Coles County has no county zoning and does not require building permits for land outside the zoning areas of Mattoon, Charleston, Oakland, Lerna, Humboldt and Ashmore, each of which reaches 1½ miles beyond its limits. What the county does regulate is the siting of specific uses (floodplain building, subdivisions, solar and wind farms, junkyards and a few others) through the Coles County Regional Planning & Development Commission (217-348-0521), and private septic systems and wells through the Health Department, where a house septic permit costs $200.
What requires a permit in Coles County?
The county’s zoning page is direct: there is no Coles County zoning for any parcel outside the zoning jurisdictions of the six towns, so the county does not ask for building permits, engineering reports, property specifications or other zoning paperwork there. Development still has to meet state and federal law, and several county ordinances still apply to particular uses.
County rules still apply
- Building in a mapped flood plain
- Dividing land into a subdivision
- Commercial solar and wind energy projects
- Regional pollution control facilities
- Junkyards and entertainment uses
- Private sewage systems and water wells (Health Department)
No county permit
- Houses, garages, sheds and pole buildings outside the town zoning areas
- Additions, decks, fences and pools on rural parcels
- Engineering reports or plan sets for zoning review
The catch is the 1½-mile ring. Mattoon, Charleston, Oakland, Lerna, Humboldt and Ashmore each have jurisdiction within 1½ miles of their boundary, and the county tells owners near a town to contact it to find out whether the project falls under that town’s ordinance. Charleston’s planning page confirms its zoning reaches 1½ miles past the city limits, and Mattoon publishes an extraterritorial permit application.
What Coles County decides and what the state holds
Coles County has no rural zoning and no building code, but the County Board sets the subdivision regulations (adopted in 1974 and last revised July 14, 1998), the flood plain rules and siting ordinances for solar and wind farms, including a 2026 wind ordinance. For commercial buildings the county points to state law, which requires an inspection before a new commercial building is first used; the forms for that are kept at the Coles County Assessment Office. Houses on rural parcels are not reviewed by any county building office, but their septic systems and wells are permitted and inspected by the Health Department.
Short on time to read all of this?
Get a free quote →Coles County building department: who handles permitting
Questions about whether a rural project needs any county approval go to Kelly Lockhart, Executive Director of the Coles County Regional Planning & Development Commission (CCRP&DC), whom the county names as the zoning contact. The Commission was formed by the County Board in 1967 to serve local governments; it offers GIS services including parcel, NG911 and zoning mapping, and it also serves Clark, Cumberland, Douglas, Edgar, Moultrie and Shelby counties. Subdivision plat petitions, including petitions to vacate a plat, are filed with the Commission. The county’s planning documents posted with the zoning page include a 2026 Comprehensive Plan, a Hazard Mitigation Plan dated July 8, 2025 and a Transportation Plan adopted March 11, 2025.
| Office | Handles | Contact |
|---|---|---|
| Regional Planning & Development Commission | Zoning questions, subdivisions, flood plain, solar and wind siting, GIS maps | Courthouse Room 309, 651 Jackson Ave, Charleston; 217-348-0521 (fax 217-348-7343); Monday to Friday 8:30 a.m. to 4:30 p.m. |
| Health Department, Environmental Health | Private sewage system permits and inspections; water well permits | 753 Windsor Road, Charleston; 217-348-0530 |
| Assessment Office | State inspection forms for new commercial buildings | Coles County Courthouse, Charleston |
| Highway Department | County highways | 217-348-0527 |
Cities and villages in Coles County
The two cities run full building departments. In Charleston (population 17,466), the Building and Development Services department at 520 Jackson Avenue permits and inspects construction inside the corporate limits and zones the 1½-mile ring around it. In Mattoon (16,667), the Community Development and Code Enforcement office at City Hall, 208 North 19th Street (217-234-7367), issues building, plumbing, mechanical, fence, sign and demolition permits and an extraterritorial permit. The county names Oakland, Ashmore, Humboldt and Lerna as the other places with zoning jurisdiction; owners there or within 1½ miles of them should start with that town hall.
Coles County permit types
Because the county issues no general building permit, the approvals that matter on rural land are the ones tied to a specific system or use.
