Inside the City of Dana Point, building, electrical, plumbing and mechanical permits and certificates of occupancy come from the city’s Building and Safety Division at 33282 Golden Lantern, Suite 209 (949-248-3564), where Jess McCloskey is the Building Official. Every application is filed electronically in eTRAKiT, the city requires permits for almost all construction, including kitchen and bath remodels and deck and guardrail repairs, and its local exemption list is limited: retaining walls are exempt only up to 3 feet and masonry fences only up to 36 inches.
What requires a building permit in Dana Point?
Dana Point requires permits for almost all construction: bathroom and kitchen renovations, deck and guardrail repairs and replacements, additions, alterations and any change to a home’s structure. The exemptions in Municipal Code section 8.02.010, restated in the city’s handout for the 2025 code cycle, are narrower than the model code list in several places.
Exempt (city list)
- One-story sheds, playhouses and portable shade structures up to 120 square feet that meet zoning setbacks and height limits
- Masonry or concrete fences up to 36 inches, and other fences up to 6 feet
- Retaining walls up to 3 feet with no surcharge
- Decks, platforms, walkways and driveways up to 30 inches above grade
- Painting, tile and carpet with no electrical, plumbing or mechanical work
- Above-ground prefabricated pools under 18 inches deep
- Antennas and flagpoles up to 12 feet
Still needs a permit
- Any exempt item on a coastal bluff, in the Flood Plain Overlay District or an environmentally sensitive area
- Any exempt item that needs a discretionary Planning approval
- Fences and walls under 6 feet that are a project condition, a guard or a pool barrier
- Finish work that is part of a code enforcement case
- The electrical connection for a plug-in pool pump, filter or heater
Separate electrical, plumbing and mechanical permits apply to otherwise exempt items unless those trades are exempt too.
What Dana Point decides and what the state holds
The city sets its own permit exemptions, fees, design values and fire sprinkler rules, administers its Local Coastal Program and its zoning, and requires its own proxy forms for anyone pulling a permit for someone else. The state licenses contractors.
Dana Point building department: who handles permitting
The Building and Safety Division, part of Community Development, is responsible for building standards for the design, construction, use and occupancy of every building in Dana Point. It works with the Planning Division, Engineering Services in Public Works and the Orange County Fire Authority (OCFA). Jonathan Lightfoot is the Director of Community Development.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building and Safety Division, 33282 Golden Lantern, Suite 209, Dana Point, CA 92629 |
| Main phone | 949-248-3564; fee questions 949-248-3594 |
| Building Official | Jess McCloskey, 949-248-3545 |
| Lobby hours | Monday to Thursday 7:30 a.m. to 5:30 p.m.; Friday 7:30 a.m. to 4:30 p.m. |
| Permit counter | Walk-ins Monday to Friday, 8 a.m. to 3:30 p.m. |
| Inspections | Automated line 949-248-3590; text scheduling 888-308-3015 |
| Planning / coastal permits | 949-248-3564, planning@danapoint.org; coastal questions 949-248-3568 |
| Engineering Services | 949-248-3554 |
Dana Point permit types
All permit applications are filed electronically in the eTRAKiT portal. Large submittals, such as new houses and new commercial buildings, must be pre-screened before they are submitted. The city has warned of fraudulent emails asking eTRAKiT users to pay invoices by wire transfer: it never asks for or accepts wire payments, and real messages come only from danapoint.org addresses.
Residential permits
- Kitchens, baths and windows. The city posts alteration requirements and design guides for kitchens and bathrooms, and a residential window replacement handout.
- Decks and guardrails. Repairs and replacements need permits; there are handouts for deck repair and glass guardrails, and city standard guardrail details.
- Walls. City standard block wall and retaining wall plans on 11 by 17 sheets cover simple walls.
- Fire sprinklers. Under the city’s sprinkler handout, written for the 2022 code cycle, new homes and attached garages must be sprinklered, and existing homes must be sprinklered when an addition takes the floor area to 5,000 square feet or more, when the building already has sprinklers, or for an ADU when the main home is sprinklered. Sprinkler plans go to the OCFA first, and the city will not issue the permit without OCFA approval.
