Outside the cities and villages that have their own zoning ordinances, Mason County requires a building permit from the Zoning Office before construction starts on any parcel. The office is in the County Courthouse, 125 N. Plum Street, Havana (309-543-3759, option 9). Routine repairs, re-roofing, alterations costing under $1,000 and utility service connections need no permit. Lots without public sewer or water need a plan certified by the Mason County Health Department, whose septic permit costs $100. The County Board sets the zoning fees, which are paid to the County Clerk.
What requires a permit in Mason County?
Section 9.1 of the county zoning ordinance (adopted June 10, 1975, revised 2008) requires a building permit before any construction begins on a parcel within the county’s zoning jurisdiction, apart from three listed exemptions.
Permit needed
- New houses and other new buildings
- Additions, structural alterations and relocated buildings
- Alterations costing $1,000 or more
- Accessory buildings
- Fences, except farm fences, ornamental features and fences under 100 lineal feet
- Repairs to a substantially flood-damaged building in the floodplain
- Temporary dwellings and mobile home parking, by temporary permit
No permit
- Routine maintenance or repair, such as re-roofing
- Alterations to existing buildings costing less than $1,000
- A service connection to a municipally owned and operated utility
- Agricultural fences, and ornamental posts, lattices, arbors and trellises
Some uses need a special use permit from the Zoning Board of Appeals before any building permit, including all development within 500 feet of a freeway, expressway or interstate right-of-way and within 1,500 feet of an interchange, and energy storage systems. Commercial solar and wind facilities follow their own 2026 ordinances.
What the county decides and what the state holds
The County Board adopts the zoning, floodplain and energy facility ordinances and sets fees by board action; the Zoning Office enforces them and the Zoning Board of Appeals hears variances, special uses and appeals. The county posts no building code of its own, so its permit is a zoning and land-use review. The Health Department applies the state private sewage and well rules, and plumbers and roofing contractors hold state licenses.
Mason County building department: who handles permitting
The Zoning Office, run by the county’s Code Enforcement Officer, issues building permits and handles zoning, floodplain and energy facility applications. Other county permits come from the Highway Department and the Health Department.
Short on time to read all of this?
Get a free quote →| Office | Handles | Contact |
|---|---|---|
| Zoning Office | Building permits, zoning, floodplain, special uses and variances | County Courthouse, 125 N. Plum St., Havana, IL 62644; 309-543-3759, option 9 |
| Highway Department | New entrances, work in county highway right-of-way, oversize loads | County Engineer Nicholas Peplow, 1164 E. Laurel Ave., Havana; 309-543-3253 |
| Mason County Health Department | Septic permits and inspections, water and geothermal well applications | 1002 E. Laurel Ave., Havana, IL 62644; 309-210-0110; environmental health Monday to Thursday 7 a.m. to 4:30 p.m. |
Cities and villages in Mason County
The county ordinance covers all land and water in Mason County except incorporated cities, villages and towns that have their own zoning ordinances in effect. The Census lists nine incorporated places (2025 estimates): Havana (2,799), Mason City (1,956), Manito (1,473), Easton (298), San Jose (277, part), Bath (262), Kilbourne (256), Forest City (211), Topeka (50). The county’s pages link the City of Havana and the Village of Manito; the county does not publish which towns lack zoning, so ask the town hall first. The county GIS search and property tax search show a parcel’s location.
Mason County permit types
Applications go to the Zoning Office on its own forms. Each must name the applicant, owner, architect, engineer and contractor, describe the site and the existing and proposed use, give the zoning district, and include a plat of survey by a registered land surveyor or another suitable drawing. That drawing shows the lot, structures, easements, streets, parking and driveways, yards and any highway access limits, plus abutting land and buildings within 40 feet. One permit for a main building also covers the accessory structures built with it.
Residential permits
- Houses in the agricultural district: a single-family home needs at least 3 acres and must sit 35 feet from any public right-of-way, 10 feet from every lot line and at least 1,000 feet from an existing house. A converted farm dwelling split off on its own lot needs at least an acre and may cover no more than 30% of it.
- Fences: a building permit unless the fence is agricultural, ornamental or under 100 lineal feet in total.
