In the City of Darien, building permits are issued by the Community Development Department at City Hall, 1702 Plainfield Road (630-353-8115; Monday to Friday, 8:30 a.m. to 5:00 p.m.); the department head is Dan Gombac, Community Development Director. Applications, plans, contractor licenses, payments and inspection requests all go through the city’s OpenGov portal. Permit fees follow a schedule revised February 4, 2021: flat fees such as $50 for an air conditioner or a patio and $115 for a deck or shed, and a construction-cost table for new homes, additions and alterations.
What requires a building permit in Darien?
The city’s rule of thumb is simple: a permit is needed any time you change anything structural, plumbing or electrical, and structural changes need stamped architect plans or a letter from a structural engineer. Its “Do I Need a Permit?” sheet (last revised December 19, 2013) gives common examples on each side of the line.
Permit required
- New homes, room additions and attached or detached garages
- Structural alterations, including new or enlarged openings in foundations, walls, ceilings and roofs
- Re-roofing where old shingles are torn off
- New electrical and plumbing work inside walls
- Fireplaces and solid-fuel stoves; new and replacement air conditioners; generators
- Sheds, decks, porches, fences, driveways, patios (including paver brick) and retaining walls
- In-ground and above-ground pools; underground sprinklers
- Concrete work over 100 sq ft, new water service, sewer work in the public right of way
- Landscaping ponds or landscaping that changes the grade; electric vehicle chargers
- All commercial alterations and build-outs
No permit (single-family)
- Normal repair and maintenance, and replacing deteriorated materials
- A roof overlay, as long as the roof ends up with no more than two layers
- Roof repairs, siding, soffits and fascia
- Same-size window and door replacement
- Drywall, plaster and other cosmetic work that leaves structure alone; replacing fixtures
- Flatwork under 100 sq ft such as stoops and service walks; driveway overlay or sealcoating
- Landscaping that does not change the grade
- Replacing a furnace alone (an air conditioner replacement does need a permit)
In multi-family buildings only normal repairs and fixture replacement are free of permits.
What Darien decides and what the state holds
Darien adopts its own codes. Its current list, effective March 1, 2025, names the 2021 International Residential, Building, Existing Building, Mechanical, Property Maintenance, Fuel Gas and Swimming Pool and Spa codes, the 2020 National Electrical Code, the 2024 International Fire Code and the 2024 International Energy Conservation Code, with local amendments first set out in Ordinance O-15-18. On September 8, 2026 the City Council passed Ordinance O-34-26, a building code update for the 2021 Existing Building Code, by a 7–0 vote. Plumbing follows the 2014 Illinois State Plumbing Code and accessibility the 2018 Illinois Accessibility Code. The February 2025 information packet still lists the 2021 energy code, so where the two differ, the codes page is the newer statement.
Short on time to read all of this?
Get a free quote →Darien building department: who handles permitting
The Community Development Department handles planning, zoning, building and property maintenance. Its building staff run the permit process for construction, signs, solar installations, grading, stormwater facilities, construction water and demolitions, including plan review, fees, third-party inspections and certificates of occupancy, and they register contractors. Plan review fees are charged through an outside professional service, and grading plans for new homes go to a consulting engineer. Unincorporated land outside the city is permitted by DuPage County Building and Zoning (630-407-6700), which serves unincorporated areas only.
| Detail | Information |
|---|---|
| Office | Community Development Department, City Hall, 1702 Plainfield Road, Darien, IL 60561 |
| Permits and inspections | 630-353-8115; fax 630-852-4709 |
| City Hall main line | 630-852-5000 |
| Hours | Monday to Friday, 8:30 a.m. to 5:00 p.m. |
| Department head | Dan Gombac, Community Development Director, 630-353-8106 |
| Online filing | OpenGov portal (applications, contractor licenses, payments, inspections) |
Staff can walk applicants through the portal by appointment; paper applications may take longer to process.
Darien permit types
Every job starts with the building permit application in OpenGov, plus the drawings and documents the city lists for that type of work. Handouts cover fences, driveways, patios, pools, hot tubs, sheds, decks, solar, generators, sump pumps, lawn sprinklers and car chargers.
Residential permits
- Remodels. Moving or adding a wall needs a stamped letter or plans from a licensed architect or structural engineer. Electrical, plumbing and cabinet replacement without structural change needs a drawing showing where the new work goes.
- Roofs. The application, the contract given to the homeowner, the roofer’s contractor license application and state license. Darien follows the 2021 International Residential Code for ice barriers and re-roofing and does not inspect roof permits.
- Fences. A plat of survey marking the fence line and the fence company’s proposal; an owner doing the work submits the summary sheet from the store showing type, footage and height. Fence installers need no city license.
