Montgomery County, Illinois Building Permit Guide

To get a building permit in Montgomery County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Montgomery County issues no building permits; before building, owners file a Structural Improvement Permit notice with the Supervisor of Assessments in Hillsboro, and septic and well permits come from the county Health Department.

Authority: Montgomery County Supervisor of Assessments (construction notice)Building permits: Issued by cities and villages onlyPhone: 217-532-9595
County building permit
NoneStructural Improvement Permit notice instead
Late notice
Up to $500 a dayFine for building without notice
Septic and wells
Health DepartmentHillsboro, 217-532-2001
Solar farm fee
$5,000 per MWCapped at $125,000

The county says it plainly: Montgomery County does not issue building permits. What it requires is a Structural Improvement Permit, a notice of building construction filed with the Supervisor of Assessments at 1 Courthouse Square, Room 201, Hillsboro (217-532-9595), before any house, garage, barn, shed or commercial building goes up; it is used for assessment and new 911 addresses, and building without it can bring a fine of up to $500 a day. New septic systems and wells need permits from the Montgomery County Health Department, solar farms need a County Board permit, and the cities and villages set their own building rules.

What requires a county permit or notice in Montgomery County?

Montgomery County’s permit picture is short, and each item comes from a different county office:

County filing needed

  • Any building construction or improvement, including houses, garages, barns, sheds, storage units and commercial buildings: Structural Improvement Permit notice
  • New and renovated private sewage disposal systems: Health Department permit
  • Drilling a new water well or sealing an abandoned well: Health Department permit
  • Solar farms and solar gardens in unincorporated areas: County Board development permit
  • Land divisions under the county Subdivision Ordinance and the Plat Act

Not issued by the county

  • Building permits (the county does not issue them)
  • County electrical, plumbing or mechanical permits
  • Plan review or building inspections for houses

The Structural Improvement Permit form words its scope this way: “All persons shall be required to provide notice of building construction/improvements to real property in Montgomery County,” a term that includes but is not limited to houses, garages, barns, sheds, storage units of any kind and commercial buildings. It says failing to file the notification before construction is an offense punishable by a fine of up to $500 for each day work proceeds, with each day after the structure is finished counted as a separate offense. Its acknowledgement adds that all other city, township, subdivision and state ordinances must still be followed.

What Montgomery County decides and what the state holds

The County Board sets the notice requirement, the subdivision, solar and wind ordinances and the Health Department’s private sewage disposal ordinance. Septic systems are permitted under the Illinois Department of Public Health’s private sewage disposal program together with the county ordinance, and new wells and well sealing are permitted and inspected by the Health Department. Plumbers are licensed by the Illinois Department of Public Health and roofing contractors by the state.

Short on time to read all of this?

Get a free quote →

Montgomery County building department: who handles permitting

The Supervisor of Assessments takes Structural Improvement Permit notices, assigns a notification number and, for new structures, starts the new 911 address. The Health Department’s Environmental Health staff permit, evaluate, approve and inspect septic systems and permit wells. The County Board issues solar farm and garden permits after a public hearing, with the County Coordinator’s office answering questions. The GIS office, whose technician is also the county’s Plat Act officer, keeps the parcel map; use it to see whether a property lies inside a city or village.

Montgomery County permit contacts
OfficeContact
Supervisor of Assessments (Structural Improvement Permit)1 Courthouse Square, Room 201, Hillsboro, IL 62049; 217-532-9595; assessor@montgomerycountyil.gov
Health Department, Environmental Health (septic, wells)11191 Illinois Route 185, Hillsboro, IL 62049; 217-532-2001; satellite office 1357 E. Union Ave., Litchfield, 217-324-3430
County Engineer / Highway Department11159 IL Route 185, Hillsboro; 217-532-6109; engineer@montgomerycountyil.gov
GIS office and Plat Act officer#1 Old Courthouse Square, Room 305, Hillsboro; 217-532-9580
County Coordinator (solar and wind questions)217-532-9577
Building permits in Montgomery County’s municipalities
MunicipalityWhere to ask about building permits
Litchfield (city, pop. 6,598), Hillsboro (city, 6,184), Nokomis (city, 2,133)City hall; the county issues no building permits there
Witt (770), Coffeen (627) (cities)City hall; the county issues no building permits there
Raymond, Taylor Springs, Farmersville, Schram City, Irving, Coalton, Fillmore, Waggoner, Butler, Ohlman, Walshville, Wenonah (villages)The village clerk; the county issues no building permits there
Panama (205 here, 120 in Bond County), Donnellson (145 here, 7 in Bond County), Harvel (117 here, 54 in Christian County)The village clerk; the county issues no building permits there
Unincorporated landNo building permit; Structural Improvement Permit notice plus Health Department septic and well permits