- Mobile homes: occupied only in a licensed park or as the ordinance allows; a temporary parking permit of up to 60 days requires a $250 deposit, cut by $100 if the home was parked before the permit, and no one may live in it or connect permanent utilities meanwhile.
- Temporary dwellings: garages, basements and campers may be lived in only under a temporary permit from the Zoning Enforcement Officer.
- Septic and wells: without public sewer or water, the application needs a sewage and water plan the Health Department certifies in writing.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Business and industrial buildings use the same permit, with the number of employees and the proposed operation on the application. Energy projects have their own ordinances: commercial solar (Ordinance 2026-56), commercial wind (Ordinance 2026-57) and energy storage, which the county posted as adopted June 9, 2026. Energy storage systems need a special use permit, reviewed at a Zoning Board of Appeals hearing; the application needs 10 paper copies and one electronic copy, and its fee is the lesser of $5,000 per megawatt or $50,000.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning district: the ordinance sets agricultural, rural estate, four residential, three business, two industrial and an extraction district.
- Special uses and variances: heard by the Zoning Board of Appeals after a newspaper notice published at least 15 days ahead, paid for by the applicant.
- Floodplain: the 2018 flood ordinance applies to land in the mapped floodplain.
- Entrances: a new driveway onto a county highway needs a Highway Department entrance permit.
The board’s November 2, 2026 agenda shows the kind of cases it hears: a variance to put a residential fence on the edge of the public right-of-way in an R-3 district, a special use for a new manufactured home with the old house to be demolished within a year, and a special use and fence variance for an electrical substation on farmland.
Mason County permit fees
Section 11.1 of the zoning ordinance leaves the fees for zoning amendments, use permits, certificates of compliance, variations and appeals to County Board action from time to time, paid to the County Clerk, and the fence section requires “the appropriate fee” with a building permit application. The Zoning Office does not post a fee schedule online, so call 309-543-3759, option 9, for the current permit fee. The fees the county and Health Department do publish:
| Item | Fee |
|---|---|
| Building permit | Not posted; ask the Zoning Office |
| Use permit, certificate of compliance, variation, zoning amendment, appeal | Set by County Board action; paid to the County Clerk |
| Mobile home temporary parking permit deposit | $250 (refundable as the ordinance provides) |
| Energy storage special use | Lesser of $5,000 per MW or $50,000 |
| Hearing notice publication | Paid by the applicant |
| Private sewage disposal permit (Health Department) | $100 application fee |
| Violation of the zoning ordinance | Fine up to $500; each week a separate offense |
Rather talk it over?
Call 1-855-478-4290 →Ask the Zoning Office for the base building permit amount before you file, and budget separately for the Health Department’s $100 septic fee and the soil investigation it requires.
Trade permits and who may pull them
The county’s zoning pages list no electrical, plumbing or mechanical permits and no county contractor license; the building permit is a zoning permit. Trade-related approvals come from these places:
- Septic systems: the Health Department permit asks for the installing contractor’s Illinois license number, the soil investigation and a site diagram showing the lot lines, parcel number, distances to wells, sewer lines and other sources of contamination, utilities and soil borings. The owner signs to accept responsibility for maintenance and must pass the maintenance records to the next owner.
- Wells: water well and geothermal well applications go through the Health Department.
- Plumbing and roofing: state licenses, as everywhere in Illinois.
- Work in county highway right-of-way: a Highway Department permit for the person doing the work.
The zoning application names the architect, engineer and contractor where the project has them; an owner can apply directly.
How to apply for a building permit in Mason County
Use the county GIS search to locate the parcel, and if it is inside a town, ask that town whether it has its own zoning.
Look up lot size and setbacks for the zoning district; book a Zoning Board of Appeals hearing first if you need a special use or variance.
Without public sewer, file the septic application with the soil investigation, diagram and $100 fee; without public water, file a well application.
Show the lot, buildings, easements, driveways, yards and abutting land within 40 feet.
Submit the county form at the courthouse in Havana and pay the fee the office quotes.
Work not substantially started within 180 days needs a new permit.
Rather not deal with the Mason County building department?
