet need an ILP too, as do swimming pools, which need a 5-foot fence around the pool area or a mechanical cover and may not sit in the front yard (wading pools excepted). Fences, walls and hedges up to 6 feet tall in side or rear yards need an ILP; in the single-family district one in the required front yard may not exceed 3 feet. No ILP is needed for swing sets, children’s tree houses, mailboxes, lamp posts, walks, retaining walls, drainage installations, parking spaces or non-commercial pet housing. A manufactured home lived in while the owner builds a permanent house needs a one-year ILP, renewable for one more year if the house is started but unfinished.
Short on time to read all of this?
Get a free quote →What Orange County decides and what the state holds
The county decides its sewage disposal ordinance (Ordinance 2024-3), its addressing rule (Ordinance 2011-8) and who may install septic systems, and its Commissioners appoint the two fringe-area members of the Orleans Plan Commission. The towns decide their own zoning, permits and fees. Indiana writes the septic rule the county applies (410 IAC 6-8.3), the building codes, and the design release for Class 1 structures, and it reviews septic plans for commercial facilities and licenses plumbers.
Orange County building department: who handles permitting
For land outside the towns and their planning areas, the Health Department’s sanitarian handles septic permits and inspections, and the county’s 911 address request goes through the same office before an address is assigned. The Health Department is closed on the listed holidays and on Election Days. Near Paoli and Orleans, the town’s planning jurisdiction can reach past the town line, so check the Jurisdictional Area map that Paoli keeps on file at its Plan Commission office and at the Orange County Recorder’s Office.
| Place | Who handles permits |
|---|---|
| Unincorporated county | Health Department septic permit and address approval, (812) 723-7112; no county building or zoning office appears in the county’s published rules |
| Paoli and its extra-territorial jurisdiction | Paoli Zoning Administrator, 812-791-8610, issues ILPs under the Paoli Unified Development Ordinance |
| French Lick | Zoning Department, French Lick Town Hall, 7949 W Hunters Run Drive, (812) 325-0480, weekdays 8 a.m. to 4:30 p.m. |
| Orleans and its two-mile fringe | The town’s Administrator issues ILPs under the Orleans zoning ordinance; the Advisory Plan Commission includes two fringe residents |
| West Baden Springs | The published sources do not say; ask the town office |
Orange County permit types
The Health Department bundles everything for a septic system into its Septic Packet: the steps to a permit, a list of ARCPACS-certified soil science consultants, a list of permitted installers, the onsite sewage system permit application and the 911 address request.
Residential permits
- New home on a septic system. Soil test, septic permit application, installer plan, then the permit, which also supports the 911 address request.
- Septic repair or replacement. Needs a permit before work starts, as any alteration does.
- Mobile homes and RVs. The address form has boxes for a mobile home or trailer and for an RV or camper, the latter with an RV/Camper Affidavit.
- In Paoli. An ILP from the Zoning Administrator for any alteration to land or structures, including a residential driveway onto a town street. Mobile homes may be lived in permanently only in a mobile home park, where each placement needs an ILP and the home must be skirted before anyone moves in.
- In French Lick. The Residential Building Permit form, completed, scanned and emailed to the Zoning Department. It covers a new single-family home, duplex, addition or accessory building, asks for the size, height and setbacks, the construction cost and whether the water and sewer departments have been contacted, and the commercial form notes that an approved application expires after 90 days. The forms carry the Planning Department’s own number, 812-936-4737.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
A commercial building open to the public or used by employees is a Class 1 structure, so the owner applies to the Indiana Department of Homeland Security (IDHS) for a Construction Design Release before construction. Its sewage system, if not on a regulated sewer, still needs an Orange County permit, and the Indiana Department of Health’s onsite program reviews plans for systems serving commercial facilities. French Lick has a separate Commercial Building Permit form, and Paoli’s ordinance requires an Indiana-registered engineer’s certificate of compliance with its performance standards for light or general industrial uses.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Soil test and septic permit. The county permit is issued to the installer after a site visit and plan review.
- Floodplain check. The address form asks whether the structure is outside a FEMA flood zone. FEMA lists unincorporated Orange County as participating in the flood insurance program, with maps effective May 19, 2014; a floodway also needs the state Construction in a Floodway permit.
- Driveways on state roads. INDOT’s Electronic Permit System handles entrances onto state highways.
- Town zoning. Variances and special exceptions go to the town’s Board of Zoning Appeals before a permit issues.
Orange County permit fees
The county fees in print are the Health Department’s. Town permit fees are set by each town: Paoli’s development ordinance refers its ILP filing fee to a separate town fee schedule whose amounts are not in the ordinance text, and French Lick prints a $25 fee on each of its building permit application forms and collects it once the permit is approved.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee | Source |
|---|---|---|
| Septic permit, new construction | $100, good for one year after plan submission | Health Department FAQ and steps sheet |
| Homeowner septic installation exam | $20 | Health Department steps sheet |
| Paoli ILP | Filing fee on the town fee schedule (First Amended Fee Schedule, Resolution 2016-03) | Paoli Unified Development Ordinance |
| French Lick residential building permit application | $25, by check or cash, collected after approval | French Lick Residential Building Permit Application |
| French Lick commercial building permit application | $25, by check or cash, collected after approval | French Lick Commercial Building Permit Application |
| INDOT private driveway / minor commercial / major commercial | $55 / $150 / $600 | INDOT permits page |
| State design release (Class 1) | $75 filing fee plus a processing fee, generally $0.050 per gross sq ft | 675 IAC 12-3-2 |
The $100 septic fee buys a permit that stays valid for one year from the date the plan is submitted, so time the soil work and installation to finish inside that year.
