Lindon’s Building & Inspection division, part of Community Development at the City Center, reviews plans, issues building permits and inspects work inside the city, and applications go in online through CivicReview. Under the 2026-2027 fee schedule a new house pays a $500 application fee, a permit fee set from ICC valuation data and the 1997 UBC fee table, and a plan review fee of 25% of that permit fee.
What requires a building permit in Lindon?
Lindon issues building permits for new construction of every kind and for work on existing buildings. The categories in its 2026-2027 fee schedule show what the City permits:
Residential
- New single-family homes, townhomes, duplexes and detached ADUs
- Additions, remodels and basement finishes
- Pools, detached garages and sheds
- Retaining walls and solar
- Furnace or air-conditioner replacement, water heaters and service panel replacement
- Re-roofs and demolition
Commercial
- New multi-family and commercial buildings
- Tenant improvements
- Signs (wall, monument, pole and billboard)
- Fire sprinkler and alarm systems, reviewed under Orem’s fee schedule
A building may not be occupied until the building official has inspected it and issued a certificate of occupancy. Work begun or finished without a required permit pays a double permit fee under City Code 15.04.030.
Who issues building permits in Lindon?
Lindon’s Building Department, within Community Development, handles permits and plan review for new construction and carries out the on-site inspections; its building inspector doubles as the City’s code enforcement officer. Bryce McConkie is the Chief Building Official. The same department runs planning and zoning, and the Planning Commission approves commercial site plans before the building permit. Public Works inspects sediment control, water, sewer, irrigation and street work, and Orem Fire Service provides Lindon’s fire services and reviews fire sprinkler and alarm plans under Orem’s policies and fee schedule.
Unincorporated land next to Lindon falls to Utah County Community Development, which serves only areas outside city limits.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Community Development, Lindon City Center, 100 North State Street, Lindon, UT 84042 |
| Phone | 801-785-7687 |
| buildingdept@lindoncity.org | |
| Chief Building Official | Bryce McConkie |
| Apply | Building Permit Application on CivicReview (online) |
| Public Works (site and utility inspections) | 801-796-7954 |
| Orem Fire Service | 801-229-7070 |
Lindon permit applications and forms
Since March 1, 2021 every Lindon building permit has been submitted digitally through the online application, which the City hosts on CivicReview alongside its land use application, fence permit modification request and appeal application.
Documents the Building & Inspection page provides:
- Residential, commercial, remodel/basement finish and tenant improvement plan submittal checklists.
- The Residential (Single-Family Home) Inspection Checklist.
- The Notice to Builders and General Contractors on keeping streets and sidewalks clear, which builders sign.
- The State of Utah Owner/Builder Certification Form and Agreement, for owners doing their own work.
- A Commercial Building Owner Acknowledgement for Tenant Improvement.
- The Accessory Apartment Requirements Handbook. Owner-occupied accessory apartments are allowed in every residential zone after staff review of the plans and a City public notice.
Lindon permit costs and fees
Fees come from Lindon’s 2026-2027 Fee Schedule, approved with the City budget. The building permit fee is worked out in two steps: the project is valued with the ICC Building Valuation Data published the previous February (houses, townhomes and duplexes at 95% of that figure), and the fee is then read from Table 1-A of the 1997 Uniform Building Code. Fire sprinklers and alarms are left out of both the valuation and the permit fee.
| Item | Fee |
|---|---|
| Application fee: new house, townhome, duplex or detached ADU | $500 |
| Application fee: other residential (pools, additions, garages, sheds, retaining walls, solar) | $100 |
| Application fee: new multi-family, commercial, tenant improvement | The full plan review fee |
| Plan review | 25% of the permit fee residential, 65% commercial |
| Additional plan review | $85 an hour, 1-hour minimum |
| State fee | 1% of the building permit fee |
| Furnace or A/C, water heater, or service panel replacement | $85 each |
| Re-roof | $145 |
| Re-inspection | $85 an hour, 1-hour minimum |
| Permit reinstatement | $100 |
| Planning administrative fee, residential | $50 |
Not sure this scope needs a permit?