Montgomery County permit types

Not sure this scope needs a permit?

Get a free quote →

Residential permits

  • Structural Improvement Permit (notice). A one-page form: tick either “improvement to an existing structure only” or “new structure that will require a new 911 address”, mark whether a septic permit is needed, give the property number, owner, type of construction (commercial, home, outbuilding or other), estimated start date and cost estimate, list the structure details (size, bathrooms, basement, central air, garage, porches), name the road for a new address, and attach a photo of where the driveway will be. The form can be mailed, e-mailed or completed by phone.
  • Private sewage disposal permit. Issued to the owner and the licensed septic installer before construction of any new or renovated system; installers register with the Health Department on its private sewage contractor registration form.
  • Well permits. Required for drilling a new water well and for sealing an abandoned one; staff visit the site to inspect.

Commercial permits

Commercial buildings file the same Structural Improvement Permit notice. Solar farms and solar gardens in unincorporated areas need a development permit from the County Board under the solar ordinance adopted April 10, 2018 and last revised March 10, 2026; ground-mounted developments covering more than 5 acres count as solar farms. The ordinance requires a detailed site plan, UL-listed components and an interconnection agreement with the utility, limits arrays to 30 feet in height, and sets farm setbacks of 50 feet from property lines and public road rights-of-way and 150 feet from homes (neighbors may sign a waiver). The ordinance covers unincorporated areas other than those around municipal limits governed by municipal ordinance. Food businesses need a Health Department food permit.

What comes before the building

  • Address and driveway. New structures get a new 911 address through the notice, which asks for the road name and a driveway photo.
  • Septic site. Tick the septic box on the notice and apply to the Health Department before construction.
  • Plats. Land divisions follow the county Subdivision Ordinance, with the GIS technician acting as Plat Act officer.
  • Flood maps. FEMA lists unincorporated Montgomery County in the flood insurance program on an emergency-program basis with a 1981 flood hazard boundary map.

Rather talk it over?

Call 1-855-478-4290 →

Montgomery County permit fees

The Structural Improvement Permit form and its instructions show no filing fee, and the Health Department’s posted septic application shows none either; ask Environmental Health for current septic and well permit charges. The fees the county does publish are in its solar ordinance:

Montgomery County published fees and penalties
ItemFee
Structural Improvement Permit noticeNo fee shown on the form
Building without filing the noticeFine up to $500 per day
Solar farm or garden application$5,000 per MW of nameplate capacity, up to $125,000, non-refundable
County costs above the solar application feeBilled to the applicant, due within 15 days
Solar permit extension (up to two years)$250 per MW
Solar development without approval$1,000 first violation, $500 per additional month
Water test for a new wellNo lab fee

Worked example. A 4 MW solar garden pays 4 × $5,000 = $20,000 when it applies; a 30 MW solar farm would reach the $125,000 cap (30 × $5,000 = $150,000, capped). A permit that has not started construction within five years lapses unless the County Board grants an extension, which for the 4 MW project costs 4 × $250 = $1,000.

