Crawford County’s government in Robinson has no building, zoning or planning department, and its ordinance index lists no county building code or zoning ordinance. What the county does regulate in unincorporated areas comes through a floodplain development ordinance, a 2024 solar farm ordinance and its address-sign rule, plus the Crawford County Health Department (202 N. Christopher Blvd., 618-544-8798), which approves private sewage systems for $100 and processes well permits. The city of Robinson and the villages of Oblong, Palestine, Hutsonville, Flat Rock and Stoy govern building inside their own limits.
What requires a permit in unincorporated Crawford County?
Crawford County’s department list covers animal control, the assessor, circuit clerk, clerk and recorder, coroner, forest preserve, health department, highway department, probation, sheriff, state’s attorney and treasurer, with no building, zoning or planning office. The county board’s ordinance index, the county’s list of the ordinances it has adopted, names no building code, zoning ordinance or subdivision ordinance. The county therefore publishes no building permit for a house, garage or shed on rural land, but several county and state approvals still apply.
Approvals that apply
- Private sewage system plan approval and permit from the county health department
- Water well permit, processed by the health department for the state health agency
- Development in a mapped flood area, under the county’s floodplain ordinance
- Commercial solar farms, under Ordinance 2024-O-1 adopted March 14, 2024
- Work affecting county highways, through the Highway Department
- Address signs, under Ordinance 2012-O-004
Not published by the county
- A countywide building permit or building code
- County zoning permits, setbacks or a zoning board
- County electrical, plumbing or mechanical permits
- A county contractor license or registration
Because the county board adopts ordinances on its own schedule, check the most recent board minutes on the county website before a large rural project; the 2025 and 2026 minutes posted through September 2026 show no new zoning or building ordinance.
What the county decides and what the state holds
Illinois leaves building codes to local governments, and where a county has adopted none, as here, Illinois law sets minimums for commercial buildings and new homes instead. Septic systems follow the Illinois Private Sewage Disposal Code, enforced locally by the health department; wells follow the state water well construction code and are drilled only by contractors licensed by the Illinois Department of Public Health. Plumbing follows the Illinois Plumbing Code and plumbers are licensed by the state, as are roofing contractors.
Short on time to read all of this?
Get a free quote →Crawford County building department: who handles permitting
For unincorporated land, the offices a builder deals with are the Health Department (septic and wells), the Highway Department (county roads) and the county board, through the Clerk and Recorder, for ordinance questions such as floodplain development and solar farms. The county’s pages do not name a floodplain administrator; the county board’s page directs questions to the Clerk and Recorder. To find out whether a parcel is incorporated, look it up on the county’s Beacon GIS map or parcel information portal, run by the Supervisor of Assessments.
| Office | Contact |
|---|---|
| Crawford County Health Department (septic, wells) | 202 N. Christopher Blvd., Robinson, IL 62454; 618-544-8798, fax 618-544-9398; Monday, Wednesday and Thursday 8 a.m. to 5 p.m., Tuesday 8 a.m. to 7 p.m. |
| Highway Department (county roads) | 10312 N 900th St, Robinson; 618-544-2416 (24-hour 618-544-7211); County Engineer Justin Childress |
| Clerk and Recorder (board records, recording) | Courthouse, 100 S. Douglas Street, Robinson; 618-546-1212; 8 a.m. to 4 p.m. |
| Supervisor of Assessments (parcels, GIS) | Courthouse Annex, 100 S. Douglas Street; 618-544-8221; 8 a.m. to 4 p.m. weekdays |
The county seat, Robinson (population 7,283), and the villages of Oblong (1,352), Palestine (1,210), Hutsonville (469), Flat Rock (322) and Stoy (105) are separate governments. Building, zoning and trade rules inside their limits come from each city or village’s own ordinances, and the county’s pages do not say which of them run a building permit program, so ask the city or village hall before starting work there.
Crawford County permit types
With no county building permit, the permit types in unincorporated Crawford County are the health, road and ordinance approvals listed by the offices themselves.
