Macoupin County, Illinois Building Permit Guide

To get a building permit in Macoupin County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Macoupin County has no zoning in its unincorporated areas; its only building permit there is a $100 Building Program Permit for new construction that needs a septic system, filed with the county GIS Manager in Carlinville.

Authority: Macoupin County GIS Manager / Plat OfficerServes: Unincorporated county onlyPhone: 217-854-8281 ext. 5050
County permit
$100New construction needing a septic system
County zoning
NoneUnincorporated areas
Septic permit
$300Macoupin County Public Health
Late permit fine
$500–$1,000If not obtained 30 days before building

Macoupin County does not zone its unincorporated land, and its pages list no county building code there. What it does require is a $100 Building Program Permit for any new construction in the unincorporated county that needs a septic system, filed by the property owner with the county GIS Manager and Plat Officer at 201 E. Main Street, Carlinville; the septic or well permit then comes from the Macoupin County Public Health Department. Inside the county’s 27 cities, villages and towns, each municipality sets its own building and zoning rules.

What requires a permit in unincorporated Macoupin County?

The county’s permit hub is explicit about how little it regulates outside city and village limits. Unincorporated Macoupin County has no zoning, so there are no county setbacks, use districts or zoning certificates to obtain. The one county building permit, the Building Program Permit, applies to new construction that requires a septic system; the county’s pages describe no plan review or building inspections under it. Separate county-wide permits cover private septic systems and water wells, and a wind energy siting permit is required for any wind energy conversion system anywhere in the county.

County permit needed

  • New construction needing a septic system: Building Program Permit ($100)
  • Septic systems and repairs: Public Health permit (county-wide unless public sewer is available)
  • New, modified or sealed water wells and geothermal wells: Public Health permit (county-wide)
  • Wind energy conversion systems: County Board siting permit (county-wide)
  • A 911 address before any building permit

No county permit or rules

  • Zoning in unincorporated areas (none)
  • Solar arrays in unincorporated areas (no county solar permit or regulations)

The permit application warns that not obtaining a Building Program Permit 30 days or more before construction may expose the property owner to fines of $500 to $1,000. Land divisions must still follow the Macoupin County Subdivision Ordinance and the Illinois Plat Act.

What Macoupin County decides and what the state holds

The county has no zoning for unincorporated land and no county solar regulations there, and wind siting permits go to the County Board. Private sewage and water wells are handled by the county Public Health Department under the Macoupin County Private Sewage Disposal Ordinance and the state Private Sewage Disposal Code (77 Ill. Adm. Code 905) and well construction code. Within cities and villages, the municipality decides whether to adopt zoning and a building code.

Short on time to read all of this?

Get a free quote →

Macoupin County building department: who handles permitting

For unincorporated land, three county offices matter. The GIS Manager and Plat Officer takes Building Program Permit applications. The Macoupin County Public Health Department’s Environmental Health division issues septic, well and geothermal permits and inspects wells. The County Board, through the County Clerk, handles wind energy siting permits. To tell whether an address is unincorporated, check with the GIS Manager or the Supervisor of Assessments, whose office keeps maps of every property in the county; if the parcel is inside a city or village limit, the county page sends you to that municipality.

Building and zoning in Macoupin County’s municipalities
MunicipalityWho handles building and zoning
Carlinville (city, pop. 5,465)City Zoning Administrator, City Hall, 550 N. Broad Street: temporary zoning permits valid one year, then a permanent zoning certificate
Staunton (4,932), Gillespie (3,083), Virden (part, 3,006), Mount Olive (1,936), Girard (1,768), Bunker Hill (1,593), Benld (1,403)Contact the city; the county’s permits page sends city parcels to the city
Brighton (village, part; 1,864 in Macoupin), Medora (village, part; 361)Contact the village; both villages also lie partly in Jersey County
Palmyra, Wilsonville, Mount Clare, Sawyerville, East Gillespie, White City, Lake Ka-Ho, Modesto, Royal Lakes, Chesterfield, Hettick, Standard City, Dorchester, Eagarville, Scottville (villages)Contact the village clerk
Shipman (town, 504), Nilwood (town, 198)Contact the town clerk
Unincorporated landMacoupin County: Building Program Permit (septic sites), Public Health septic and well permits; no zoning
Macoupin County permit contacts
OfficeContact
GIS Manager / Plat Officer (Building Program Permit)201 E. Main Street, P.O. Box 107, Carlinville, IL 62626; 217-854-8281 ext. 5050 (the permits page shows 217-854-3181 ext. 5050)
Public Health, Environmental Health (septic, wells)509 Illinois Avenue, Gillespie; 217-839-4111
Supervisor of Assessments (parcel maps, PTAX-760)201 East Main, P.O. Box 15, Carlinville, IL 62626; 217-854-8281
County Clerk (wind siting, board records)217-854-3214 ext. 918
Highway Department21480 IL Route 4, Carlinville; 217-854-6416; weekdays 8 a.m. to 4 p.m.
County office hoursMonday to Friday, 8:30 a.m. to 4:30 p.m.