Get a free quote →The City’s older residential checklist still names a $100 application deposit for every residential permit; the adopted schedule sets $500 for a new house and $100 for other residential work.
| Item | Fee |
|---|---|
| Park, recreation and trails impact (detached house) | $4,500 |
| Sewer impact (3/4- or 1-inch meter) | $1,809 |
| Water impact (1-inch meter) | $1,467 |
| Storm water impact (per equivalent residential unit) | $799 |
| Police / fire impact | $162 / $152 |
| Culinary meter installation, 1-inch | $650 |
| Secondary water meter, 3/4-inch (lots under 10,000 sq ft) or 1-inch | $650 |
| Sewer / water inspection | $70 each |
| Public improvement repair assurance, refundable | $5,000 (townhouse or duplex $2,500) |
New lots must also turn in irrigation water shares or pay a fee in lieu of 95% of market value, which the City reviews quarterly. With the North Union and Provo Bench canal companies dissolved, the Council adopted Ordinance 2026-15-O and Resolution 2026-30-R on September 8, 2026: a residential lot now needs one Provo River Water Users Company Alpine District Full share per net acre (half a share in nonresidential zones), rounded to the nearest tenth, and the fee schedule lists the accepted equivalents, such as 2 Alpine District Late shares, 5 Deer Creek Storage shares or 3 Pleasant Grove Irrigation Company shares.
Electrical, plumbing and mechanical permits in Lindon
Lindon’s Building Department permits and inspects electrical, plumbing, mechanical and gas work itself. On a new house these are inspected as part of the building permit (rough electrical, mechanical and plumbing, often together in a 4-way inspection, plus under-slab work and two gas inspections, the line and pressure test and then the meter). Stand-alone replacements have flat fees: $85 for a furnace or air conditioner, a water heater or a service panel.
Rather talk it over?
Call 1-855-478-4290 →All new construction must bring its electrical service in underground unless the Chief Building Inspector and Public Works Director find that impractical. Request temporary power from Rocky Mountain Power (888-221-7070); Rocky Mountain Power also inspects all underground service. Fire sprinkler and fire alarm plans are reviewed under the Orem City fee schedule through Orem Fire Service.
Application documents and plan review
The checklists warn that a submittal missing any listed item is incomplete and will not be reviewed.
New house
- Site plan to engineering scale with setbacks, lot-corner, foundation, garage slab and curb elevations, contours on a sloped lot, retaining walls, sewer and water locations and easements
- SWPPP where the disturbed area or location requires it (check with Public Works Storm Water)
- Plans at 1/4 inch to 1 foot with wet signatures and engineer’s stamps
- Elevations, roof plan, cross sections, foundation and steel details
- Framing, beam and header sizes; stair details
- Floor plans with door and window sizes; electrical panel, meter size and circuits; plumbing fixtures and water line; furnace, gas appliances and gas line diagram
- Energy code compliance report and a site-specific soils or excavation observation report
Commercial
- Site plan with construction type, area, height, occupancy and occupant load
- Site plan approved by the Planning Commission
- Foundation, floor, elevation and structural framing plans
- Truss layout, HVAC plan and plumbing, gas and interceptor sizing
- Electrical plan with energy compliance documents
- Complete fire sprinkler and alarm plans
- Wet-stamped structural calculations and ADA access details
Remodels and basement finishes need only floor plans with labeled rooms, door and window sizes, the electrical layout and the furnace location. Lindon does not publish a plan review time.
Rather not deal with the building department?
Get a free quote →How to apply for a Lindon building permit: 6 steps
Commercial projects need a Planning Commission-approved site plan; check the zone on Lindon’s interactive zoning map.
Use the residential, commercial, remodel or tenant improvement checklist for your project.
Fill in the Building Permit Application and upload the digital plans and reports.
$500 for a new house, $100 for other residential work, or the full plan review fee for commercial work.
Revise plans as the building official asks; extra review time is billed at $85 an hour.
Pay the permit, impact and bond amounts, sign the Notice to Builders and schedule each inspection at least 24 hours ahead.