Residential permits
- Private sewage system: the health department’s plan review application (revised September 9, 2025) asks for the owner and contractor, system address and township, number of bedrooms and residents, water supply, a soil investigation report giving the depth of the limiting layer, the proposed system design and a lot diagram showing wells, water lines, buildings, lot lines, elevations and any sanitary sewer within 300 feet. Soil tests are required to set the loading rate; percolation results are not accepted.
- Water well: the state’s water well permit form, filed through the health department with the $100 permit fee payable to the Illinois Department of Public Health; closed-loop geothermal wells use a separate state application.
- New houses, garages and sheds: no county building permit; the septic and well approvals, any floodplain rule and any county road work still apply.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial and other non-residential buildings in unincorporated areas also have no county building permit, but they fall under the statewide minimums described in the state note below. Non-residential septic systems use the same health department application with employee counts and design flow. Commercial solar farms are governed by the county’s Solar Farm Ordinance, 2024-O-1, and food businesses need health department food permits, with plan review at $200 for commercial kitchens.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before construction
- Check the parcel. Confirm on the county GIS map whether the land is inside Robinson or a village.
- Soils first. Most of the county has soils that rule out subsurface seepage fields, so most new systems are surface-discharging aeration units or sand filters; a certified soil scientist’s report comes before the septic application.
- Discharge permit coverage. Since February 10, 2014, new or renovated surface-discharging systems that reach waters of the United States need coverage under the Environmental Protection Agency’s NPDES general permit ILG62 before they operate; that process is separate from the county permit.
- Floodplain. FEMA’s flood map for unincorporated Crawford County is dated June 2, 2011; development in mapped flood areas is regulated by the county’s floodplain ordinance.
Crawford County permit costs and fees
There are no county building permit fees to budget. The fees that do apply on rural sites are the health department’s, from its fee schedule approved by the Board of Health on September 16, 2026 and revised November 4, 2026:
| Item | Fee |
|---|---|
| Septic permit | $100 |
| Septic installation inspected outside operating hours | $40 per hour extra |
| Missed septic appointment | $25 |
| Real estate septic inspection | $200 |
| New water well permit | $100, check payable to IDPH |
| Water test kit (pick up) | $25 |
| Onsite water collection and inspection | $50 |
| Food plan review | $100 non-commercial or mobile; $200 commercial |
| Food service establishment permit | $115 to $165 by category |
Rather talk it over?
Call 1-855-478-4290 →A typical new rural home with a septic system and a new well therefore pays $100 for the septic permit and $100 for the well permit, plus the soil scientist’s report and the installer’s price, which the county does not set. The health department notes that all prices may change without notice. Fees for building inside Robinson or a village are set by that city or village.
Trade permits and who may pull them
Crawford County issues no electrical, plumbing or mechanical permits and publishes no county contractor license or registration. The trade rules that apply on rural land come from the state and the health department:
- Septic systems: only Illinois licensed private sewage installation contractors, or the homeowner, may install them; the plan review form limits homeowner work to an owner who owns and occupies a single-family residence. The contractor must notify the health department 48 hours before construction and call for final inspection before covering the system.
- Aeration units: the system’s dealer must give the owner an initial two-year service policy, and the department recommends renewing it.
- Wells: only water well contractors licensed by the Illinois Department of Public Health may construct them; the health department keeps a list of local contractors.
- Plumbing and roofing: plumbers are licensed by the state and plumbing follows the Illinois Plumbing Code; roofing contractors hold a state license.
Inside Robinson and the villages, any electrical, plumbing or contractor registration rules are each municipality’s own.
How to get permits for a rural Crawford County project
Look the parcel up on the county’s Beacon GIS map to see whether it is unincorporated or inside Robinson or a village.
Check the FEMA map for the site and ask the Highway Department about any work touching a county road.
Have a certified soil classifier report the soil type and depth of the limiting layer for the septic design.
Submit the private sewage plan review application, soil report, site sketch and $100 fee to the health department.
