Skip to main content
Municipal GuideTexasLive Oak · Bexar County

Live Oak, Texas Building Permit Guide

Live Oak’s Permits & Inspections Department issues building and trade permits through MGO Connect, and new codes, including the 2024 IRC and 2026 NEC, took effect on July 1, 2026.

Authority: City of Live Oak Permits & InspectionsCode: 2024 I-Codes; 2026 NECPhone: 210-653-9140 ext. 2244
Authority
City of Live Oak Permits & InspectionsBexar County
Submission
MGO ConnectApplications, fees and inspections
New home fee
$0.65 per sq ftPlus $0.35 per sq ft plan review
Inspections
Request by 3:30 p.m.Next business day

Inside the City of Live Oak, permits come from the Permits & Inspections Department, based in the Fire Station at 8001 Shin Oak Drive, and applications are filed online through MGO Connect. A new house is charged $0.65 per square foot plus $0.35 per square foot for plan review, and inspections requested by 3:30 p.m. go on the next business day’s schedule.

What requires a permit in Live Oak?

Live Oak wants permits pulled before any work starts. Besides new homes and commercial buildings, the City’s list covers many smaller jobs:

Permit needed

  • Additions, remodels, and moving or removing interior walls or drywall
  • Replacing a bathtub or shower
  • AC, heating, plumbing and electrical installation or replacement
  • Water heaters and water softeners
  • Roof replacement
  • Every fence installation or replacement
  • Sheds over 120 sq ft, workshops, carports and garages
  • Patios, decks, pergolas, arbors and patio covers
  • All concrete flatwork: parking pads, pathways, patios and driveways
  • Pools and hot tubs, foundation repairs, irrigation, demolition, house moving, mobile homes and signs

No permit needed

  • A one-storey detached building of 120 sq ft or less with no plumbing, electrical or HVAC, outside flood zones, easements and setbacks
  • Retaining walls up to 3 feet that carry no surcharge
  • Prefabricated pools under 24 inches deep
  • Free-standing decks up to 100 sq ft and 30 inches high
  • Painting, flooring, tiling, cabinets and countertops
  • Replacing trim, fascia and soffits, or same-size doors
  • Stopping leaks and clearing stoppages

Emergency plumbing repairs made after hours still need a permit, applied for within 24 hours.

Who issues building permits in Live Oak?

The City’s Permits & Inspections Department, part of Development Services, reviews plans, issues building and trade permits, inspects the work and also handles health permits for food businesses. Kelly Brunner is the Building Official. Fire inspections are booked separately with the Fire Marshal’s Office, and Public Works issues right-of-way, driveway approach and sidewalk permits.

Short on time to read all of this?

Get a free quote →
Live Oak permit contacts
OfficeContact
Permits & Inspections8001 Shin Oak Drive (inside the Fire Station), Live Oak, TX 78233; 210-653-1829 or 210-653-9140 ext. 2244; permits@liveoaktx.net. Closed for lunch 12 to 1 p.m.
Fire Marshal’s Office (fire inspections)210-653-9140 ext. 2242
City utility locates210-653-9140 ext. 2220
Online permitsMGO Connect

Master permits, trade permits and registration

A permit can be pulled by a contractor registered with the City or by a homeowner with a homestead exemption doing work on their own home. On a building project, the general contractor holds the master permit, and once it is approved, the plumber, electrician and mechanical contractor each apply and pay for their own permit under it in MGO before the master permit is issued. All permits on the job must be approved and paid before any of them is released. A subcontractor who comes back after the master permit has passed final needs a separate permit.

Every contractor and trade must register with the City ($100 a year), and licensed trades must show an active licence. Permits cannot be transferred, and they must be posted on site before work starts.

Live Oak permit fees

Fees are set in Appendix C of the Code of Ordinances, last amended in October 2025. Items marked as carrying an issuance fee add $50 to the permit.

Live Oak residential permit fees
ProjectFee
New one- or two-family home$0.65 per sq ft, plus $50 issuance fee
Residential plan review$0.35 per sq ft
Addition, remodel or alteration$0.50 per sq ft
Electrical, mechanical or plumbing, new home$200 each, plus $50 issuance fee
Trade repair or replacement$60
Roof replacement, shed, carport, patio or patio cover$200 each
Flatwork or deck$150
Fence$50
Above-ground / in-ground pool$100 / $500
Foundation repair$250
Residential irrigation$100
Residential solar$60 plus $10 per panel
Demolition$500
Re-inspection, per trade$75 the first time, $100 after that

Not sure this scope needs a permit?

Get a free quote →

Square footage counts the whole foundation area, any covered area on the first floor and any second-floor space. For a new home of 2,000 sq ft on that basis, the building permit is $1,300 plus the $50 issuance fee, plan review is $700, and the three trade permits add $250 each: $2,800 in all. Plan review fees are due when the plans are submitted.

Commercial building permits run from $100 for work up to $1,000 in value to $1,665.30 plus $4 per $1,000 above $500,000, with a separate valuation-based plan review fee. Paying a permit by credit card adds 3.25%.

Trade and fire permits

Water heater permits are pulled by a registered Responsible Master Plumber, and HVAC permits by a registered licensed mechanical contractor, unless a homestead owner does the work. Water heaters may not be installed or replaced in a residential attic, and replacing ductwork means passing a duct leakage (Duct Blaster) test at the mechanical final.