Inspections in Lindon
Every inspection on a new house has to be scheduled at least 24 hours ahead; contact the Building Department at 801-785-7687 or buildingdept@lindoncity.org, and Public Works at 801-796-7954 for its inspections. The approved stamped plans must be on site, and nothing may be covered before it passes.
| Stage | Inspected by |
|---|---|
| Sediment control (must pass before the footing inspection) | Public Works |
| Building clearance once property pins are set; footing (soil report due 24 hours before); foundation; foundation drain and waterproofing | Building Department |
| Under-slab heating and plumbing; suspended-slab rebar; shear | Building Department |
| Rough framing, electrical, mechanical and plumbing (4-way); insulation; weather barrier; fire-rated drywall nailing | Building Department |
| Temporary and permanent power; gas line pressure test and gas meter | Building Department |
| Water service, sewer lateral, drive approach and sidewalk, pressurized irrigation, land drain, SWPPP | Public Works |
| Final building inspection | Building Department |
Want this handled start to finish?
Get a free quote →Re-inspections cost $85 an hour with a 1-hour minimum. If mud, dirt bridges or building materials are left in the street or on the sidewalk and are not cleared within 24 hours of notice, the City bills the cleanup (at least $250 an hour under the adopted schedule), and no further inspections or certificate of occupancy are issued until it is paid. Occupying a building without a final certificate of occupancy forfeits construction bonds and leads to a notice of noncompliance recorded against the property.
Local Lindon details that matter
Wildfire zone: Lindon adopted a Wildland Urban Interface zone map dated December 1, 2025 (Ordinance 2025-18), and property inside that zone is built under the wildland-urban interface code.
Water shares: development must bring irrigation water shares or pay 95% of their market value, and only shares from the companies listed in the fee schedule are accepted.
Street cuts: each street excavation costs $1,000 per cut or trench, and a refundable public improvement repair assurance protects curbs, gutters and sidewalks during the job.
Underground power: overhead service to a new building is allowed only when the City agrees underground service is impractical.
Utah building code
Utah adopts one construction code for the whole state; cities and counties enforce it, and any local amendments are set by the Legislature. Utah rules
Official Lindon permitting resources
City and state sources:
- Lindon Building & Inspection: checklists and forms
- Lindon Building Permit Application (CivicReview)
- Lindon 2026-2027 Fee Schedule
- Lindon City Council minutes, September 8, 2026 (water share changes)
- Residential Plan Submittal Checklist
- Commercial Plan Submittal Checklist
- Residential (Single-Family Home) Inspection Checklist
- Lindon Wildland Urban Interface information
- Lindon City Code, Chapter 15.04 Administration
- Lindon Community Development directory
- Utah Division of Professional Licensing
Inspections are where schedules slip.
Get a free quote →Lindon building permit FAQs
How much is a building permit for a new house in Lindon?
The permit fee comes from the 1997 UBC fee table applied to 95% of the ICC valuation, plus 25% for plan review and a 1% state fee; the $500 application fee is paid up front. Impact fees for a detached house include $4,500 for parks, $1,809 for sewer and $1,467 for water.
Do I need a permit to replace a furnace, water heater or roof?
Yes. Furnace or air-conditioner, water heater and service panel replacements are $85 each, and a re-roof is $145.
How do I apply?
Online only: complete the Building Permit Application on CivicReview and upload digital plans that match the City’s checklist.
How far ahead do I book inspections?
At least 24 hours. Building inspections go through the Building Department (801-785-7687) and site and utility inspections through Public Works (801-796-7954).
Can I build an accessory apartment?
Yes, in any residential zone if the owner lives on the property; the plans are reviewed by staff and the City sends a public notice before approval.
What if I started work without a permit?
City Code 15.04.030 doubles the permit fee for projects started or finished without a required permit.
Simplify Lindon permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Utah. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Lindon sooner?
Let Alliance prepare, file, and track your Lindon permits while your crew stays on the job.
More Utah permitting guides
This guide is provided by Alliance Permitting for general information about Lindon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.