In Bureau County, the Planning & Zoning Department, Room B-5 of the courthouse at 700 South Main Street, Princeton (815-875-1631), issues building permits under the county zoning, floodplain and subdivision ordinances. It covers unincorporated land and the 14 incorporated towns that have no zoning of their own; nine others, including Princeton and Spring Valley, run their own. Bureau County has not adopted a building code, so its three inspections check zoning, not construction, and since June 1, 2026 a permit costs $30 for the first $5,000 of construction cost plus $3 for each additional $1,000.
What requires a building permit in Bureau County?
The county requires a building permit from its Zoning Enforcing Officer before most construction starts where its zoning ordinance applies. The department’s own list for homes covers new houses, additions, decks, porches and patios, detached buildings including sheds of 144 square feet or more, and above- and below-ground pools. A structure on skids needs a permit just like one on a foundation, and most signs need one too.
Permit needed
- Dwellings, additions, garages and gazebos
- Decks, porches, patios and swimming pools
- Sheds and other storage buildings of 144 square feet or more
- Commercial and industrial buildings
- Mobile homes, towers, small wind systems, and commercial wind, solar and battery projects
- Fences in business or manufacturing districts, or in a corner sight triangle
- Most signs on private property
No permit
- Routine maintenance such as repainting or re-roofing; windows and siding are generally exempt too
- Alterations worth less than $300, or that do not change a building’s outside dimensions
- Sheds and fully enclosed storage buildings under 144 square feet
- Fences in residential districts outside the sight triangle
- Hooking up to a municipal utility
- Agricultural uses, apart from the few exceptions the ordinance lists
In parts of Princeton Township with drainage problems shown on the county map, no permit is issued until the applicant first appears before the Bureau County Planning Commission.
What the county decides and what the state holds
Bureau County has zoned since 1965 and regulates building location, use, flood hazard and subdivision, but it has not adopted a building code, so no county official reviews plans for structural or fire safety. For a new or substantially improved commercial building in a place without a building code, state law (20 ILCS 3105/10.09-1) bars occupancy until the owner hires a qualified inspector who certifies the building against the state-listed codes and files that certificate with the county. The county FAQ still lists the 2006 building code and 2008 electrical code for this; the statute now refers to the current or preceding International Building Code with Illinois energy, accessibility, plumbing and fire rules, so check the edition with the inspector you hire.
Short on time to read all of this?
Get a free quote →Bureau County building department: who handles permitting
The Planning & Zoning Department administers the county zoning ordinance, the Floodplain Ordinance and the Subdivision Ordinance, issues building permits and occupancy certificates, and serves the Zoning Board of Appeals. It keeps records of all zoning and subdivision activity and aerial photographs of the whole county, but it cannot give legal advice or locate property lines.
| Office | Handles | Contact |
|---|---|---|
| Planning & Zoning Department | Building permits, occupancy certificates, zoning, floodplain, subdivisions, ZBA petitions | Courthouse, 700 South Main Street, Room B-5, Princeton, IL 61356; 815-875-1631; zoning@bureaucounty-il.gov; Mon–Fri 8:00 a.m.–4:00 p.m. |
| Bureau County Health Department (Bureau, Putnam & Marshall) | Septic system, water well and geothermal well permits and inspections | bpmhd.org |
| Bureau County Highway Department | Driveway and field entrance, drainage, construction and utility-line permits on county highways | 595 Elm Place, Princeton; 815-875-4477 |
| Supervisor of Assessments | Parcel index numbers (PIN) | 815-875-6478 |
Who permits in each city and village
| Place | Who issues building permits |
|---|---|
| Arlington, Buda, Bureau Junction, Cherry, Dover, Hollowayville, La Moille, Malden, Manlius, Mineral, New Bedford, Ohio, Sheffield and Wyanet | Bureau County Planning & Zoning (no municipal zoning) |
| Dalzell, DePue, Ladd, Neponset, Princeton, Seatonville, Spring Valley, Tiskilwa and Walnut | The city or village itself; the county lists each office on its Municipal Zoning Agencies page, and Princeton has a Building & Zoning Department at 2 S. Main St. |
| Small parts of Annawan and Peru inside the county line | Not named on the county’s lists; ask the county office or the town |
| Unincorporated land, including Kasbeer, Langley, Limerick, Milo, Normandy, Providence, Thomas, Van Orin, Whitefield, Yorktown and Zearing | Bureau County Planning & Zoning |
The county notes that several of the towns with their own zoning have also adopted building codes. To learn which rules cover a parcel, call the department with the PIN from the upper right corner of the tax bill.