Fire sprinkler and fire alarm permits are $250 each for up to 200 heads or devices, plus $1 for each one above 200, and all fire inspections are scheduled with the Fire Marshal’s Office.

Plans and documents

Every MGO application needs a written scope of work, and multi-sheet plans must be combined into one digital file. For a new house, the City’s May 2026 checklist asks for:

Rather talk it over?

Call 1-855-478-4290 →
  • A scaled site plan with property lines, setbacks, easements, driveways, a surveyed benchmark elevation, first-floor elevation and drainage arrows; AC units cannot sit in the 5-foot setback
  • Floor, roof, elevation, wall section, door and window plans, with the adopted code years on the cover page
  • Plumbing, mechanical and electrical plans, including smoke and carbon monoxide alarms
  • A foundation plan designed and stamped by a registered professional engineer, plus framing, truss and wind brace plans
  • A passing REScheck or other approved energy report, and Manual J and S load calculations
  • An HOA approval letter for alterations in an HOA community, and an elevation certificate if the lot is in a flood hazard area

Comments from every department come back together by email, and responses must be in a written comment letter with a complete revised set. A building permit cannot be approved until the plat is recorded and the site plan is released by Planning & Zoning and Engineering. Commercial plans add a Texas Accessibility Standards registration for work of $50,000 or more, a statement of special inspections and, for demolition over 100 sq ft, an asbestos report.

How to get a permit in Live Oak

1. Register

Register your company and trades with the City, or confirm your homestead exemption if you are doing the work yourself.

2. Get HOA approval

Fences, roofs, carports, sheds and flatwork in an HOA neighborhood need the HOA’s written approval with the application.

3. Apply in MGO Connect

Upload the scope of work, site plan and the plans from the matching City checklist, and pay the plan review fee.

4. Answer review comments

Reply in a written comment letter with a complete revised plan set.

5. Add the trade permits

Once approved, each subcontractor applies and pays under the master permit; then all permits are released together.

6. Post the permit and call inspections

Post the permit on site, then request each inspection in MGO by 3:30 p.m.

Rather not deal with the building department?

Get a free quote →

Inspections in Live Oak

Request inspections in the MGO portal by 3:30 p.m. for the next business day; later requests go to the following day’s queue. Inspectors work Monday to Friday from 8 a.m. to 5 p.m. on routes set by the day’s volume, so the City cannot offer appointment times. Put gate codes or call-ahead instructions in the request notes, and cancel through MGO or by email before 8 a.m. on the inspection day to avoid a re-inspection fee.

Small jobs have short lists: a fence needs only a final; a roof needs a decking inspection (at least 7/16-inch OSB or plywood) and a final; flatwork needs a pre-pour and a final; and a carport needs pre-pour, frame and final inspections. A permit expires 180 days after it is issued or after the last inspection, and the Building Official may extend it on a written request made before it lapses.

A commercial certificate of occupancy ($250) can be requested only after every final has passed, including fire, health, site and building, and the backflow test reports, sanitation letter and other closing documents are uploaded. The City can also issue a certificate of completion for an unfinished shell building and several kinds of temporary certificate of occupancy.

Local Live Oak rules

Penalties: starting work without a permit costs double the permit fee per trade, at least $750. The fee schedule sets a $500 charge for not posting the permit on site, although the City’s permit FAQ still mentions a $50 fine.

Fences: up to 6 feet on side and rear lines and 3 feet in a required front yard in the R1, R2, R3 and B1 districts, built of wood, metal or masonry; barbed or razor wire and add-on lattice to gain height are banned.

Carports: attached to the house, one storey, open on three sides, no wider than 20 feet, and no closer than 5 feet to the front property line.

Pools: pools and decks must be at least 5 feet from property lines, with the excavation kept at a 1:1 distance from the house foundation.

Roofs and digging: wood roofs are prohibited. Texas 811 locates do not cover the City’s water, wastewater and stormwater lines; call 210-653-9140 ext. 2220 for those. Replacing a sidewalk or driveway approach needs a separate Public Works permit.

Want this handled start to finish?

Get a free quote →

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Live Oak official resources

Inspections are where schedules slip.

Get a free quote →

Live Oak permit FAQs

How much is a building permit for a new house in Live Oak?

$0.65 per square foot plus a $50 issuance fee, with plan review at $0.35 per square foot. The plumbing, electrical and mechanical permits are $200 each plus $50 issuance. A 2,000 sq ft home comes to about $2,800.

Do I need a permit for a fence in Live Oak?

Yes, for every new or replacement fence. The permit is $50 and needs a final inspection.

Do I need a permit to replace my roof?

Yes. A roof replacement permit is $200, with decking and final inspections.

Do I need a permit for a shed?

Only if it is over 120 sq ft, more than one storey, attached, has utilities, or sits in a flood hazard area. A shed permit is $200.

Can a homeowner pull a permit?

Yes, if the home has a homestead exemption and the owner does the work.

What is the inspection request cutoff?

3:30 p.m. in MGO for an inspection the next business day.

How long is a Live Oak permit valid?

180 days from issue or from the last inspection. Ask the Building Official for an extension in writing before it expires.

Simplify Live Oak permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Live Oak sooner?

Let Alliance prepare, file, and track your Live Oak permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Live Oak permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.