Skip to main content
Municipal GuideFloridaMiami Shores · Miami-Dade County

Miami Shores, Florida Building Permit Guide

How to get a building permit in Miami Shores, FL: the Village Building Department, online filing, review times and inspection scheduling.

Authority: Miami Shores Village Building DepartmentCode: Florida Building Code, 8th Edition (2023)Phone: 305-795-2204
Authority
Miami Shores Village Building Department10050 NE 2 Avenue, Miami Shores, FL 33138
Apply Online
Citizen Self-Service (CSS)Online permit submission and status
Inspections
Online inspection requestsSubmit by 3:30 p.m.
Code
FBC 8th Ed. (2023)Effective December 31, 2023

Miami Shores Village Building Department is the municipal building-permit authority. It provides customer service, plan review and inspections and administers the Village's online Citizen Self-Service portal.

What requires a permit in Miami Shores?

The Village states that permits are required for construction, alteration, conversion, repair, enlargement, movement and demolition of buildings and structures. Its FAQ identifies new residential and commercial construction, additions and remodeling, re-roofing, solar work, electrical upgrades, gas testing, fire sprinklers, signs, pools, decks, patio covers and carports among common permit scopes.

The Village lists some work that does not need a building permit, such as interior cosmetic work like cabinets and flooring, and sheds under 120 square feet with no electricity. Concrete work is also on that list, but driveways need a right-of-way permit from Public Works.

Short on time to read all of this?

Get a free quote →

Who handles permits in Miami Shores?

Miami Shores permitting contact
DetailInformation
Office10050 NE 2 Ave, Miami Shores, FL 33138
Phone305-795-2204
HoursMonday to Friday, 8:30 a.m. to 4:00 p.m.

Miami Shores permit types and local forms

The Building Department publishes a general permit application and project-specific packages for residential additions, roofing, emergency mechanical work, docks and seawalls, private-provider projects and other scopes.

The Building Department can keep a contractor’s licence and insurance information on file for a $50 initial fee and a $30 annual update fee.

Permit fees and payment

In Miami Shores the permit fee is paid at submittal. The amount depends on the Village fee schedule and the project scope.

A re-inspection after a second rejection may carry an $85 re-inspection fee.

Trade permits and inspection days

Inspection days differ by trade. Building, roofing and electrical inspections are available Monday through Friday, plumbing inspections Monday through Thursday, and mechanical inspections only on Mondays and Wednesdays.

Not sure this scope needs a permit?

Get a free quote →

Application and correction-package requirements

All Miami Shores permit applications must include 2 copies of the submittal documents. Applicants set up an EnerGov Citizen Self-Service account and apply through the portal; the office also receives submittals Monday to Friday, 8:30 a.m. to 4:00 p.m.

The Village has a specific correction rule: corrections are not accepted while any plan-review disciplines remain pending, and partial correction packages are not accepted. Comments from all disapproved trades must be addressed and submitted together.

How to apply: 6-step Miami Shores process

1. Confirm Village jurisdiction and approvals

Check that the parcel is inside Miami Shores Village and whether the job also needs a Public Works right-of-way permit.

2. Select the correct permit and trades

Match the application package to the building, roofing, electrical, plumbing, mechanical and specialty work involved.

3. Prepare the document package

Include the required application and 2 copies of the supporting documents for the permit type.

4. Submit through CSS

Apply in Citizen Self-Service and pay the permit fee at submittal.

5. Resolve all review comments together

Wait until pending disciplines finish and submit one coordinated correction package addressing every disapproved trade comment.

6. Schedule inspections and close out

Request inspections online before the cutoff, complete all trade finals and obtain the required completion or occupancy approval.

Rather talk it over?

Call 1-855-478-4290 →

Miami Shores inspections

Inspection requests submitted before 3:30 p.m. are scheduled for the following available business day for that trade. Inspectors work in the field from 8:00 a.m. to 5:00 p.m.

The permit card and approved plans must be available at the site. Work must be accessible and exposed for inspection. Re-roof inspections require a ladder to be set and secured by the applicant.

Review times and permit life

The Village says most permits are processed within 5 to 10 business days. Residential addition, remodel and new-home applications have up to 15 business days for a completeness check, then 10 business days for plan review. Commercial permits have a 15-business-day review period.

Rather not deal with the building department?

Get a free quote →

Permits are valid for 180 days, and each approved inspection extends the permit for another 180 days. A permit with no approved inspection for 180 days becomes invalid.

Florida building code

The Florida Building Code, 8th Edition (2023), has applied statewide since 31 December 2023; the Florida Building Commission has proposed the 9th Edition (2026) to take effect on 31 December 2026. Florida permit rules

Official Miami Shores permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Miami Shores permit FAQs

Can permits be submitted online?

Yes. The Village's Citizen Self-Service portal accepts permit applications and supporting documents and can be used to check plan-review status.

Can I submit one correction while another trade is still pending?

No. Miami Shores states that corrections are not accepted while disciplines remain pending and that all disapproved trade comments must be addressed together.

When is the inspection cutoff?

Submit the request by 3:30 p.m. for the next available business day for that trade.

Simplify Miami Shores permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →

Alliance Permitting is a permit documentation and submission company in Florida. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Miami Shores sooner?

Let Alliance prepare, file, and track your Miami Shores permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Miami Shores permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.