Get a free quote →Review, corrections and what causes delay
The biggest delays come from hearings: a special use or variance needs a published notice at least 15 days before the Zoning Board of Appeals meets, and hearings are held in the upstairs courtroom of the courthouse at 6 p.m. Anyone other than the applicant who wants to testify fills in a witness slip first. The Health Department issues no septic construction permit until the application is complete and the fee paid. Once issued, the work must be finished within 24 months; the Zoning Administrator may grant an extension of up to 12 months, but only after the Zoning Board of Appeals approves it. The Zoning Enforcement Officer can revoke a permit when the work breaks the rules it was issued under.
Inspections in Mason County
The Zoning Enforcement Officer checks that work matches the permit and the ordinance and can revoke permits found in violation; violations are petty offenses with fines up to $500, each week counting separately. The Health Department inspects septic work: notify it at least 2 working days before backfilling for the final inspection, and keep the absorption area secured against traffic so the soil is not compacted, removed or added to at any stage of construction. The inspection states whether the system meets state public health standards, and the department gives no warranty on the system.
Flood-damaged buildings
The Zoning Office’s floodplain notice explains what happens after a flood. If a house in the floodplain is damaged to 50% or more of its pre-flood market value (as previously established by the Supervisor of Assessments), it must be brought into compliance before repair. The main test is whether the lowest floor is at least one foot above the base flood elevation, which needs a licensed land surveyor’s FEMA Elevation Certificate; a repair permit is issued once a compliant certificate is presented, and the notice adds that flood insurance may provide up to $30,000 to protect a structure from future flood damage.
Building codes in Mason County
Mason County’s zoning page posts its zoning, flood, energy facility, nuisance and burn ban ordinances but no building code, and its permit is administered under the zoning ordinance. FEMA lists unincorporated Mason County (community 170463) as participating in the National Flood Insurance Program, with a current flood map dated June 6, 2018.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Want this handled start to finish?
Get a free quote →Mason County permit FAQs
Do I need a permit to re-roof my house in Mason County?
No. Routine maintenance and repair, including re-roofing, is exempt, as are alterations costing less than $1,000.
How much does a Mason County building permit cost?
The county does not post its building permit fee; the zoning ordinance leaves zoning fees to County Board action, paid to the County Clerk, so call the Zoning Office at 309-543-3759, option 9.
Do I need a permit for a fence?
Yes, unless it is a farm fence, an ornamental feature, or less than 100 feet long in total.
Who issues septic permits in Mason County?
The Mason County Health Department in Havana; the application fee is $100, and most sites need a soil test.
How big must a lot be for a house in the agricultural district?
At least 3 acres, with the house 35 feet from the road right-of-way, 10 feet from lot lines and 1,000 feet from an existing house.
Does the county issue permits in Havana?
Not where a town has its own zoning ordinance; county zoning excludes those towns. Ask the town first.
How long do I have to finish?
Start within 180 days and finish within 24 months; an extension of up to 12 months needs Zoning Board of Appeals approval.
Mason County permit records and official resources
The Zoning Enforcement Officer files every application and a copy of every permit issued, so ask the Zoning Office for copies; county records can also be requested under the Freedom of Information Act. County Board and zoning hearing agendas are posted on the county site.
Inspections are where schedules slip.
Get a free quote →- Mason County Zoning Office
- Zoning ordinance
- Flood ordinance (2018)
- Floodplain notice for damaged buildings
- Commercial solar energy facility ordinance (2026-56)
- Commercial wind energy facility ordinance (2026-57)
- Energy storage systems ordinance
- Non-commercial solar ordinance
- Zoning Board of Appeals agenda, November 2, 2026
- Highway Department and permit forms
- New entrance on a county highway permit
- Work in county highway right-of-way permit
- Health Department septic permits
- Private sewage disposal permit application
- Health Department water and well applications
- FEMA Community Status Book, Illinois
Simplify Mason County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Mason County sooner?
Let Alliance prepare, file, and track your Mason County permits while your crew stays on the job.
More Illinois permitting guides
Menard County
Read guide →Cass County
Read guide →Tazewell County
Read guide →Massac County Building Permit Guide
Read guide →Matteson Building Permit Guide
Read guide →Mattoon Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Mason County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.