Glen Carbon, Illinois Building Permit Guide

To get a building permit in Glen Carbon, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Glen Carbon’s Building and Zoning Department issues building, electrical and plumbing permits in the village and takes every application through its online Licensing & Permitting Portal; paper and emailed applications are no longer accepted.

Authority: Village of Glen Carbon Building and ZoningFiling: Online portal onlyPhone: 618-288-2613
Permit office
Building and ZoningVillage Hall, 151 N. Main Street
Smallest permit
$30Work valued up to $1,000
Fee schedule
Ordinance 2025-50Schedule dated January 1, 2026
Inspections
By emailRequests go to the inspections mailbox

In the Village of Glen Carbon, building permits come from the Building and Zoning Department at Village Hall, 151 N. Main Street (618-288-2613, weekdays 8 a.m. to 4:30 p.m.), and every application and plan set is filed through the village’s online Licensing & Permitting Portal. Fees follow the Schedule of Fees adopted by Ordinance 2025-50: a building permit for work valued up to $1,000 costs $30, rising in steps with the value of the work.

What requires a building permit in Glen Carbon?

The village’s own list is broad. Permits are required for new homes and commercial buildings, roofs, siding, decks, fences, garages and carports, sheds, pools, remodeling jobs and electrical upgrades, and the village’s FAQ asks residents with questions about a planned project to call Building and Zoning (it lists 618-288-7502). The fee schedule adds signs, banners, solar installations, demolition, mobile home placement and occupancy permits, and a separate grading permit applies whenever a project changes existing grades by adding, removing or moving dirt.

Permit needed

  • New houses, additions and commercial buildings
  • Remodeling and electrical upgrades
  • Roofs and siding
  • Decks, pools and solar panels
  • Fences, sheds, garages and carports
  • Signs and banners
  • Demolition and mobile home placement

Low or no fee

  • Demolition permits: $0
  • Mass grading under 1 acre: $0 (over 1 acre $500)
  • First re-inspection: no charge
  • Accessory buildings other than garages: $30 flat

Starting without a permit costs a flat $500 failure-to-obtain-permit fee, and each code carries a penalty of $50 to $1,000 for every day a violation continues.

What Glen Carbon decides and what the state holds

The village sets its own codes and fees; its Board of Trustees adopted the current fee schedule by ordinance. The current building codes page lists the 2018 International Residential, Building, Mechanical, Fuel Gas, Property Maintenance and Swimming Pool and Spa Codes, the 2017 National Electrical Code and the village’s 2013 rental property code. Statewide rules sit alongside them: the Illinois Plumbing Code, the Illinois energy code for commercial and residential work and the 2018 Illinois Accessibility Code.

Glen Carbon building department: who handles permitting

The Building and Zoning Department enforces the building code first and the Zoning Code second. Under the Zoning Code it regulates the uses allowed in each district, yard and height limits, off-street parking, fences, walls and signs, and it works with the Village Board of Trustees and the Building and Development Committee on development matters. The department is led by the Director of Community Development, Erika Heil; the village notes that its inspectors are often out in the field.

Short on time to read all of this?

Get a free quote →

Glen Carbon issues permits only inside the village limits. Land outside the limits in unincorporated Madison County is handled by Madison County Building & Zoning, described in our Madison County guide; neighboring Edwardsville has its own city permit office.

Glen Carbon permit contacts
DetailInformation
OfficeBuilding and Zoning, Glen Carbon Village Hall, 151 N. Main Street, Glen Carbon, IL 62034 (mail: P.O. Box 757)
PhoneDirector of Community Development 618-288-2613; Village Hall 618-288-1200
HoursMonday to Friday, 8 a.m. to 4:30 p.m.
ApplicationsLicensing & Permitting Portal (online only)
InspectionsBy email to inspections@glen-carbon.il.us

Glen Carbon permit types

All permit types are opened in the Licensing & Permitting Portal. The village posts two short guides for first-time users, one on registering an account and one walking through a permit application, and plans are uploaded with the application rather than dropped off.

Residential permits

  • New homes and additions. Charged on the value of the work under the building permit table, with separate electrical and plumbing permits priced on the home’s market value.
  • Decks, pools, roofs and solar. Each is priced from the building permit table by the value of the job rather than at a flat rate.
  • Sheds and outbuildings. Accessory buildings other than garages are a flat $30; garages follow the building permit table.
  • Fences and banners. Fences are $30; banners $40, with no more than two permits a year of up to two weeks each.
  • Mobile homes. A permit is needed before a home is placed or moved within a mobile home park, priced from the building table, and park placements also need a $100 inspection and occupancy permit.

