Marion County has no building, planning or zoning department on its website, and it posts no building permit, zoning ordinance or building fee schedule for unincorporated land. The county permits that are published come from the Marion County Health Department (septic systems $75, new wells $100) and the Highway Department (culverts and entrances on county roads). The county directory lists a zoning line, (618) 548-3853, which is also the Supervisor of Assessments’ number in the Salem courthouse; call it to ask whether any county approval applies to your parcel. Commercial solar farms go through county special use permits. Inside Centralia, Salem and the other towns, ask the city or village hall.
What requires a permit in Marion County?
For land outside the cities and villages, the county’s own pages show these approvals:
County approval needed
- A new or replacement private sewage (septic) system: Health Department permit
- A new water well, or modifying or sealing one: state application through the Health Department
- A closed-loop geothermal well
- Installing, replacing, altering or removing a culvert in county right-of-way: Highway Department approval
- A commercial solar energy facility: county special use permit
Not published by the county
- A countywide building permit for houses, garages or commercial buildings
- A county zoning ordinance or zoning permit form
- A county building code or building fee schedule
- A floodplain development ordinance
The county directory still lists a zoning contact, and 2026 County Board agendas treat a solar project as a prior non-conforming use, so call (618) 548-3853 before you build.
What the county decides and what the state holds
The County Board, working through committees such as County & Community, decides county matters including commercial solar special use permits. The Health Department enforces the state private sewage code and the state water well codes locally, and refers uncorrected violations to the State’s Attorney. Plumbers and roofing contractors are licensed by the state.
Marion County building department: who handles permitting
These county offices handle the permits and records a builder needs on rural land:
| Office | Handles | Contact |
|---|---|---|
| Health Department, Division of Environmental Health | Septic permits and installation inspections, well permits, realty inspections | 118 Cross Creek Blvd., Salem, IL 62881; 618-548-3878, ext. 215; also 1013 N. Poplar, Centralia, (618) 532-6518; weekdays 8 a.m. to 5:15 p.m. |
| Highway Department | Culverts and entrances in county right-of-way; county roads | County Engineer Alex Kreke, 901 W. Elm St., Salem; (618) 548-3887; weekdays 7 a.m. to 3:30 p.m. |
| Supervisor of Assessments (directory zoning line) | Parcel records, aerial maps; the directory’s zoning number | 100 E. Main St., Room 101, Salem; (618) 548-3853; weekdays 8 a.m. to 4 p.m. |
| 911 / Addressing | Addresses for new homes | (618) 548-3685 |
Short on time to read all of this?
Get a free quote →Cities and villages in Marion County
The county lists four cities and ten villages; the Census estimates for 2025 are Centralia (9,598 in Marion County), Salem (7,035), Sandoval (1,123), Central City (1,067), Odin (903), Kinmundy (702), Junction City (517), Patoka (507), Iuka (491), Wamac (395, part), Alma (302), Kell (169), Vernon (97), Walnut Hill (92). Farina also extends into the county with no residents counted. Centralia also reaches into Clinton County. The county’s pages do not say who issues building permits inside each town, so ask the city or village hall; the county’s municipalities page links websites for Centralia, Salem, Central City, Kinmundy, Odin and Sandoval. Townships do not issue building permits, but the Highway page lists a road commissioner for each of the county’s 17 townships, who looks after township roads.
Marion County permit types
Residential permits
- Septic systems: the Health Department’s private sewage disposal plan review application (updated 2025) covers new, replacement and renovated systems. It asks for the owner, contractor and license number, directions to the site, the number of bedrooms, garbage grinder, water softener and hot tub, the water supply, the soil loading rate and limiting layer, and the design of the tank and field, aerobic unit, sand filter, lagoon or holding tank. A soil analysis is required for every subsurface seepage system, and a variance request form is available.
- Wells: before a private well is drilled, file the Illinois Department of Public Health application to construct, modify or abandon a water well with its $100 fee payable to the department; geothermal closed-loop wells have their own application.
