In Glen Ellyn the Community Development Department’s Building Division issues building permits and inspects construction, working from the Civic Center at 535 Duane Street (630-547-5250; Monday to Thursday 8 a.m. to 4:30 p.m.; Fridays to noon under the May 22 to September 4 summer schedule). Applications are filed and signed online in the village’s LAMA permit software. Under the Schedule of Fees and Deposits effective April 21, 2025, a residential addition, alteration or remodel costs 1.25% of construction cost with a $500 minimum, and a new one- or two-family house costs 1%.
What requires a building permit in Glen Ellyn?
The village’s “Work That Requires a Building Permit” sheet lists 20 categories and says the list is not complete. Ordinary repairs with equivalent materials, where structure and utility systems are not altered and loads do not increase, typically need no permit, and the Building and Zoning Official can confirm a specific case from a complete description.
Buildings and systems
- Any new building or structure, and enlarged, altered or remodeled buildings, including basements or attics turned into living space and any room changed to a bedroom
- Accessory structures of every kind: garages, porches, decks, sheds, gazebos, fences, pergolas, play and tree houses, flagpoles and barbecues
- New, altered or replacement heating, cooling, water heating, plumbing, gas, ventilation, electrical, fire sprinkler and fire alarm systems
- New roofing, and residential or commercial re-roofing over 300 sq ft or more than 20% of the roof
- New exterior walls, and siding or cladding replaced over 300 sq ft or more than 20% of the wall area
- Outside equipment such as condensers, heat pumps, solar systems, generators and pool pumps
- Demolition, except areas of 300 sq ft or less and accessory structures in residential districts
Site and special cases
- Walks, patios, driveways and sport courts over 100 sq ft
- Retaining walls, ponds and fountains, and site work disturbing over 300 sq ft of grade
- Foundation waterproofing, drain tile, sump pumps, yard drains, dry wells and downspout discharges
- Pools, spas, hot tubs, playgrounds, swing sets and basketball hoops anchored to the ground
- Tents, stages and other temporary structures
- Repairs after fire, flood or accident (except interior finishes)
- Any work in, or within 30 feet of, a designated flood area
- Exterior changes to a Glen Ellyn Landmark, and to commercial, multi-family, duplex or townhome buildings
- Work in the street, sidewalk or parkway, and any change of occupancy or use
What Glen Ellyn decides and what the state holds
The village adopts and amends its own codes. Its posted list, which applies to applications received after January 1, 2024, names the 2018 International Building, Residential, Fire, Mechanical, Property Maintenance and Fuel Gas codes and the 2017 National Electrical Code, each amended by the Village Code, with the 2024 International Energy Conservation Code as amended by Illinois. The list also adopts the 2014 Illinois State Plumbing Code, the 2018 Illinois Accessibility Code, the 2010 ADA standards and the 2019 DuPage County Countywide Stormwater and Floodplain Ordinance, alongside the village’s own appearance, sign, stormwater, tree preservation, zoning and subdivision chapters.
Short on time to read all of this?
Get a free quote →Glen Ellyn building department: who handles permitting
Community Development reviews development projects, issues building permits, carries out building, fire safety and occupancy inspections, and reviews and issues stormwater permits. Its staff review most work on single-family homes, sending some plans to outside consultants, while commercial plans are checked by professional consultants or village staff. Some inspections are done by technical consultants or by Public Works. The department also staffs the Plan Commission, Zoning Board of Appeals, Historic Preservation Commission, Architectural Appearance Commission and Building Board of Appeals. Land outside the village that is unincorporated is permitted by DuPage County Building and Zoning (630-407-6700), which serves only unincorporated areas.
| Detail | Information |
|---|---|
| Office | Community Development Department, Civic Center, 535 Duane Street, Glen Ellyn, IL 60137 |
| Phone and fax | 630-547-5250; fax 630-547-5370 |
| Village main line | 630-469-5000 |
| Civic Center hours | Monday to Thursday 8 a.m. to 4:30 p.m.; Friday 8 a.m. to noon under the summer schedule (May 22 to September 4) |
| Survey and certification submittals | buildingpermits@glenellyn.org |
| Online filing | LAMA permit portal (glenellyn.onlama.com) |
Glen Ellyn permit types
LAMA walks applicants through the requirements for each permit type and work scope. Have the documents ready as PDF files before starting: typically construction plans, equipment information, the plat of survey, the scope of work and any trade contracts. The village’s forms page adds a one- and two-family zoning worksheet, a contractor listing sheet, drainage and site development (grading) plan requirements, a stormwater certification application, tree preservation guidelines, water supply fixture unit calculations and a plumbing affidavit.
Residential permits
- Plans. Construction plans must be prepared and stamped by an Illinois registered architect or structural engineer.
- Quick permits. Fences, water heaters and furnace or air conditioner replacements may be reviewed when submitted and issued without a full plan review.