Commercial permits

Commercial buildings use the same value-based building table, which reaches $290 at $85,000 and then adds $4 per $1,000. Commercial electrical and plumbing permits are each 1% of the cost of all labor and materials, and non-residential site plans and subdivision plans are reviewed for $500 each plus any outside costs the village pays.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning approvals. Variances and appeals cost $450, special use permits $450 and rezoning or text amendments $550 plus $75 a lot; each fee includes up to $150 of publication and mailing costs.
  • Subdivisions and planned developments. Preliminary plats cost $300 plus $50 a lot and final plats $400; planned development procedures run $1,000 plus $50 an acre (commercial) or a living unit (residential), and new single-family lots pay a $750 greenspace fee at final plat approval.
  • Grading and erosion control. Mass grading needs a permit ($0 under an acre, $500 over) and a performance guarantee equal to the cost of the work in the erosion control plan.
  • Utilities. Village water and sewer tap-on fees, listed with the fees below, are charged separately from the building permit.
  • Underground utilities. Call JULIE (811) at least 48 hours, not counting weekends and holidays, before digging.

Glen Carbon permit costs and fees

All fees come from the Schedule of Fees dated January 1, 2026, adopted as Appendix D of the Village Code by Ordinance 2025-50, which the Board of Trustees passed on December 9, 2025. The schedule states that it overrides any fee printed in other ordinances, policies or applications. The building permit fee is a stepped table based on the value of the work.

Glen Carbon building permit fees (Schedule of Fees, January 1, 2026)
Work valued atFee
$0 to $1,000$30
$1,001 to $10,000$70
$10,001 to $15,000$85
$15,001 to $20,000$100
$20,001 to $25,000$115
$25,001 to $50,000$130 to $190 in $5,000 steps of $15
$50,001 to $55,000 / $55,001 to $60,000$205 / $215
$60,001 to $85,000$230 to $290 in $5,000 steps of $15
$85,001 and above$290 plus $4 per $1,000

Rather talk it over?

Call 1-855-478-4290 →
Other Glen Carbon permit and inspection fees
ItemFee
Electrical, residential$45 per $100,000 of market value, per unit
Plumbing, residential$65 per $100,000 of market value
Electrical or plumbing, commercial1% of labor and materials
New electrical service not in the building plans$45
Fence / accessory building (not a garage) / sign$30 / $30 / $80
Occupancy permit / returned permit$25 / $25
One permit extension beyond 6 months$50
Re-inspection: first / second / third and afterNo charge / $50 / $150
Missed inspection: first / second / third and after$100 / $250 / $500
Skipped inspection: first / second / third$250 / $500 / $1,000
Failure to obtain a permit$500

Worked example from the table: a deck project valued at $12,000 falls in the $10,001 to $15,000 band, so the building permit fee is $85; any new wiring adds the electrical charge.

Water and sewer connection fees

New buildings on village utilities also pay tap-on fees from the same schedule. Water taps cost $3,300 for a 5/8-inch line, $3,700 for 1 inch and $6,600 for 1½ inches; 2-inch taps are $7,200 and larger taps $7,500, each plus the cost of labor and materials, and taps larger than 1½ inches are the contractor’s responsibility. A single-family sewer tap-on is $3,500 inside the village and $4,500 outside, and multi-family, commercial and industrial users above 3.5 population equivalents pay an extra $350 (inside) or $400 (outside) for each one. Buildings with average daily flows above 1,500 gallons must provide a copy of their Illinois EPA sewer construction permit.

Trade permits and who may pull them

Electrical and plumbing permits are issued by the same Building and Zoning Department through the portal. For homes both are priced on the property’s market value rather than the cost of the trade work, and a new electrical service that is not shown on the building plans is a separate $45 permit. Commercial electrical and plumbing permits are a percentage of the trade cost.

  • Plumbing: work follows the Illinois Plumbing Code, which the village lists among its codes, and is done by a plumber licensed through the Illinois Department of Public Health.
  • Electrical: installations must meet the 2017 National Electrical Code as the village lists it.
  • Mechanical and fuel gas: the 2018 International Mechanical and Fuel Gas Codes apply; the fee schedule lists no separate mechanical permit.
  • Pools and spas: built to the 2018 International Swimming Pool and Spa Code and priced from the building table.