Trade permits and who may pull them

Montgomery County runs no electrical, plumbing or mechanical permit program and lists no county contractor registration for builders. The one county trade rule on its pages is for septic work: the private sewage disposal permit is issued to both the owner and a licensed septic installer, and installers file a private sewage contractor registration application with the Health Department. Plumbing in Illinois follows the state plumbing code and is done by plumbers licensed through the Illinois Department of Public Health, and roofing contractors need a state license. Litchfield, Hillsboro and the other municipalities set their own electrical and contractor rules; ask city hall.

Rather not deal with the Montgomery County building department?

Get a free quote →

How to file in Montgomery County

1. Check whether the parcel is in a town

Use the county GIS map; city and village parcels follow that municipality’s permit rules.

2. Plan septic and well

For a rural site, apply to the Health Department before construction; the septic permit goes to the owner and a licensed installer.

3. Complete the Structural Improvement Permit

Fill in the form, tick the septic box if needed, and attach a driveway photo for a new address.

4. Send it before you build

Return it to the Supervisor of Assessments by mail, e-mail or in person, or complete it by phone.

5. Keep the notification number

The office assigns it once the notice is processed.

6. Follow every other rule

City, township, subdivision and state ordinances still apply.

Review, corrections and what causes delay

There is no plan review for the notice itself, but the septic permit must be issued before the system is built, and Environmental Health staff evaluate and approve each system. Solar projects take longest: the County Board must hold a public hearing within 60 days, after notice published in a newspaper at least once a week for two weeks and mailed by the applicant to affected owners, and must decide within 30 days of the hearing. Unpaid application fees stop any decision.

Inspections in Montgomery County

With no county building permit, the county’s pages describe no building-code inspections of houses or other buildings. Its inspections are environmental: Health Department personnel evaluate, approve and inspect private sewage disposal systems, and they visit well drilling and well sealing sites. Free water test kits are available for private wells, with no lab fee when a new well is tested, when an infant lives in the home or for medical reasons. For solar developments, the County Board may require a final site inspection before the facility may operate, and an emergency contact must be posted at the access point. Inside the cities and villages, inspections follow the municipality’s own program.

Building codes and flood maps in Montgomery County

Because the county issues no building permits, its pages show no county building-code review for unincorporated areas; its posted ordinances cover subdivisions, solar, wind, fireworks, animal control and responsible bidding. Each city and village decides its own codes. FEMA’s Community Status Book lists Montgomery County (community 170992, unincorporated areas) as a participating community that joined on February 3, 2000 under the emergency program, with a flood hazard boundary map dated January 9, 1981 and no flood insurance rate map listed.

Want this handled start to finish?

Get a free quote →

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Montgomery County permit FAQs

Does Montgomery County issue building permits?

No. The county says it does not issue building permits; it requires a Structural Improvement Permit notice for assessment purposes.

Is there a fee for the Structural Improvement Permit?

No fee is shown on the form, but building without filing it can bring a fine of up to $500 a day.

How do I get a new 911 address?

Tick “new structure” on the Structural Improvement Permit, name the road and attach a photo of the driveway location.

Who issues septic permits?

The Montgomery County Health Department in Hillsboro (217-532-2001), to the owner and a licensed septic installer, before construction.

Do I need a permit to drill or seal a well?

Yes. The Health Department issues permits for new wells and for sealing abandoned wells and inspects the sites.

How much is a solar farm permit?

$5,000 per megawatt of nameplate capacity, up to $125,000, paid by certified check before the application is processed.

What about building in Litchfield or Hillsboro?

Not the county, which issues no building permits anywhere; ask the city hall about its own rules. The county’s notice form applies to “building construction/improvements to real property in Montgomery County” and names no exception for cities or villages, so ask the Supervisor of Assessments whether you must also file it.

Montgomery County permit records and official resources

Structural Improvement Permit notices are held by the Supervisor of Assessments, septic and well records by the Health Department, and plats by the GIS office. For other records, the county’s Freedom of Information Officer can be reached at 217-532-9551, and County Board agendas and minutes are posted online.

Inspections are where schedules slip.

Get a free quote →

Simplify Montgomery County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Montgomery County sooner?

Let Alliance prepare, file, and track your Montgomery County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Montgomery County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.