Not sure this scope needs a permit?
Get a free quote →Bureau County permit types
Applications are made to the Zoning Enforcing Officer on the department’s forms. They name the applicant, owner, architect, engineer and contractor, describe the site by lot, block and subdivision or by township and section, and give the type of structure, its use and the zoning district. A plat of survey by a registered land surveyor must show the site, existing and proposed buildings, easements, streets, parking, driveways, yards and any highway access limits, plus abutting buildings within 40 feet.
Residential permits
- New houses and additions pay the building permit fee on construction cost and need an occupancy certificate, applied for at the same time as the permit.
- Accessory buildings built with a new house are covered by the house permit; a shed added later needs its own permit once it reaches 144 square feet.
- Mobile homes have a flat $100 permit.
- Fences: no permit in residential districts, but the ordinance still limits height, materials, setbacks and sight-triangle placement, which the county’s fencing page explains.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and industrial buildings take the same construction-cost permit, and the owner arranges the state-required third-party inspection before occupancy. Commercial wind and solar facilities pay $5,000 per megawatt for the building permit, capped at $75,000, and battery storage pays $5,000 per megawatt up to $50,000; each also needs a conditional use permit with its own capped fee. Cell towers are $25 per foot of height, and adding equipment to an existing tower is a flat $1,200.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. The five-member Zoning Board of Appeals decides variances and appeals of the Zoning Administrator’s rulings; for rezonings and conditional uses it recommends and the County Board decides. Filing after construction has started costs several times more.
- Septic and well. Where there is no public sewer, the sewage disposal plan must be approved by the Bureau County Health Department or the Illinois Department of Public Health, and the Health Department’s septic, well or zoning evaluation costs are the applicant’s.
- Floodplain. Development in the 100-year floodplain is tightly limited by the county Floodplain Ordinance, and if a site’s status is uncertain the applicant must supply certified elevations.
- Subdivision. Dividing land under county zoning goes through the Subdivision Ordinance (1969, revised 1979), with a $225 preliminary plat fee.
- Driveways. A new entrance onto a county highway needs the Highway Department’s driveway and field entrance permit.
Rather talk it over?
Call 1-855-478-4290 →Bureau County permit costs and fees
Fees are set by the County Board’s Resolution Fixing Zoning Application and Building Permit Fees, passed May 12, 2026 and effective June 1, 2026. It replaced the resolution of October 9, 2018 and brought wind, solar and storage fees into line with Public Act 104-0458.
| Item | Fee |
|---|---|
| Building permit | $30 for the first $5,000 of total construction cost (materials and labor), plus $3 for each additional $1,000 |
| Mobile home permit | $100 |
| Small wind energy system | $250 per tower |
| Cell and other commercial towers | $25 per foot of height; co-location or equipment replacement $1,200 |
| Commercial wind or solar facility | $5,000 per megawatt, maximum $75,000, plus county expenses above that |
| Energy storage system | $5,000 per megawatt, maximum $50,000 |
| Permit issued after excavation, foundation or construction has begun | Double the fee |
| Rezoning or conditional use (filed before construction) | $225; $700 for a special hearing |
| Variance or appeal (filed before construction) | $125; $350 for a special hearing |
| Rezoning or conditional use / variance or appeal (filed after construction) | $725 / $625; $1,200 / $750 for a special hearing |
| Preliminary plat / final plat | $225 / $225 plus $10 per lot |
Worked example from the resolution: a house with a construction cost of $250,000 pays $30 for the first $5,000 plus 245 × $3 for the remaining $245,000, or $765. Build the foundation first and the same permit costs $1,530. Petitioners also pay the actual hearing costs: court reporter and transcript, the Bureau County Soil and Water Conservation District’s Natural Resource Information Report, newspaper notice and mailed notices.
Trade permits and who may pull them
With no county building code, the county’s pages list no electrical, plumbing or mechanical permits and no contractor registration. The trade rules that still apply come from the state or, inside the nine towns with their own zoning, from that town.
Rather not deal with the Bureau County building department?
Get a free quote →- Plumbing: plumbing work follows the Illinois Plumbing Code and must be done by a plumber licensed by the Illinois Department of Public Health.