Not sure this scope needs a permit?

Get a free quote →

Macoupin County permit types

The county’s permit hub lists every county permit and license in one place, and says which apply only to unincorporated land and which apply county-wide.

Residential permits

  • Building Program Permit. A one-page application, made by the property owner, with owner and applicant details, the type of construction, the property address and the parcel number. The parcel must already have a current 911 address. The owner then delivers a copy of the permit to the Public Health Department to obtain the septic and well permits.
  • Private septic system. A Public Health construction permit ($300) for new, repaired or replaced systems, required county-wide unless public sewer is available; the owner hires a licensed septic contractor and a licensed soil scientist, and the contractor usually files the application.
  • Water wells. A Public Health permit ($100) for a new water well and before sealing an abandoned well ($100); closed-loop geothermal wells cost $250. Licensed well drillers or pump contractors usually file for the owner.

Commercial permits

The county runs no commercial building permit or plan review in unincorporated areas; its pages list no county building code. Food businesses need a Public Health food permit ($75 to $110 by risk level), and wind energy projects go through the county siting process, with a $125,000 plan review deposit, a $5,000 consideration fee and $500 per megawatt on approval. Solar farms in unincorporated areas face no county solar permit; questions about how they are taxed go to the Supervisor of Assessments.

What comes before the building permit

  • 911 address. No Building Program Permit can be granted until the property has a current 911 address.
  • Soil evaluation. A licensed soil scientist assesses the site so the septic contractor can choose the right system.
  • Plats. Dividing land must comply with the Macoupin County Subdivision Ordinance and the Illinois Plat Act.
  • Roads. The Highway Department looks after 222 miles of county highways and 41 bridges and assists the 26 township highway commissioners, who maintain 1,080 miles of township roads; ask the Highway Department about work that touches a county highway.
  • Floodplain. The county’s permit hub lists no county floodplain permit.

Rather talk it over?

Call 1-855-478-4290 →

Macoupin County permit costs and fees

Fees are those printed on the county’s Licenses, Permits & Zoning Information page and on the Building Program Permit application.

Macoupin County permit fees
ItemFee
Building Program Permit (new construction needing septic, unincorporated)$100, payable to the County of Macoupin
Private septic system permit$300
Septic contractor license$75
Private water well permit / well sealing$100 / $100
Geothermal (closed-loop) well$250
Wind energy siting permit$125,000 plan review deposit, $5,000 consideration fee, $500 per megawatt on approval
No permit 30 or more days before constructionPossible fine of $500 to $1,000

Worked example from the posted fees: a new house on an unincorporated rural lot with a septic system and a new water well pays $100 for the Building Program Permit, $300 for the septic permit and $100 for the well permit, or $500 in county permit fees before contractor charges. If the owner installs the septic system personally, the county says a homeowner must also obtain a license for the installation.

Trade permits and who may pull them

Macoupin County issues no electrical, mechanical or general building trade permits for unincorporated land and its pages describe no county contractor registration. The trade rules it does run are in public health:

  • Septic installers: every contractor working in Macoupin County, including contractors from surrounding counties, needs a private sewage contractor license from the Public Health Department ($75), and homeowners must also obtain a license for any septic installation or repair they do themselves.
  • Well contractors: new or replaced wells are drilled by a licensed well driller, and work on existing wells is done by a licensed well-pump contractor; a homeowner may seal their own abandoned well after a written request describing the method and materials, with 48 hours’ notice to the Health Department.
  • Soil scientists: a licensed soil scientist evaluates the site for any new, repaired or replaced septic system.