Rather not deal with the building department?

Get a free quote →

The fee schedule’s registration section covers the village’s $25 annual business registration; it lists no separate contractor license fee, and the building pages do not describe a contractor licensing program.

How to apply for a Glen Carbon building permit

1. Confirm the village has the parcel

Glen Carbon permits only inside its limits; unincorporated land goes to Madison County.

2. Check zoning

Ask Building and Zoning about the district, setbacks, height limits and any variance or special use you may need.

3. Register on the portal

Create an account in the Licensing & Permitting Portal using the village’s registration guide.

4. Apply and upload plans

Choose the permit type, describe the work and its value, and upload plans and site drawings; emailed and paper filings are refused.

5. Pay the fee

The fee is set from the January 1, 2026 schedule by the value of the work.

6. Book inspections

Email the inspections mailbox with the address and the stage that is ready.

Review, corrections and what causes delay

The village does not publish a set review time, and its inspectors are often in the field, so allow time for questions to be answered. The fee schedule allows one extension of a permit beyond six months, for $50, and it must be approved within six months of the permit; returned permits carry a $25 processing charge. Applications that arrive on paper or by email are not processed, and work that goes ahead before a required inspection triggers skipped-inspection fees starting at $250.

Inspections and certificates in Glen Carbon

Inspections are requested by email only, to the department’s inspections mailbox; include the address and the inspection needed. The fee schedule makes the costs of mistakes clear. The first re-inspection is free, the second costs $50 and each one after that $150. Missing an inspection appointment costs $100 the first time, $250 the second and $500 each time after that. A contractor, applicant or homeowner who proceeds without a required inspection pays a skipped-inspection fee of $250, then $500, then $1,000.

The fee schedule lists a $25 occupancy permit under Village Code 9-3-7. Rental property is held to the village’s 2013 rental property code and the 2018 International Property Maintenance Code, and mobile homes placed in a park need a $100 inspection and occupancy permit.

Want this handled start to finish?

Get a free quote →

Illinois building code in Glen Carbon

Glen Carbon enforces the codes on its current building codes page: the 2018 International Building, Residential, Mechanical, Fuel Gas, Property Maintenance and Swimming Pool and Spa Codes, the 2017 National Electrical Code, the Illinois Plumbing Code, the Illinois energy code, the 2018 Illinois Accessibility Code and the village rental property code; code violations are fined $50 to $1,000 a day. FEMA’s Community Status Book lists the Village of Glen Carbon (community 170442) as participating in the National Flood Insurance Program since July 18, 1983; its row shows no flood map dates of its own and no Community Rating System class.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Glen Carbon building permit FAQs

How much is a building permit in Glen Carbon?

It depends on the value of the work: $30 up to $1,000, $70 up to $10,000, then $15 more for most $5,000 steps up to $290 at $85,000, and $4 per $1,000 above that.

Can I still file a paper application?

No. The village has gone paperless and accepts permit applications and plans only through its online Licensing & Permitting Portal.

Do I need a permit for a fence, shed or new roof?

Yes. Fences are $30, sheds and other non-garage outbuildings $30, and roofs are priced from the building permit table by the cost of the job.

How do I schedule an inspection?

By email to the inspections mailbox listed on the village’s Request an Inspection page, which asks for inspection requests by email.

What happens if I miss or skip an inspection?

A missed appointment costs $100, then $250, then $500; proceeding without a required inspection costs $250, then $500, then $1,000.

Which building codes does Glen Carbon use?

The 2018 International codes, the 2017 National Electrical Code and the Illinois plumbing, energy and accessibility codes.

How much are water and sewer tap-ons for a new house?

A single-family sewer tap-on is $3,500 inside the village ($4,500 outside), and a 5/8-inch water tap is $3,300 or a 1-inch tap $3,700.

What does a zoning variance cost?

$450 for a variance or an appeal, including up to $150 of publication and mailing costs; a rezoning is $550 plus $75 a lot.

Glen Carbon permit records and official resources

Building and Zoning keeps the permit records for village addresses. Requests for other records go to the village’s FOIA officers on the village Freedom of Information Act form, mailed or delivered to Village of Glen Carbon, FOIA, 151 North Main Street.

Inspections are where schedules slip.

Get a free quote →

Simplify Glen Carbon permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Glen Carbon sooner?

Let Alliance prepare, file, and track your Glen Carbon permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Glen Carbon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.