Residential permits
- Private sewage disposal system. Required before anyone builds, alters or extends a septic system anywhere in the county. The Health Department reviews a plan for each system and inspects it before it is covered.
- Water well. The Health Department issues permits for new wells and approves the location, construction, modification and sealing of every well.
- Flood plain development. Building in a mapped flood plain falls under the county flood plain ordinance; ask the Commission before you design.
- Splitting land. A minor subdivision of not more than three lots, with no new right-of-way or easements, gets preliminary and final plat approval together; larger subdivisions follow the full plat process.
Not sure this scope needs a permit?
Get a free quote →The Health Department describes the three system types most often installed in Coles County: a conventional septic tank with a subsurface seepage field, which needs permeable soil without high groundwater; a buried sand filter, which uses less space but may discharge treated water to the surface; and an aerobic treatment unit, which works in some high-groundwater sites but needs ongoing service. Discharging into road ditches or onto neighboring land is prohibited, and surface discharges may need NPDES coverage.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
A new commercial building outside the towns needs no county building permit, but the county notes that state law requires it to be inspected before first use, and the forms are at the Assessment Office. Commercial solar and wind farms are governed by the county’s solar ordinance and its 2026 wind ordinance, and applications under them go to public hearings; the Apex wind energy application’s hearings began on March 17, 2025. Regional pollution control facilities, junkyards and entertainment venues also fall under county siting ordinances, so contact the Commission before buying or leasing a site for those uses.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Which jurisdiction? Check whether the parcel is inside a town or within 1½ miles of Mattoon, Charleston, Oakland, Lerna, Humboldt or Ashmore; if so, that town’s zoning and permit rules may apply.
- Soil evaluation. The Health Department says the first step for a new septic system is a soil evaluation, which sets the system type and where it can go.
- Sewer availability. The Health Department may refuse a septic permit where a public sewer is within 300 feet of a single-family home or 1,000 feet of a commercial or multi-family building.
- Easements. Where a system needs an easement, it must be recorded with the County Clerk and a copy filed with the permit application.
Coles County permit costs and fees
With no county building permit, there is no county building permit fee for rural land. The fees an owner is most likely to meet are the Health Department’s septic plan review charges, printed on the plan review application revised April 28, 2025; all are non-refundable.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Single-family home, system without surface discharge | $200 |
| Single-family home, surface-discharging system with NPDES coverage | $250 |
| Single-family home, surface-discharging system without NPDES coverage | $300 |
| All other buildings, no surface discharge | $200 |
| All other buildings, surface discharge | $300 |
| Late fee (application less than 7 days before construction) | $25 |
Section 3.3 of the subdivision regulations lets the County Board set plat review and subdivision recording fees under state law; the regulations print no amounts. Building permit fees inside Charleston and Mattoon, and in their 1½-mile areas, are set by each city.
Trade permits and who may pull them
Coles County has no electrical, plumbing or mechanical permit program of its own; trade permits exist only inside the towns that run them.
- Septic installers: the Health Department issues a sewage permit only to an Illinois-licensed private sewage disposal installation contractor who is registered in Coles County, or to a homeowner installing a system for the single-family home they own and live in. All other work must be done by a licensed contractor.
- Plumbing: plumbing work follows the Illinois Plumbing Code, and plumbers are licensed by the Illinois Department of Public Health.
- Roofing: roofing contractors are licensed by the Illinois Department of Financial and Professional Regulation.
- Well drillers: well and pump installation follows the Illinois Water Well Construction Code and the state contractor licensing act cited on the Health Department’s well page.
- Electricians and general contractors: the county publishes no license or registration requirement for rural work; Charleston requires electricians to be licensed inside its limits, apart from homeowners working on their own single-family home.
Rather not deal with the Coles County building department?
Get a free quote →How to get the permits a Coles County project needs
Ask the Regional Planning Commission (217-348-0521), which does parcel and zoning mapping, whether the land is inside a town or within 1½ miles of one.
Near a town, contact that city or village; on rural land, ask the Commission whether a flood plain, subdivision or siting ordinance applies.