- Basements, decks, sheds, fences, generators and car chargers. Each has its own guideline sheet, and fences come with an affidavit.
- New houses and additions. Expect foundation and height certifications, a final grading survey and, where a building sits within two feet of the minimum zoning setback, an approved foundation location survey by a licensed land surveyor before work goes past the foundation.
- Demolition. The village publishes demolition procedures and requirements; sewer, storm and water lines must be disconnected and inspected before a house comes down, and a demolition tax may apply.
- Landmarks. Historic preservation maintenance and alteration guidelines apply to designated properties.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial plans are reviewed by consultants and/or village staff, with comments sent through LAMA. The department posts walkthrough checklists for new businesses and restaurants, required-inspection lists for commercial and food service work, a temporary certificate of occupancy policy, Knox key box rules, a telecommunication submittal guideline and fire alarm guidelines for existing non-sprinklered multi-family buildings. Fire alarm, sprinkler and suppression systems are permitted and charged separately.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The Zoning Board of Appeals meets on the second Tuesday of each month at 7:00 p.m. at the Civic Center. It holds hearings on variations for single- and two-family homes and recommends to the Village Board, and it hears appeals of zoning decisions.
- Appearance and landmarks. Exterior changes to commercial, multi-family and attached homes follow the village’s appearance guidelines (Ordinance 5508VC), and landmarks follow the historic preservation guidelines; an exterior appearance review costs $210.
- Stormwater and floodplain. Community Development issues stormwater permits under the village’s stormwater and floodplain chapter and the DuPage County ordinance; a stormwater variation has its own application.
- Trees. A tree preservation review for single-family site work, grading or landscaping that is not part of another permit costs $250.
Glen Ellyn permit costs and fees
The Schedule of Fees and Deposits, effective April 21, 2025, is part of the Glen Ellyn Village Code. Plan review is included in the building permit fee unless the schedule says otherwise, and where a project has several line items the fees add up. Some fees are paid when applying and the rest at issuance, and refundable deposits cover damage to public property.
Rather talk it over?
Call 1-855-478-4290 →| Scope of work | Fee |
|---|---|
| New one- or two-family house | 1% of construction cost |
| New non-residential, mixed-use or multi-family building | 1.15% of construction cost |
| Residential addition, alteration or remodel | 1.25% of construction cost, $500 minimum |
| Commercial addition, alteration or remodel | 2% of construction cost, $1,500 minimum |
| Deck; detached garage | $295; $935 |
| Fence; windows, doors, siding, soffits or gutters | $80 each |
| Residential re-roofing; commercial | $90; $190 |
| Driveway | $155 |
| Pool, spa or hot tub, above ground; below ground | $135; $270 |
| Solar panel system | $470 |
| Water heater replacement; lawn irrigation | $125; $175 |
| Demolition, under 1,000 sq ft; 1,000 to 4,000 sq ft | $625; $775 |
| Expedited review, house (5 or 3 business days) | $500 or $1,000 extra |
| Permit extension | $50 per month |
| Work started without a permit | 200% of the permit fee, $260 minimum |
| Inspection after a second failed inspection | $105 |
Worked example from the schedule: a $60,000 kitchen remodel in a house pays 1.25%, or $750; a $30,000 remodel would work out to $375, so the $500 minimum applies. A new house’s 1% fee already covers its driveway and other paving, attached porches and decks, up to three detached accessory structures and site development and stormwater fees and deposits, but not water and sewer connections, fire sprinkler review, elevators or solar and geothermal systems. New homes also pay a $1,560 fire company contribution per dwelling, a $1,000 sewer service connection and the Glenbard Wastewater Authority fee of $278 per population equivalent (3.5 for a single-family house), and a $550 demolition tax applies when a building of more than 1,000 and up to 4,000 sq ft is demolished or more than half of a structure’s exterior roof and wall area is structurally altered. A zoning variation costs $685 plus a $1,000 escrow.
Trade permits and who may pull them
Electrical, plumbing and HVAC work are priced as separate line items: for example, a residential service upgrade is $130, a sub-panel $95, new water, sewer or storm lines for a house $310 and a sewer backup control system $285. Every contractor must meet the license and insurance rules in Village Code Section 4-1-11, and contractors working in breach of them can be cited, stopped or have the permit suspended or revoked.
Rather not deal with the building department?
Get a free quote →Registration is done in LAMA. The village charges no registration fee and requires no surety bond. Contractors upload a certificate of insurance naming the Village of Glen Ellyn as certificate holder and additional insured, with at least $1,000,000 per occurrence of general liability for a general contractor or $500,000 for an independent contractor, plus property damage and workers’ compensation cover; state- or municipally licensed trades upload their license instead. Public utility contractors are exempt for right-of-way work, and the general contractor files a contractor listing sheet naming everyone working on each permit. Property owners working on their own property are exempt from the contractor license and insurance rules; an owner doing plumbing without a license signs the village’s plumbing affidavit.