- Driveways, patios and walks. The application, the plat of survey marking the area being replaced or widened and the contractor’s proposal; an owner doing the work lists themselves as contractor.
- Pools, sheds, decks and generators. Each needs the application and a plat of survey showing the location, plus the product or construction details (pool brochure and specifications, shed specifications, a deck drawing with dimensions, the generator’s specifications and its electric and gas lines). Above-ground pool permits take about two weeks.
- Solar. Roof- or wall-mounted systems are an accessory use in every zoning district. Submit the portal applications, a plat with a dimensioned panel layout, structural calculations sealed by a licensed structural engineer and plans meeting the 2021 International Solar Energy Provisions; standard systems are usually issued within 10 days of a complete submittal.
- New homes. Two sets of architect-stamped plans, a sealed plat of survey and grading plan (three copies) with elevations, contours and erosion control, and proof of the DuPage County impact fee.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Commercial, office and industrial projects need three sets of stamped plans showing sprinkler, HVAC, electrical, fire alarm and exit lighting details, wall ratings, accessibility features and a door schedule. The city sends commercial plans to the fire district for its own review and inspection, and the fire district bills its fees directly. New or relocating businesses also need a business license from the City Clerk (630-353-8110).
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. The nine-member Planning and Zoning Commission meets on the first and third Wednesdays at 7:00 p.m. It decides “simple” single-family variations itself (front or corner side yard cuts of 10% or less, or side yards reduced to no less than 7.5 feet); other variations go on to the Municipal Services Committee and the City Council, which usually takes two to three months. Applicants supply stamped envelopes for owners within 250 feet and post a hearing sign 15 to 30 days ahead.
- Stormwater and grading. New construction needs an engineering and grading plan reviewed for stormwater compliance, and the DuPage County stormwater permit is paid to the city.
- Sewer, water and health. New homes and residential additions of 800 sq ft or more must contact DuPage County’s sanitary sewer department (630-407-6809) and show the city the receipt; Public Works decides what a water service needs, and food or health-related businesses may need the DuPage County Health Department (630-682-7400).
- Floodplain. The city adopted FEMA’s August 1, 2019 flood maps to stay in the National Flood Insurance Program.
Darien permit costs and fees
The city posts a Building Department / Public Works Permit Fee Schedule revised February 4, 2021. Several items, such as detached garages, generators and pools, are marked “TBD” and priced after plan review. A temporary waiver of certain building permit fees approved by the council for March 3 to April 30, 2026 has ended.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Air conditioner replacement; roof; patio; private sidewalk | $50 each |
| Deck or shed | $115 |
| Fence | $25 |
| Driveway | $75 plus a $175 refundable deposit |
| Demolition | $100 |
| New home, addition or alteration: construction cost up to $8,000 | $75 |
| Construction cost $15,001 to $20,000 | $200 |
| Construction cost $50,001 to $75,000 | $1,000 |
| Construction cost $150,001 to $200,000 | $2,000 |
| Construction cost over $200,000 | $2,500 plus $10 per extra $1,000 |
| Plan review: new single-family home; addition | $315; $215 |
| Plan review: garage, basement remodel, deck or shed | $115 |
| Plan review: commercial | 0.3% of construction cost |
| Re-inspection | $80 first, $100 after |
| Work started without a permit | Twice the standard fee |
| Final occupancy | $50 (commercial certificate of occupancy $100) |
Worked example from the table: a home addition costing $60,000 falls in the $50,001 to $75,000 band, so the permit fee is $1,000, and the addition plan review adds $215, for $1,215 before any engineering or trade charges. New homes on empty lots also pay impact fees: for a detached house the total is $5,263 with three bedrooms or $7,507 with four, covering the park, grade school and high school districts, the library and the city. A tear-down and rebuild pays no Darien impact fee but does pay the DuPage County impact fee (630-407-6882). Engineering fees apply to all new construction, at least $500 for a new single-family home.
Trade permits and who may pull them
Every contractor working in Darien, subcontractors included, must hold a city contractor’s license, applied for and renewed in OpenGov. Licenses run from May 1 to April 30; the fee is $60 a year, or $30 for a half-year license issued from November 1. General, carpentry, landscaping, concrete, asphalt, pool, sign and HVAC contractors file a certificate of insurance naming the City of Darien as certificate holder and a $10,000 license and permit bond; a general contractor may instead post one $20,000 bond that covers all of its subcontractors. Electricians show an electrical license from a testing jurisdiction in Illinois (city, county or state), insurance and the $10,000 bond, and pay the $60 fee.
Rather not deal with the building department?
Get a free quote →Plumbers, roofers and fire protection or fire alarm contractors file the application with a copy of their State of Illinois license only, with no fee, bond or insurance, although a plumber doing sewer work must also hold a Darien contractor’s license. Fence installers need no license at all. Lawn sprinkler contractors need a city license and their state license, and the backflow (RPZ) device is inspected at the end. On owner-built jobs the homeowner is listed as the contractor on the application.