- Solar. Solar systems are priced at $400 up to 5 kW and $500 above that, with a solar electrical load calculation worksheet in the handouts.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Tenant improvements follow the city’s tenant improvement submittal requirements and commercial kitchen and food service water quality handouts; commercial projects use the OCFA commercial pre-screening form. A certificate of occupancy is needed for a change in use or occupancy type or when a business does tenant improvements that need a permit, but not for a like-for-like tenant, a change of ownership or a name change. A certificate for a new tenant without improvements costs $132.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Coastal development permit. All development in the city’s coastal zone, as defined in its Local Coastal Program, needs a coastal development permit unless specifically exempted; call Planning at 949-248-3568.
- Other planning approvals. Site development permits, conditional use permits, variances and administrative modifications are filed through eTRAKiT’s Projects portal, but applicants must contact Planning before submitting. Planners meet Monday to Thursday 7:30 a.m. to 5 p.m. and Friday until 4 p.m.
- Engineering. Grading follows Resolution 19-06-04-02, and soils report questions go to Engineering Services. Unless a project is small or the report is waived, foundations must be designed from an approved soils report.
- Fire hazard zones. The handouts include the city’s 2025 fire hazard severity zone map.
Dana Point permit costs and fees
Building fees are a mix of cost-based fees in the city’s Building Schedule of Service Fees, which the fee page says took effect on October 1, 2020, and valuation-based fees, with the value set by the Building Official from the scope on the plans. Staff time is billed at blended rates of $210 an hour for plan check and $176 an hour for inspection.
| Item | Fee |
|---|---|
| Permit issuance (each permit) / plan check filing | $25 / $90 |
| Stand-alone mechanical, electrical or plumbing permit issuance | $25 plus item fees |
| Trade plan check (minimum one hour) | $199 per hour |
| Electrical service up to 400 amps | $66 |
| Solar PV up to 5 kW / over 5 kW | $400 / $500 |
| Furnace, with ducts and vents | $22 |
| Plumbing fixture / building sewer | $33 / $22 |
| Water heater / tankless water heater | $66 / $76 |
| Re-inspection, per discipline | $197 |
| Expired building permit renewal | $100 |
| Certificate of occupancy, new tenant without improvements | $132 |
| Building Official time | $217 per hour |
Rather talk it over?
Call 1-855-478-4290 →Several waivers apply. City fees for ADA alterations for disabled veterans are waived, as are city development and building permit fees for deed-restricted housing affordable to extremely low, very low and low income households, with mixed-income projects discounted in proportion. Owners who live in a home and do maintenance work on it, themselves or with licensed contractors, pay only the $25 base permit fee for stand-alone trade permits, with no item fees, and no trade plan check fee.
To be processed the same day, an application must be approved by every department before 5 p.m. Monday to Thursday or 4 p.m. on Friday; later approvals roll to the next business day. Planning fees follow the Planning Division’s own schedule.
Trade permits and who may pull them
Building and Safety issues electrical, plumbing and mechanical permits, priced by item from the service fee schedule: for example $66 for an electrical service up to 400 amps, $33 per plumbing fixture and $66 for a water heater. Every plan submittal must include plumbing, mechanical and electrical plans. They are usually prescriptive drawings that need no engineer, but the city’s MEP thresholds handout calls for a design by a licensed professional for electrical services of 400 amps or more, standby generators over 8 kW, natural gas systems over 500,000 BTU and complex systems, and for calculations with solar systems over 10 kW or added equipment circuits, which an electrical contractor may provide. Trade plan check is billed by the hour.
Permits go to a California licensed contractor or to the owner of record. Contractors must hold a valid state license and show workers’ compensation coverage if they have employees. A homeowner may take out a permit for a one- or two-family home and its accessory buildings only if they live there or intend to, do the work themselves and sign that no one will be employed in a way that falls under workers’ compensation law; identity is checked at the counter. Dana Point does not accept letters of authorization: an agent must carry the city’s Owner-Builder Proxy or Contractor Proxy form, with ID and, for contractors, both sides of the signed license card. The city has no business license, so contractors from outside the city need only their permits.
How to apply for a Dana Point building permit
Ask Planning whether the site is in the coastal zone, on a bluff or in the flood plain overlay, and whether a discretionary permit comes first.
New houses and new commercial buildings are pre-screened before submittal.
Follow the city’s account guide and videos to register and submit.
Use the residential or tenant improvement submittal requirements, the city’s 11 by 17 plan formats and the proxy, owner-builder or contractor forms.