Hire a soil classifier from the Health Department’s list before designing a septic system.
Submit the plan review application with a scaled plan, the soil report, the signed maintenance acknowledgment and the fee at least 7 days before work starts.
If the property needs a private well, the Health Department permit comes before drilling.
Pick up the state inspection forms at the Assessment Office and have the building inspected before first use.
Review, corrections and what causes delay
The Health Department returns septic applications that are incomplete, and it lists what the plan must show: lot size, system location and type, lateral lengths, distances to water lines, wells and buildings, site and ground elevations, the soil evaluation and the nearest sewer. Field variances are not given for items that belong on the application. An application filed less than 7 days before construction adds a $25 late fee, and no work may start and no inspection will be made until the permit is issued. A septic permit is void if construction does not start within six months.
Inspections in Coles County
There are no county building inspections on rural land. The inspections that do happen are the Health Department’s: it reviews septic plans and conducts on-site and final inspections, and Section 8.4 of the county private sewage ordinance forbids backfilling any part of a system before it has been inspected, so anything covered early must be dug up again. Aeration systems and lift stations need an alarm outside the building on a dedicated circuit with a disconnect within 50 feet, surface-discharging systems need chlorinators and a sample port, and treated effluent must stay on the owner’s property. For a new commercial building, the inspection required by state law before first use is arranged by the owner using the Assessment Office forms. Inside Charleston and Mattoon, the cities inspect.
Illinois building code in Coles County
Coles County has not adopted a building code for unincorporated land. FEMA’s Community Status Book lists unincorporated Coles County (community 170986) as participating in the National Flood Insurance Program, with flood maps effective July 18, 2011, and the county’s flood plain ordinance governs building in mapped flood areas.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Want this handled start to finish?
Get a free quote →Coles County permit search and official resources
For copies of county records, including septic permits and subdivision files, contact the county’s Freedom of Information Act office at the courthouse, Room 326, 651 Jackson Avenue, Charleston, (217) 348-0595. The Health Department also has a form for requesting information on a previously installed septic system.
- Coles County zoning statement
- Coles County Regional Planning & Development Commission
- Coles County Subdivision Regulations
- Coles County solar ordinance
- Coles County wind ordinance
- Health Department sewage systems
- Septic system requirements (September 2026)
- Septic plan review application and fees
- Health Department water wells
- Coles County office directory
- Coles County FOIA
- City of Charleston building permits and inspections
- City of Mattoon Community Development and Code Enforcement
- FEMA Community Status Book, Illinois
Inspections are where schedules slip.
Get a free quote →Coles County building permit FAQs
Do I need a county building permit to build a house in rural Coles County?
No, as long as the land is outside the zoning areas of the six towns; a home on a private septic system or well still needs Health Department permits for them.
How do I know if a town’s rules apply?
If the parcel is within 1½ miles of Mattoon, Charleston, Oakland, Lerna, Humboldt or Ashmore, contact that town; the Regional Planning Commission can help locate the parcel.
How much is a septic permit?
$200 for a single-family home with no surface discharge, $250 or $300 for surface-discharging systems, plus $25 if you apply less than 7 days before work starts.
Can I install my own septic system?
Yes, if you own and live in the single-family home; otherwise an Illinois-licensed installer registered in Coles County must do it.
Does a commercial building need an inspection?
Yes. The county notes that state law requires a commercial building to be inspected before first use; the forms are at the Assessment Office.
Who regulates solar farms and wind turbines?
The county, under its solar ordinance and its 2026 wind ordinance; commercial applications have gone to public hearings at the courthouse.
How long is a septic permit valid?
Six months from issue; if construction has not started by then, the permit is void.
Whom do I call about work along a county highway?
The Coles County Highway Department, listed in the county office directory at 217-348-0527.
Simplify Coles County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Coles County sooner?
Let Alliance prepare, file, and track your Coles County permits while your crew stays on the job.
More Illinois permitting guides
Mattoon
Read guide →Charleston
Read guide →Douglas County
Read guide →Cook County Building Permit Guide
Read guide →Country Club Hills Building Permit Guide
Read guide →Crawford County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Coles County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.