- Roofing: roofers need a state license from the Department of Financial and Professional Regulation, even though a re-roof needs no county permit.
- Septic and wells: the Health Department reviews plans, issues private sewage permits and inspects systems before use; wells and geothermal wells also need its permit.
- Commercial buildings: the qualified inspector the owner hires under state law, not the county, certifies the building’s electrical, plumbing and building work.
How to apply for a Bureau County building permit
Call with your PIN; if the parcel is in one of the nine towns with their own zoning, apply there instead.
Ask whether the site is in the 100-year floodplain or a Princeton Township drainage area that needs Planning Commission review first.
Without public sewer and water, get the Health Department evaluation or permits.
A registered land surveyor prepares the plat showing buildings, yards, driveways and neighbors within 40 feet.
Submit the application, apply for the occupancy certificate at the same time, and pay the fee before any excavation to avoid the double fee.
Mark the building corners and property lines with stakes or paint for the first inspection.
Review, corrections and what causes delay
The most common hold-ups are a parcel that turns out to be under a town’s zoning, a site in the floodplain without certified elevations, and a lot without an approved sewage plan. If work is not substantially started within 90 days, a new permit at the current fee is needed, and the officer can revoke a permit when the building is not finished within two years or no real progress is being made.
Inspections and certificates in Bureau County
The department usually makes three zoning compliance inspections: a site visit at the stake-out stage, a second at the footings, and a final when the project is done. These check setbacks, use and floodplain rules, not construction quality; the county says plainly that they are not building inspections. Owners do not need to be present unless the department asks.
A certificate of occupancy is required before a new building is used, before an existing building or land changes to a different use classification, and before a nonconforming use changes. For a new building it is issued within a reasonable time after the final inspection, and records of all certificates are kept in the Zoning Enforcing Officer’s office and are open to public inspection.
Want this handled start to finish?
Get a free quote →Illinois building code in Bureau County
FEMA’s Community Status Book lists unincorporated Bureau County (community 170729) as participating in the National Flood Insurance Program, with flood maps effective August 2, 2011. The county row covers unincorporated land only.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Bureau County permit search and official resources
To look up a past permit, occupancy certificate, zoning decision or subdivision plat, contact the Planning & Zoning Department, which keeps files on all zoning and subdivision activity it oversees, including plats inside villages without their own zoning. It can copy plats on sheets up to 11 by 17 inches. Deeds come from the County Clerk and Recorder, and tax questions go to the Supervisor of Assessments.
- Bureau County Planning & Zoning Department
- Frequently asked zoning questions
- Municipal zoning agencies in Bureau County
- Zoning and building permit fee resolution, May 12, 2026
- Bureau County Zoning Ordinance by article
- Article XI: permits and certificates of occupancy
- Flood Damage Prevention Ordinance
- Subdivision ordinance
- Fencing regulations
- Bureau County Highway Department permits
- Health Department sewage program
Inspections are where schedules slip.
Get a free quote →Bureau County building permit FAQs
Does Bureau County have a building code?
No. The county issues building permits under zoning, floodplain and subdivision rules only; some towns with their own zoning have adopted codes.
How much is a county building permit?
$30 for the first $5,000 of construction cost plus $3 per additional $1,000, so a $250,000 house is $765; it doubles if work starts first.
Do I need a permit for a shed?
Yes if it is 144 square feet or more, even on skids; smaller enclosed storage buildings are exempt.
Does a fence need a permit?
Not in a residential district unless it is in a corner sight triangle; fences in business or manufacturing districts do need one.
Does the county permit in Princeton?
No. Princeton, Spring Valley, DePue, Ladd, Walnut, Tiskilwa, Neponset, Seatonville and Dalzell have their own zoning and permit offices.
Who handles septic permits?
The Bureau County Health Department, which reviews the plan, issues the permit and inspects the system before use.
How long is a permit good for?
Work must be substantially started within 90 days, and the permit can be revoked if the building is not finished within two years.
Simplify Bureau County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Bureau County sooner?
Let Alliance prepare, file, and track your Bureau County permits while your crew stays on the job.
More Illinois permitting guides
Henry County
Read guide →Lee County
Read guide →LaSalle County
Read guide →Burr Ridge Building Permit Guide
Read guide →Calumet City Building Permit Guide
Read guide →Canton Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Bureau County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.