Answer corrections from Building, Planning, Engineering and the OCFA.
Pay through the portal; never by wire transfer.
Rather not deal with the building department?
Get a free quote →Review, corrections and what causes delay
Minor projects and revisions that take no more than 15 minutes to review can get over-the-counter plan review, now handled online through eTRAKiT rather than in person; paper submittals are not accepted. The building page still lists over-the-counter review hours on Tuesday and Thursday, 8 a.m. to noon and 1 to 3:30 p.m. A fire sprinkler permit cannot be issued without OCFA-approved plans, and discretionary Planning applications are not reviewed until all their fees are paid.
Inspections in Dana Point
Book inspections through the automated line at 949-248-3590 or by text through SelecTXT at 888-308-3015, which can schedule, reschedule and cancel. Text cancellations after 4 p.m. for the next day, and same-day cancellations, are not allowed; call 949-248-3564 instead. Comments such as a gate code or a morning or afternoon preference can be added, but times are not guaranteed. The daily inspection schedule is posted as a PDF on the Building and Safety page.
Inspectors check structural work, life safety, energy, accessibility and the electrical, plumbing and mechanical systems at set stages, and the residential final checklist lists what is needed to close a permit. A re-inspection costs $197 per discipline. Deputy inspectors for special inspections must register with the city.
Work done without permits is resolved by a special investigation: the owner of record takes out the investigation permit and books a site visit, then submits plans. There is no grandfather clause, and a foreclosure, short sale, flip or probate sale does not release a new owner, so check permit history before escrow closes.
California building code in Dana Point
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Dana Point applies the 2025 codes from January 1, 2026 with its own amendments in Municipal Code Title 8; section 8.02.010 holds its permit exemptions. Its design values are climate zone 6, a 110 mph basic wind speed, seismic design category D or E (or from a site soils report) and a rain load of 3 inches per hour; without a soils report, foundations are designed for 1,500 psf bearing and 100 psf lateral pressure.
Want this handled start to finish?
Get a free quote →Dana Point building permit FAQs
Who issues building permits in Dana Point?
The city’s Building and Safety Division at 33282 Golden Lantern, Suite 209; coastal development permits come from the Planning Division.
Do I need a permit for a block wall or retaining wall?
Yes for a masonry or concrete fence over 36 inches or a retaining wall over 3 feet; other fences are exempt up to 6 feet unless they are a pool barrier, guard or project condition.
Do I need a coastal development permit?
Yes for development in the city’s coastal zone unless the project is specifically exempted; ask Planning at 949-248-3568.
Can someone pull a permit for me with a letter?
No. Dana Point accepts only its Owner-Builder Proxy or Contractor Proxy forms, not letters of authorization.
How do I schedule an inspection?
Call 949-248-3590 or text 888-308-3015; late or same-day cancellations must be phoned in to 949-248-3564.
Do I need a city business license?
No. Dana Point has no business license; outside contractors need only their permits.
Will my addition need fire sprinklers?
Under the city’s sprinkler handout, yes if the home already has sprinklers or the addition brings the total floor area to 5,000 square feet or more; the Building Official reviews each scope at plan check.
Can I apply on paper?
No. All permit applications go through eTRAKiT, including over-the-counter reviews.
Dana Point permit search and official resources
Permit records and plans are kept by the Permit Center; use the city’s record request form for permit histories and copies.
Inspections are where schedules slip.
Get a free quote →- Dana Point Building & Safety
- eTRAKiT permit portal
- Applications and handouts
- Work exempt from building permits (B107)
- Help for homeowners
- Plan review services
- Fire sprinkler requirements (B008)
- MEP plan thresholds (B035)
- Inspection Center and text scheduling
- Building staff directory
- Schedule of service fees
- Building schedule of service fees
- Development applications and coastal development permits
- Business registration
- FEMA Community Status Book, California
Dana Point takes part in the National Flood Insurance Program; its current flood maps are dated March 21, 2019.
Simplify Dana Point permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Dana Point sooner?
Let Alliance prepare, file, and track your Dana Point permits while your crew stays on the job.
More California permitting guides
Orange County
Read guide →Fountain Valley
Read guide →Fullerton
Read guide →Danville Building Permit Guide
Read guide →Davis Building Permit Guide
Read guide →Del Norte County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Dana Point permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.