Building permits in the Village of Deerfield come from the Community Development Department, whose Building & Code Enforcement Division works from Village Hall at 850 Waukegan Road (847-719-7484), Monday to Friday from 8 a.m. to 4:30 p.m. Most permit types are filed online through the village’s OpenGov portal. Under the 2026 fee schedule, most work costs $19 per $1,000 of estimated construction cost and new one- and two-family homes $0.75 per square foot, plus a plan review fee. Applications filed after March 1, 2026 are reviewed under the 2024 International Codes the Village Board adopted on January 20, 2026, according to the board’s minutes.
What requires a building permit in Deerfield?
Deerfield’s “When do I need a permit?” infographic covers work around a typical house. It is a guide, not a full list; the owner is ultimately responsible for getting the right permits, and every submittal needs the proposal or scope of work.
Permit needed
- Additions, decks, porches, garages (build, enclose or alter), sheds and other accessory structures, demolition
- Kitchen and bath remodels, even cosmetic in-kind replacement; attic and basement finishing; gut rehabs
- New or replacement roofs and overlays; new skylights; windows or doors where the opening changes
- Moving or adding walls, structural stair work, insulation when a wall is opened
- Electrical service upgrades, panel moves, car chargers and new wiring or light fixtures
- Plumbing services, lead pipe and meter replacement, RPZ replacement, new or moved fixtures, boilers, new or relocated air conditioning
- Driveways, patios, walks and hardscape; masonry over 50 square feet; new or relocated fences; pools and spas; irrigation; solar panels; regrading or underground drainage
No permit
- Painting, flooring, carpet, tile, cabinets and appliances with no electrical or plumbing work
- Siding, gutters, soffits and fascia; chimney spot repair; roof patching
- In-kind replacement of windows and doors without enlarging the opening, and of skylights
- In-kind replacement or repair of a furnace, water heater or air conditioner
- One plumbing fixture or light fixture replaced in kind on its own
- Garage door or opener replacement; landscaping and play equipment; masonry repair up to 50 square feet or tuckpointing; in-kind fence replacement where the original fence had a permit
When in doubt, call the Building Division at 847-719-7484.
What Deerfield decides and what the state holds
Deerfield sets its own building regulations in Chapters 6 (buildings), 8 (electricity) and 13 (property code) of its municipal code. According to the January 20, 2026 board minutes (in the February 2, 2026 packet), the Village Board voted 5-0 for Ordinance O-26-03, moving from the 2018 International Codes to the 2024 International Building, Residential, Mechanical, Fire, Fuel Gas, Property Maintenance and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with local amendments; they apply to permit applications submitted after March 1, 2026. (The Building Division page still describes the adoption as expected; the board minutes and the Community Development page show it done.) Plumbing follows the state plumbing code; fees, zoning, appearance and tree preservation rules are the village’s own.
Short on time to read all of this?
Get a free quote →Deerfield building department: who handles permitting
All development in Deerfield comes through the Community Development Department, which administers the zoning ordinance, building code, comprehensive plan and subdivision code. Its Building & Code Enforcement Division reviews plans, issues permits, inspects construction and enforces village codes; it also licenses contractors, issues the semi-annual elevator inspection certificates and supports the Board of Building Appeals, the Board of Zoning Appeals and the Electrical Commission. The Planning Division supports the village’s planning commissions. Some plans are also reviewed by the Village Engineering Department. Deerfield straddles Lake and Cook counties; unincorporated land outside the village is permitted by the county, not by Deerfield.
| Detail | Information |
|---|---|
| Office | Community Development Department, Village Hall, 850 Waukegan Road, Deerfield, IL 60015 |
| Building Division | 847-719-7484; fax 847-945-0287 |
| Hours | Monday to Friday, 8 a.m. to 4:30 p.m. (Village Hall closed noon to 1 p.m.) |
| Village Hall | 847-945-5000 |
| Engineering | 847-317-2490 (Public Works and Engineering, Monday to Friday, 7 a.m. to 3:30 p.m.) |
| Portal | OpenGov permitting and licensing (online applications, status, messages to staff) |
Deerfield permit types
Deerfield has moved most permits to OpenGov, where you create an account, apply, track status and message staff. The online categories include demolition, commercial interior buildout, commercial and multi-family construction, decks, detached accessory structures, driveways and hardscape, electrical-only work (service upgrades, EV chargers, generators, wiring), elevators, fences, grading and foundation work, irrigation, pools and hot tubs, residential construction (new one- and two-family homes and additions), residential interior remodels, roofing, sewer repair, signs, solar panels, sport courts, telecommunications and private utilities, and water service. An “uncategorized project” application is used only when the Building Division directs it, and any remaining paper permit types are downloaded from the forms page.
Residential permits
- New houses and additions use the Residential Construction application. New one- and two-family homes pay $0.75 per square foot, include plumbing fixtures and temporary water in the general permit fee, and carry a $1,500 base electrical fee per dwelling.