- Driveway culverts: the Highway Department decides the culvert size, material, length and alignment for a home-site entrance off a county road.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial solar farms need county special use permits. On January 5, 2026 the County Board passed Resolution 2026-01, confirming the USS Wright Solar project as a prior non-conforming use, on a 13 to 2 roll call. Later 2026 agendas carried a decommissioning report for the Swamp Fox Solar project, a notice of a change in ownership of the special use permit for the SG Salem I PV facility, and the SG Salem II PV application: on September 22, 2026 the board voted to send that application to SKS Engineers for review, with the developer saying construction would be combined with SG Salem I and begin in spring 2027, and the October 27 agenda listed the engineer’s approval letter. Farm and commercial entrances on county roads follow the culvert policy.
Not sure this scope needs a permit?
Get a free quote →A restaurant or other food business needs a Marion County Health Department food permit before it opens. The department asks owners to fill in its opening-a-food-establishment form and call Environmental Health to talk through the plans, then submit the application with a layout drawing of the space, a written narrative of the operation and, where required, a Certified Food Protection Manager certificate. Review takes 6 to 7 business days, after which staff set a pre-opening inspection date. The permit class follows the menu: Class I covers complex preparation of foods that need time and temperature control, hot or cold holding, advance preparation, catering, smoking or curing and serving immunocompromised people; Class II covers food mostly prepared or served immediately; Class III covers reheating commercially prepared foods and selling only packaged foods or drinks.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Locate the parcel: the Supervisor of Assessments keeps a property record card for every parcel and sells aerial map printouts that help pin down the parcel.
- Address: 911 Addressing at (618) 548-3685.
- Septic and well: both approved before construction.
- Entrance: culvert approval and payment before the Highway Department orders the pipe.
- Town rules: inside a city or village, ask that town about its own permits first.
Marion County permit fees
The county posts no building or zoning permit fee. The published fees come from the Health Department’s permit fee schedule and the Highway Department’s culvert policy:
| Item | Fee |
|---|---|
| Septic permit, new or replacement | $75 |
| Realty inspection, septic / water | $75 / $75 |
| Water permit, new well | $100 (county fee schedule) |
| Existing well / water testing | $25 |
| Food permit, Class I / II / III | $75 / $50 / $35 |
| Temporary food permit | $20 |
| State well construction application | $100 payable to the Illinois Department of Public Health |
| Home-site entrance culvert, new | Owner reimburses the cost of materials |
| Commercial or farm entrance culvert, new | Owner reimburses equipment, labor and materials |
| Fill over 12 inches above a culvert | Owner pays the extra backfill, truck and driver |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the posted schedule: a new home on a private well and septic system pays the Health Department $75 for the septic permit and $100 for the new well, before any soil analysis or contractor costs; a business that only reheats commercially prepared foods or sells packaged foods and drinks falls in Class III at $35. The well page and the fee schedule each name a $100 well charge; ask the Health Department whether both apply to your well. Culverts are ordered only after the owner pays, and widening an existing culvert at the owner’s request is billed to the owner.
Once a deck, garage, porch or room addition is finished on an owner-occupied home, the Supervisor of Assessments can apply the Homestead Improvement Exemption under 35 ILCS 200/15-180, which keeps the added value off the tax bill for four years after completion, capped at $75,000 a year of fair cash value ($25,000 of assessed value). Owners apply at the Assessments office in Room 101 of the courthouse.
Trade permits and who may pull them
The county posts no electrical, plumbing or mechanical permit and no contractor registration for unincorporated land. Trade rules on its pages come from the Health Department:
- Septic installers: the application notes that, in general, work not done by the homeowner must be done by a licensed contractor, and it records the contractor’s license number.
- Well drillers and pump installers: the department administers the Water Well and Pump Installation Contractor’s Licensing Act and the state well construction and pump installation codes.
- Plumbers and roofers: state licenses, as across Illinois.
Inside the towns, contractor and trade rules are set by each city or village.
Rather not deal with the Marion County building department?
Get a free quote →How to get county approvals in Marion County
Check the property record card or aerial maps with the Supervisor of Assessments; if it is in a town, go to the town.