How to apply for a Darien building permit
Use the permit and no-permit lists, or call 630-353-8115, to confirm the work needs a permit.
If the plan breaks a setback, apply for a variation; hearings run about two to three months.
Make sure every contractor on the job holds a current Darien license, bond and insurance in OpenGov.
Upload the application, plat of survey, plans or drawings and the proposal or contract for the work type.
Plan review fees come through an outside professional service; revised plans must be stamped and may cost more.
Pay the fees, keep the permit and plans on site and start work within 60 days.
Review, corrections and what causes delay
The city does not process an application until it is complete. Missing plats of survey, unstamped plans for structural work, unlicensed or unbonded contractors and unpaid county impact or sewer fees are the usual holdups. The city also allows only one open building permit per property unless the earlier work is moving at a reasonable pace.
Inspections and certificates in Darien
All permitted work must be inspected, and the owner or contractor arranges each one; skipping a required inspection can bring a fine. Call 630-353-8115 by 2:00 p.m. for an inspection the next business day, or request it in OpenGov. Inspections usually run between 8:00 a.m. and noon, and for solar jobs the contractor must be on site. A cancellation must reach the department before 2:00 p.m. on the day before; late cancellations and failed inspections are charged as re-inspections, which must be paid before the next visit is booked.
A new house typically sees footing, foundation, backfill, under-slab, slab, rough plumbing and electrical, framing, insulation, trade finals and a final inspection. Three copies of a spot survey are due within 14 days after the foundation is placed, and only utility work may proceed until it is approved. Final occupancy needs the as-built grading survey at least four days ahead, Water Department approval and finished sod or seed, sidewalk, driveway and landscaping; a temporary occupancy permit may be issued against a cash bond. Commercial jobs add the water final, a fire alarm or sprinkler final with the fire district and city inspector, and any county health inspection.
Want this handled start to finish?
Get a free quote →A permit becomes void if work has not started within 60 days of issuance or no inspection has been requested, and every permit expires after one year unless the city grants an extension. Construction may not begin before 6:30 a.m. on weekdays or 7:30 a.m. on weekends and must stop by 10:00 p.m.
Illinois building code in Darien
FEMA’s Community Status Book lists the City of Darien (community 170750) as participating in the National Flood Insurance Program, with flood maps effective August 1, 2019.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Darien building permit FAQs
Do I need a permit to replace my roof in Darien?
A tear-off re-roof needs a permit; roof repairs and an overlay that keeps the roof to two layers do not. Roof permits are not inspected.
Do I need a permit for new windows or siding?
No for same-size windows and doors, siding, soffits and fascia. Enlarging an opening is structural work and does need one.
How much is a deck permit?
$115, plus a $115 plan review under the 2021 fee schedule.
Does my contractor need a Darien license?
Yes, every contractor does, at $60 a year, except fence installers. Plumbers, roofers and fire protection contractors file their state license with no fee.
How do I schedule an inspection?
Call 630-353-8115 by 2:00 p.m. for the next business day or use OpenGov. Failed or late-cancelled inspections cost $80, then $100.
How long is a Darien permit good for?
Work must start within 60 days, and the permit expires after one year unless extended.
Who handles permits outside the city limits?
DuPage County Building and Zoning, for unincorporated land only.
Darien permit search and official resources
Permit status and inspection results for portal applications can be followed in OpenGov; for older files, call Community Development at 630-353-8115. Copies of permit records are requested under the Freedom of Information Act from the city’s administrative records FOIA officer at 1702 Plainfield Road, in writing by mail, in person, by fax or by email; the city answers within five business days, and the first 50 black-and-white pages are free.
Inspections are where schedules slip.
Get a free quote →- Darien forms and permits
- Darien OpenGov permit portal
- Do I need a permit?
- Current building codes (effective March 1, 2025)
- Permit fee schedule (revised February 4, 2021)
- Building permit information packet (February 2025)
- Zoning variations information and application
- Community Development Department
- City Council agendas and minutes, 2026
- City Council minutes, September 8, 2026 (Ordinance O-34-26)
- Property located within a floodplain
- Freedom of Information Act requests
- DuPage County Building and Zoning (unincorporated areas)
- FEMA Community Status Book, Illinois
Simplify Darien permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Darien sooner?
Let Alliance prepare, file, and track your Darien permits while your crew stays on the job.
More Illinois permitting guides
DuPage County
Read guide →Downers Grove
Read guide →Elmhurst
Read guide →De Witt County Building Permit Guide
Read guide →Decatur Building Permit Guide
Read guide →Deerfield Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Darien permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.