- Remodels use the residential interior remodel application; kitchen and bath remodels need smoke alarms installed by the rough inspection.
- Pools, decks, fences and accessory buildings each have their own application, and the fee schedule charges a tree preservation plan review for most lot improvements.
- Owners doing their own work register as a homeowner, which is allowed for plumbing, roofing, electrical, general, concrete and excavation work but not for irrigation RPZ backflow devices.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial and multi-family construction and commercial interior buildouts have their own applications, a commercial plan review fee of $200 to $600 depending on cost, and engineering plan review at 3% of the estimated value of improvements. Signs have their own permit.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief goes to the Board of Zoning Appeals by petition; Plan Commission requests use the Plan Commission application and indemnity form, and the village publishes its special use procedures.
- Appearance review. Projects that need it go to the Appearance Review Commission, which has its own hearing application and submittal requirements, including a set for signs.
- Engineering. Some plans are also reviewed by the Village Engineering Department, which publishes an engineering checklist and transmittal form; grading, drainage and foundation work has its own permit application.
- Trees. A tree preservation plan review is charged for decks, patios, fences, sheds, pools, additions and lot redevelopment.
Deerfield permit costs and fees
Deerfield’s permit fees are set each year in the village’s annual fee resolution; the figures below are from the 2026 schedule (fees for calendar year 2026). The department’s annual report to the Village Board notes that its latest fee update raised the main permit rate from $18 to $19 per $1,000 and the new-home rate from $0.55 to $0.75 per square foot. Fees are worked out from the estimated cost of the job, and are paid at Village Hall or online for the permit types processed in OpenGov.
| Item | 2026 fee |
|---|---|
| Construction permit, all work except new one- and two-family homes | $19 per $1,000 of estimated construction cost |
| New one- and two-family home | $0.75 per square foot |
| Residential plan review (by estimated cost: to $15,000 / to $50,000 / over $50,000) | $50 / $100 / $150 |
| Commercial plan review (to $100,000 / to $500,000 / over $500,000) | $200 / $400 / $600 |
| Infrastructure impact fee | 0.5% of estimated construction cost |
| Roof construction and repair | $75 |
| Patios, walkways and other slabs | $100 |
| Solar photovoltaic | $9.50 per $1,000 of estimated cost |
| Swimming pool / air conditioning system | $19 per $1,000 of the first $10,000, then $17.20 per $1,000 |
| Electrical permit | $50 base plus $2 per device opening |
| New service or upgrade / generator / EV charger | $150 each |
| Fence | $75 |
| Residential driveway | $100, plus a $200 deposit per apron |
| Sewer repair | $100 |
| Demolition | $100 per 1,000 sq ft of lot area |
| Tree preservation plan review: decks, patios, fences, sheds, pools | $175 |
| Tree preservation plan review: room additions / lot redevelopment | $275 / $525 |
Rather talk it over?
Call 1-855-478-4290 →Worked example. A $30,000 residential interior remodel: the construction permit fee is 30 × $19 = $570, and residential plan review for a job between $15,001 and $50,000 is $100, for $670 before any other charge on the schedule that applies to the project. A 3,000-square-foot new house is 3,000 × $0.75 = $2,250 for the construction permit alone.
Related charges
- Work without a permit: twice the base building permit fee, at least $300 and at most $1,000.
- Re-inspections: $100 for a failed inspection, a no-show or a late cancellation, paid before the next inspection is booked.
- Performance guarantees for new houses: the greater of 3% of construction value or $10,000 when the work exceeds $100,000, and $3,000 (or an amount set by the director of public works) up to $100,000.
- Sewer and water: single-family sanitary connection $300 plus $100 inspection; storm connection $200 plus $100; water tap $440; $10 per plumbing fixture outside new one- and two-family homes.
- Impact fee: new dwellings pay an impact fee by type and bedroom count under Ordinance O-93-48 (for example $12,933.40 for a three-bedroom detached house).
- Contractor registration: $100 a year for general, electrical, concrete, sewer, irrigation, roofing and excavation contractors.
Trade permits and who may pull them
Deerfield licenses its contractors through online registration in OpenGov, and the trades that must register are general contractors, electricians, plumbers, irrigation, roofing, excavation, concrete and sewer contractors, plus homeowners doing their own work.
Rather not deal with the building department?
Get a free quote →| Trade | What to provide |
|---|---|
| General contractor | Signed $20,000 surety bond; $100 |
| Electrical | Copy of a current electrical license; signed $20,000 bond; $100 |
| Plumbing | Copies of the IDPH 055 and 058 plumbing licenses |
| Irrigation | Copy of the IDPH 060 license and the state cross-connection license; $100 |
| Roofing | Copy of the current State of Illinois roofing license; signed $20,000 bond; $100 |
| Excavation, concrete | Signed $20,000 surety bond; $100 |
| Homeowner | Signed legal document; may do plumbing, roofing, electrical, general, concrete and excavation work, but not irrigation RPZ backflow devices |
Electrical work is permitted under Chapter 8 of the village code at $50 plus $2 for each device opening, and service upgrades, generators and EV chargers are $150 each. Plumbing and sewer tap inspections are billed at the consultant’s fee plus 15%; the schedule lists the licensed plumbing inspector as an independent contractor. Changing contractors on an open permit takes a change of contractor request in the portal.