Ask at (618) 548-3853 whether any county approval applies to the project.
Download or pick up the private sewage application, complete every line, and submit it with the $75 fee; incomplete applications are not permitted.
File the state well application and fee before drilling.
Ask the Highway Department to size the culvert, sign the policy agreement and pay before the pipe is ordered.
Request the 911 address for a new home.
Review, corrections and what causes delay
The Health Department permits a septic system only when the application is filled out completely and correctly, and it needs the soil analysis for any seepage field. The Highway Department may deny a culvert request that would block drainage, cause flooding, raise road maintenance costs, create unsafe conditions or fall outside platted easements, and it will not order pipe until paid. Solar developers should expect County Board committee review of their special use permits and any later ownership changes.
Inspections in Marion County
The Health Department inspects septic systems during installation: give it 48 hours’ notice before the install, and staff will be present for it. Well drillers also give the Division of Environmental Health 48 hours’ notice before installation. Realty inspections of an existing septic system or well cost $75 each. Environmental health complaints are investigated, a correction period is given, and unresolved cases go to the State’s Attorney.
The county posts no building inspection program for houses or other buildings on unincorporated land, so ask the zoning line whether anything beyond the health and highway approvals applies.
Building codes in Marion County
Marion County’s website posts no building code, zoning ordinance or floodplain ordinance for unincorporated land. FEMA lists unincorporated Marion County (community 170932) under “Communities Not in the National Flood Program”, with a flood map dated November 16, 2011.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Marion County permit FAQs
Does Marion County issue building permits?
Its website lists no building department and posts no building permit for unincorporated land; call the county zoning line at (618) 548-3853 to confirm for your parcel.
How much is a septic permit in Marion County?
$75 for a new or replacement system, paid to the Marion County Health Department in Salem.
Want this handled start to finish?
Get a free quote →Do I need a permit to drill a well?
Yes. File the state well application with its $100 fee before drilling, and give the Health Department 48 hours’ notice.
Can I install my own septic system?
The application says that, in general, work not done by the homeowner must be done by a licensed contractor; a soil analysis is required for any seepage field.
Who handles driveway culverts on county roads?
The Highway Department in Salem sizes and installs them; for a home site you pay for the materials.
Is flood insurance available in unincorporated Marion County?
FEMA lists the unincorporated county among communities not in the National Flood Insurance Program.
How do I open a restaurant in Marion County?
Contact the Health Department’s Environmental Health staff, then file the food permit application with a layout drawing and narrative; review takes 6 to 7 business days and the permit costs $35 to $75 by class.
Who issues permits in Centralia or Salem?
Ask the city hall; the county’s pages do not cover permits inside the towns.
Marion County permit records and official resources
To request county records under the Freedom of Information Act, send the request to the County Board Secretary, 100 E. Main St., Room 201, P.O. Box 637, Salem, IL 62881, (618) 548-3868. County Board and committee agendas and minutes are posted on the county site. The County Clerk & Recorder’s office is at 101 E. Main St., Salem ((618) 548-3852, weekdays 8 a.m. to 4 p.m.).
Inspections are where schedules slip.
Get a free quote →- Marion County departments and phone directory
- Cities and villages in Marion County
- Supervisor of Assessments (parcels and aerial maps)
- Highway Department
- Highway culvert policy
- Marion County Health Department
- Private sewage program
- Private sewage disposal application (2025)
- Private water (well) program
- Environmental health permit fees
- Food protection program and food permit forms
- Food permit class guide
- Property tax exemptions (home improvement)
- County Clerk & Recorder
- Health Department offices
- County Board agendas and minutes
- County Board agenda, September 22, 2026
- Contact and FOIA requests
- FEMA Community Status Book, Illinois
Simplify Marion County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Marion County sooner?
Let Alliance prepare, file, and track your Marion County permits while your crew stays on the job.
More Illinois permitting guides
Centralia
Read guide →Fayette County
Read guide →Jefferson County
Read guide →Markham Building Permit Guide
Read guide →Marshall County Building Permit Guide
Read guide →Mason County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Marion County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.