How to apply for a Glen Ellyn building permit
Use the 20-item list or call 630-547-5250 with a clear description of the work.
Variations, special uses and appearance or landmark reviews come before the permit.
Each contractor registers in LAMA with insurance or a license.
Upload stamped plans and documents as PDFs; the applicant signs electronically with the owner’s authorization.
Resubmit full revised sets with a response letter through LAMA.
Pay the remaining fees, print the permit and post it where it can be seen from the street.
Review, corrections and what causes delay
The first review time depends on how many applications are in line and varies by season. Projects are reviewed in the order received unless the submittal is incomplete or the plans are inadequate, and resubmittals and small projects are prioritized. A resubmittal must include a letter answering each comment and marking which sheets changed. After the second in-house review, each further review costs $200, and revisions after the permit is issued cost $75. Where an applicant and reviewer read a code provision differently, the Building Official is consulted to clarify it.
Inspections and certificates in Glen Ellyn
For permits issued through LAMA, open the permit under “Your Items,” go to the Inspections tab and click “I’m Ready for This Inspection.” The date and time are only a request; an email confirms the day and whether it is morning or afternoon. Requests after 2:00 p.m. cannot be met the next business day, and same-day inspections are not offered. Inspections run Monday to Friday from 8 to 11 a.m. and noon to 3 p.m., except that none are held on Tuesday mornings and plumbing inspections happen only on Monday, Wednesday and Friday afternoons from noon to 4 p.m. Older paper permits are scheduled by phone at 630-547-5250.
If nobody is on site, or a cancellation comes less than one business day ahead, a re-inspection fee is charged and must be paid before the final inspection or certificate of occupancy. Foundation surveys, height certifications and grading surveys are emailed to buildingpermits@glenellyn.org. Teardowns start with a pre-demolition inspection and utility disconnections, and a clearwater test of the sewer service is required when an addition grows a building by more than 75%, more than half of the walls and roof are altered, or an interior remodel tops $100,000. After all finals pass and the site is restored, deposits are refunded and an occupancy permit may be issued; a temporary certificate of occupancy costs $470.
Want this handled start to finish?
Get a free quote →Illinois building code in Glen Ellyn
FEMA’s Community Status Book lists the Village of Glen Ellyn (community 170207) as participating in the National Flood Insurance Program, with flood maps effective August 1, 2019, and in the Community Rating System at class 6, a 20% flood insurance discount, effective October 1, 2026.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Glen Ellyn building permit FAQs
Do I need a permit to re-roof my house in Glen Ellyn?
Yes, when the work covers more than 300 sq ft or more than 20% of the roof. The residential re-roofing fee is $90.
How much does a remodeling permit cost?
1.25% of the construction cost for a house, never less than $500.
Is there a contractor registration fee?
No. Contractors register in LAMA with insurance or a license, and the village asks for no bond.
Can a homeowner do their own work?
Yes. Owners working on their own property are exempt from the contractor rules, and unlicensed owner plumbing needs the plumbing affidavit.
When are inspections available?
Weekdays 8 to 11 a.m. and noon to 3 p.m., none on Tuesday mornings, with plumbing only on Monday, Wednesday and Friday afternoons. Request by 2 p.m. the day before.
Can I pay for a faster review?
For a one- or two-family house, $500 buys a review within five business days and $1,000 within three.
Who issues permits outside the village?
DuPage County Building and Zoning, for unincorporated land only.
Glen Ellyn permit search and official resources
Applicants find approved permit documents, comments and inspection results in their LAMA account. Other permit records are requested under the Freedom of Information Act with the village’s online FOIA request form or in person at the Civic Center, where the Village Clerk’s Office handles requests.
Inspections are where schedules slip.
Get a free quote →- Building Division
- Forms, applications and permits
- Work that requires a building permit
- Schedule of fees and deposits (effective April 21, 2025)
- Adopted building codes, ordinances and regulations
- Plan review and approval
- Construction inspections
- How to schedule an inspection
- Required inspections, residential
- Contractor registration
- Contractor registration requirements
- Zoning Board of Appeals
- Freedom of Information Act requests
- DuPage County Building and Zoning (unincorporated areas)
- FEMA Community Status Book, Illinois
Simplify Glen Ellyn permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Glen Ellyn sooner?
Let Alliance prepare, file, and track your Glen Ellyn permits while your crew stays on the job.
More Illinois permitting guides
DuPage County
Read guide →Glendale Heights
Read guide →Hinsdale
Read guide →Glenview Building Permit Guide
Read guide →Godfrey Building Permit Guide
Read guide →Granite City Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Glen Ellyn permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.