Rather not deal with the Macoupin County building department?

Get a free quote →

Plumbing and roofing licenses are state matters: plumbers are licensed by the Illinois Department of Public Health and roofing contractors by the Illinois Department of Financial and Professional Regulation. Inside the cities and villages, local rules on electricians and contractors come from each municipality.

How to apply for a Macoupin County Building Program Permit

1. Confirm the parcel is unincorporated

Check with the GIS Manager or Supervisor of Assessments; city and village parcels follow local rules.

2. Get a 911 address

The permit cannot be granted without a current 911 address for the property.

3. File the application

The property owner completes the Building Program Permit application with the parcel number and pays $100 to the County of Macoupin.

4. Take it to Public Health

Deliver a copy of the permit to the Health Department to obtain the septic and well permits.

5. Hire licensed contractors

A licensed soil scientist, septic contractor and well driller prepare and file their parts.

6. Report the improvement

Within 30 days of completion, send form PTAX-760 to the Supervisor of Assessments.

Review, corrections and what causes delay

Apply at least 30 days before construction, because the application warns of fines when the permit is not obtained by then. The Health Department aims to approve a well permit within 7 to 10 business days once the contractor submits it. A permit cannot be granted without a current 911 address, and the form says the permit must be obtained by the property owner.

Inspections and certificates in Macoupin County

The county’s pages describe no building inspections or certificates of occupancy for unincorporated areas. The inspections that do happen are environmental: Environmental Health staff inspect wells while they are being built and again when the pump is installed, collect water samples, and the department issues septic permits under the county private sewage ordinance. Abandoned wells must be sealed within 30 days of abandonment, and a completed sealing form goes to the Health Department after the work. If an abandoned well is found to contaminate someone else’s drinking water supply, its owner must provide that owner with a safe and sufficient supply of water. For a new home on a private well, the department sells well-water test kits at its Gillespie office, and the Illinois Department of Public Health suggests testing drinking water from a well every year.

The one form that follows completion is PTAX-760, the reassessment request for new construction: the owner sends it by certified mail, return receipt requested, to the Supervisor of Assessments within 30 days of finishing the improvement, so the improvement can be reassessed. Inside cities and villages, inspections and occupancy certificates are whatever that municipality requires.

Want this handled start to finish?

Get a free quote →

Illinois building code in Macoupin County

The county’s permit pages list no county-adopted building code for unincorporated areas, and the Building Program Permit is tied to septic sites rather than to code review. FEMA’s Community Status Book lists Macoupin County (community 170930, unincorporated areas) among participating communities, entered under the emergency program on September 18, 1996, with a flood hazard boundary map dated January 6, 1978.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Macoupin County building permit FAQs

Does Macoupin County have zoning?

Not in unincorporated areas; the county says they have no zoning. Cities and villages set their own zoning.

Do I need a county building permit to build a house in the country?

Yes if the new construction needs a septic system: a $100 Building Program Permit from the GIS Manager, followed by Public Health septic and well permits.

Who issues septic permits?

The Macoupin County Public Health Department; a private septic permit costs $300 and the installer needs a $75 county septic contractor license.

Do I need a well permit?

Yes, county-wide: $100 for a new well or for sealing an old one, and $250 for a closed-loop geothermal well.

Are solar farms regulated by the county?

Not in unincorporated areas; the county has no solar permit or regulations there. Wind projects do need a county siting permit.

How do I know if my property is inside a city or village?

Ask the GIS Manager or the Supervisor of Assessments, who keeps maps of every property; city and village parcels go to that municipality.

Does the county issue permits in Carlinville?

No. Carlinville issues its own zoning permits through its Zoning Administrator at City Hall, 550 N. Broad Street.

Inspections are where schedules slip.

Get a free quote →

Macoupin County permit records and official resources

Building Program Permit records are kept by the GIS Manager and Plat Officer, septic and well permits by the Public Health Department, and property and improvement records by the Supervisor of Assessments. County Board minutes, resolutions, ordinances and agenda packets are published on the County Clerk’s board-records site, and the county posts a Freedom of Information Act guide for other records.

Simplify Macoupin County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Macoupin County sooner?

Let Alliance prepare, file, and track your Macoupin County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Macoupin County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.