Have a licensed well contractor file the state water well permit with the $100 fee through the health department.
The septic contractor gives 48 hours’ notice before work and calls for the final inspection before covering.
Rather not deal with the Crawford County building department?
Get a free quote →Review, corrections and what causes delay
The health department reviews and approves septic plans before construction, and soil limits are the usual issue: percolation tests are not accepted, and sites that cannot take a seepage field need a surface-discharge design and, if the effluent reaches waters of the United States, NPDES general permit ILG62 coverage. Missed appointments cost $25, and installations inspected outside office hours cost $40 an hour more.
Inspections in Crawford County
Without a county building department there are no county building inspections or certificates of occupancy on unincorporated land. The inspections that do happen are the health department’s:
- Septic: the contractor notifies the department 48 hours before construction starts and must call for final inspection and approval before the system is covered.
- Wells: after the new well and pump are in, the system is chlorinated and left about 30 days, then the department collects a free state water sample; results usually come back within a week.
- Property sales: a real estate septic inspection costs $200.
The department’s approval does not guarantee trouble-free operation of a septic system, and the owner takes responsibility for its upkeep. Inside Robinson and the villages, inspections are run under each municipality’s own rules.
Illinois building code in Crawford County
Crawford County has adopted no building code for unincorporated areas, so the statewide minimums apply there, with the floodplain and solar farm ordinances and the state private sewage and well codes enforced locally. FEMA’s Community Status Book lists Crawford County (community 170939, unincorporated areas) as participating in the National Flood Insurance Program, in the regular program since March 14, 1996, with its current flood map dated June 2, 2011; the county has no Community Rating System class.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Want this handled start to finish?
Get a free quote →Crawford County permit records and official resources
Septic installation permits and inspection reports, water well permits and well water sample data are kept by the health department. Freedom of Information Act requests go in writing to its FOIA officer at 202 N. Christopher Blvd., Robinson, or by fax to 618-544-9398; the department’s request form is optional. Recorded deeds are at the Clerk and Recorder, and parcel maps on the county’s Beacon GIS site.
- Crawford County, Illinois
- County Board, agendas and minutes
- County Board minutes (2025 and 2026)
- Ordinances index (solar farm, floodplain, address signage)
- Highway Department
- Clerk and Recorder
- Supervisor of Assessments
- Crawford County Health Department
- Private sewage systems
- Private sewage plan review application
- Private water wells
- Health department fee schedule (revised November 4, 2026)
- Health department FOIA requests
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Crawford County permit FAQs
Do I need a county building permit to build a house in rural Crawford County?
No county building permit is published: the county has no building or zoning department. You still need the health department’s septic permit, a well permit if you drill a well, and compliance with the floodplain ordinance in flood areas.
How much is a septic permit?
$100, paid to the Crawford County Health Department, with a soil investigation report; a real estate septic inspection costs $200.
Can I install my own septic system?
Yes, if you own and live in the single-family home it serves; otherwise an Illinois licensed private sewage installation contractor must install it.
Why are most systems aeration units or sand filters?
The health department says soil conditions prevent subsurface seepage fields in most of the county, so most approved systems discharge treated effluent at the surface.
Who handles permits in Robinson, Oblong or Palestine?
Each city or village governs building inside its own limits under its own ordinances; contact its city or village hall.
Is unincorporated Crawford County in the flood insurance program?
Yes. FEMA lists the county as participating, with flood maps dated June 2, 2011, and the county has a floodplain development ordinance.
Who do I call about work near a county road?
The Crawford County Highway Department at 618-544-2416; township roads are maintained by each township’s road commissioner.
Simplify Crawford County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Crawford County sooner?
Let Alliance prepare, file, and track your Crawford County permits while your crew stays on the job.
More Illinois permitting guides
Lawrence County
Read guide →Cook County
Read guide →Coles County
Read guide →Crestwood Building Permit Guide
Read guide →Darien Building Permit Guide
Read guide →De Witt County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Crawford County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.