How to apply for a Deerfield building permit
Check the property is inside Deerfield and look up its zoning on the 2026 zoning map.
Get any Board of Zoning Appeals, Plan Commission or Appearance Review Commission approval first.
Make sure each contractor, or you as a homeowner, is registered in OpenGov.
Choose the matching OpenGov application and upload the scope of work or proposal, plans and any engineering documents.
You receive an approximate review time; follow comments and status in the portal.
When approved you are told the total due; pay online or at Village Hall and download or collect the permit.
Phone 847-719-7484 with the permit number at least 24 hours ahead.
Review, corrections and what causes delay
Applications are reviewed in the order received, and nearly every submission gets at least one plan review. The department’s annual report in the February 2, 2026 Village Board packet describes a standard turnaround of three weeks, which staff beat for most of the year, with outside firms brought in for extra plan review and inspection when needed. Times stretch with project size, the season and any engineering review. A missing scope of work, an unregistered contractor or a zoning or appearance approval still pending will hold a permit back.
Inspections and certificates in Deerfield
Inspections are booked by phone with the Building Division at 847-719-7484. The village asks for at least 24 hours’ notice and recommends 24 to 48 hours to get the time slot you need; have the permit number ready, and do not leave requests on voicemail.
Want this handled start to finish?
Get a free quote →- Plumbing inspections are separate appointments, held Tuesday, Wednesday and Thursday mornings from 9 to 11:30 a.m. and taken in the order received.
- On site: someone who knows the permit and code requirements must meet the inspector, with the permit card posted and the approved plans available.
- Cancellations: free up to 30 minutes before the appointment; if no one is there within 15 minutes, the inspector leaves.
- Fees: a failed inspection, a no-show or a late cancellation can cost $100, payable before another inspection is scheduled.
- Remodels and sewers: smoke alarms must be in place at the rough inspection for kitchen and bath remodels, and a camera is required at backfill and sewer repair inspections.
Building permit and inspection records can be requested under FOIA.
Illinois building code in Deerfield
Deerfield enforces the 2024 International Codes and 2023 National Electrical Code adopted by Ordinance O-26-03 for applications submitted after March 1, 2026. FEMA’s Community Status Book lists the Village of Deerfield (community 170361, Cook and Lake counties) as participating in the National Flood Insurance Program, with a current flood map dated September 18, 2013; it joined the Community Rating System on October 1, 1995 and has been class 6, a 20% flood insurance discount, since May 1, 2008.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Deerfield building permit FAQs
How much does a building permit cost in Deerfield?
Most work is $19 per $1,000 of estimated construction cost plus a residential plan review fee of $50 to $150; new one- and two-family homes are $0.75 per square foot.
Do I need a permit to replace my water heater or furnace?
Not for an in-kind replacement or repair, according to the village’s permit infographic. Installing a new boiler or new or relocated air conditioning does need one.
Do I need a permit for a kitchen or bathroom remodel?
Yes, even for cosmetic in-kind replacement; smoke alarms must be installed by the rough inspection.
Can I do my own plumbing or electrical work?
Yes, after registering as a homeowner; homeowners may do plumbing, roofing, electrical, general, concrete and excavation work, but not irrigation RPZ devices.
What happens if I start without a permit?
The penalty is twice the base permit fee, at least $300 and no more than $1,000.
How do I schedule an inspection?
Call 847-719-7484 at least 24 hours ahead with your permit number; plumbing inspections run Tuesday to Thursday mornings.
Inspections are where schedules slip.
Get a free quote →Deerfield permit search and official resources
Applicants follow permits filed in OpenGov from their portal account; paper-based permits can be checked with the Building Division at 847-719-7484. Older building permits and land-use records are requested under the Freedom of Information Act, using the village’s online request form or the printable request form on the Building & Code Enforcement Division page.
- Community Development (Building & Planning)
- Building & Code Enforcement Division
- Permit applications and forms
- Permit regulations and guidelines
- 2026 fee schedule
- “When do I need a permit?” infographic
- Building Department inspection policy
- Work without permit regulations
- Building permit FAQs
- Village Board packet, February 2, 2026 (minutes adopting the 2024 codes)
- FEMA Community Status Book, Illinois
- Illinois Capital Development Board
- Illinois Department of Public Health – Plumbing
Simplify Deerfield permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Deerfield sooner?
Let Alliance prepare, file, and track your Deerfield permits while your crew stays on the job.
More Illinois permitting guides
Lake County
Read guide →Fox Lake
Read guide →Grayslake
Read guide →DeKalb Building Permit Guide
Read guide →DeKalb County Building Permit Guide
Read guide →Des Plaines Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Deerfield permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.