Trade permits and who may pull them
The Health Department’s rules decide who may build a septic system, and the plan it reviews must be prepared and submitted by the installing contractor.
- Septic installers. Use an installer certified by the Orange County Health Department; the department keeps the list in its Septic Packet.
- Owners installing their own system. An owner may pass the department’s homeowner installation exam ($20) and take responsibility for the construction plan and installation.
- Soil scientists. The soil test comes from a consultant on the department’s ARCPACS-certified list.
- Plumbing. Plumbing contractors and journeyman plumbers hold state licenses from the Indiana Plumbing Commission.
- Electrical, HVAC and general contractors. The state licenses none of them, and the Health Department sets no rule for them, so ask the town office whether it registers contractors before working inside a town.
How to get a septic permit and building approval in Orange County
Inside or near Paoli, Orleans or French Lick, start with that town; on other rural land, start with the Health Department.
Hire a soil scientist from the Health Department’s list; do not move soil or add fill on the test site afterward.
File the onsite sewage system permit application and the $100 fee.
Pick a county-certified installer, or pass the $20 homeowner exam, and have the installer get the system requirements from the department.
The installer stakes the layout, submits a plan with the material checklist and trench detail, and the department visits before issuing or denying the permit.
With the septic permit in hand, file the 911 address request and any town ILP or building permit.
For a commercial building, wait for the IDHS design release before construction.
Rather not deal with the Orange County building department?
Get a free quote →Review, corrections and what causes delay
The system requirements are tied to the soil report. If anyone removes or adds soil or does other earth moving on the evaluated area after the test, those requirements no longer apply and a new soil analysis is required, and the absorption area may not be moved without one. Construction also waits on soil moisture: the installer checks it with a plasticity test at trench depth. In Paoli, an ILP for a use needing a special exception cannot issue until the zoning appeals board approves it.
Inspections in Orange County
Every new septic system and repair is inspected and signed off by the Health Department’s inspector. The installer must call the department 48 hours before final cover; where that is not possible, the department has policies for photo documentation before cover. The department then meets the installer on site for the final inspection, which completes the process.
In Paoli, no building may be occupied until the Zoning Administrator issues a certificate of occupancy, due within five days after the work under the ILP is complete, provided reinspection fees and fines are paid. A Paoli ILP lapses if construction is not finished within 24 months, and the Administrator may grant one 12-month extension on a written request.
Indiana building code in Orange County
The county applies the state’s residential septic rule, 410 IAC 6-8.3, together with its own Sewage Disposal Ordinance 2024-3. Indiana’s building rules reach Orange County projects through the state design release on Class 1 work and through the towns’ permits.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Orange County permit records and official resources
To find an older septic system, use the county’s Elevate property app: realtors and buyers can log in free as a guest and search by address or parcel number for soil and septic permit data, or ask the sanitarian. Environmental complaints must be filed in writing at the Health Department office, not by phone.
Want this handled start to finish?
Get a free quote →- Orange County Health Department contact and hours
- Orange County Health Department sanitation
- Orange County septic packet
- Steps to a septic permit (PDF)
- Orange County 911 address request (Ordinance 2011-8)
- Septic permit FAQs
- Locating an existing septic system
- Town of Paoli zoning
- Paoli Unified Development Ordinance
- French Lick Zoning Department and permit forms
- Orleans codebook (Indiana 15 Regional Planning Commission)
- Indiana Department of Health onsite sewage program
- IDNR Division of Water permit programs
- INDOT permits
- IDHS building plan review process
- IDHS: Fire Prevention and Building Safety Commission rules
- Indiana Plumbing Commission
- FEMA Community Status Book, Indiana
Inspections are where schedules slip.
Get a free quote →Orange County building permit FAQs
Does Orange County issue building permits?
The county’s published permits are septic permits and the 911 address that depends on them. Paoli, Orleans and French Lick issue their own permits, and Paoli and Orleans also plan some land outside their limits.
How much is a septic permit in Orange County?
$100 for new construction, valid for one year after the plan is submitted.
Can I install my own septic system?
Yes, if you pass the Health Department’s $20 homeowner installation exam and take responsibility for the plan and the installation.
Why does the 911 address request ask about septic?
County Ordinance 2011-8 requires an applicant for a new address to provide proof of a septic permit and to verify that the site is outside the floodplain; the form also lets the sanitarian approve a new address on the strength of a pending septic approval.
Is my septic system legal?
Not if it lacks a septic tank and absorption field, drains to a field tile, ditch or creek, or uses an aeration unit or sand filter with no leach field, according to the department.
What counts as a failing septic system?
The department treats a system as failing when it will not take sewage at its design rate (gurgling toilets, backed-up or slow drains), when effluent ponds or seeps to the ground surface or into surface water, or when effluent contaminates a water source. Repairing or replacing it needs a permit first.
How long does a Paoli ILP last?
The work must be completed within 24 months, with one 12-month extension available on written request to the Zoning Administrator.
How do I reach the Health Department?
205 E Main Street, Suite 9, Paoli; (812) 723-7112; weekdays 8 a.m. to 4 p.m., closed on Election Days and listed holidays.
Simplify Orange County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Orange County sooner?
Let Alliance prepare, file, and track your Orange County permits while your crew stays on the job.
More Indiana permitting guides
Crawford County
Read guide →Lawrence County
Read guide →Washington County
Read guide →Owen County Building Permit Guide
Read guide →Parke County Building Permit Guide
Read guide →Perry County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Orange County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.