Adams County, Ohio Building Permit Guide

To get a building permit in Adams County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Adams County’s government lists no building department, so the permits most rural projects need here come from the Adams County Health Department in West Union: the septic site evaluation, sewage permits and well permits.

Authority: No county building department listedSeptic and wells: Health DepartmentPhone: 937-544-5547
New-house septic
$400 + $650Site evaluation, then permit
New well
$480Includes water tests
Floodplain
Firm soughtProposals closed Nov. 2, 2026
Population
27,865Census 2025 estimate

Adams County’s government directory lists no building or zoning office among its county departments. For a new home the permits you can count on come from the Adams County Health Department at 560 Rice Drive, West Union (937-544-5547): a septic site evaluation ($400) and permit to install ($650), and a well permit ($480). For floodplain administration and permitting in the unincorporated county, the commissioners asked firms for proposals due November 2, 2026.

What requires a permit in Adams County?

The county’s own pages describe no building permit program. What they do show is a set of health and flood rules that apply to almost every new rural home and many alterations.

Permits the county side requires

  • A site evaluation and permit to install before any septic system goes in or any new home is built, under the state sewage rules the health department applies
  • A permit to repair or alter a septic system, replace a tank or abandon an old system
  • A permit to install, repair, alter or seal a private water system: well, spring, cistern or hauled-water tank
  • Development in a mapped flood hazard area of the unincorporated county, under its flood damage prevention regulations

Exempt from building approval statewide

  • A detached one-story shed or playhouse up to 200 square feet beside a house; 120 square feet under the Ohio Building Code
  • A fence up to 6 feet beside a house; 7 feet under the Ohio Building Code
  • A retaining wall of 4 feet or less holding back no surcharge
  • Minor repairs that do not cut walls, touch structural supports or change the exits

What Adams County decides and what the state holds

The state adopts the building codes and certifies the departments allowed to enforce them. The county directory names no such department, so check the state’s building-department look-up map for the address. Where no certified department has jurisdiction, plans for a nonresidential building go to the state’s Superintendent of Industrial Compliance, and under ORC 3791.04(A)(1) an owner need not submit plans for a house. Locally, the Board of Health sets the sewage and water fees and the commissioners hold the flood damage prevention regulations for the unincorporated county.

Adams County building department: who handles permitting

West Union is the county seat, and the offices that touch construction are all there.

Short on time to read all of this?

Get a free quote →
Adams County contacts
OfficeAddress, phone and hours
Adams County Health Department, Environmental Health (septic, wells)560 Rice Drive, West Union, OH 45693; 937-544-5547 (Environmental Health extension 115); fax 937-544-3035; Monday–Friday 8:00 a.m.–4:00 p.m., closed noon to 1:00 p.m.
Board of Commissioners (floodplain contract, county regulations)215 North Cross Street, Suite 102, West Union; 937-544-3286; Monday–Friday 8:00 a.m.–4:00 p.m.
Adams County Engineer75 Willow Drive, West Union; 937-544-2943; Monday–Friday 8:00 a.m.–4:00 p.m.
Economic and Community Development215 North Cross Street, Suite 101, West Union; 937-544-5151; housing rehabilitation grants and infrastructure projects

Villages

Adams County has five villages and no cities: West Union (3,091 people in the Census Bureau’s 2025 estimate), Manchester (1,874), Peebles (1,777), Winchester (998) and Seaman (988). The published county sources do not say whether any of them runs a building or zoning program, so ask the village office before planning work inside village limits.

A rural mailing address can name a village or a neighboring county’s town, so confirm the jurisdiction from the parcel record at the County Auditor (937-544-2364) and the state look-up map.

Adams County permit types

Residential permits

For a house the health department’s sewage and water permits are the main local approvals. Its forms can be faxed, mailed or dropped off at the office, and questions about septic systems can be sent through the “Ask a Sanitarian” form on its site.

  • Household sewage treatment system. Start with the site evaluation application for a new installation or a repair; the department then confirms the site can be developed before you hire a soil scientist.
  • Private water system. A permit to install covers a well, spring, cistern or hauled-water storage tank for a single- or multi-family home and includes the first water tests.
  • Point-of-sale and operation inspections. Loan evaluations for buyers and sellers, and operation and maintenance or home-replacement inspections, are requested on separate forms.

Commercial permits

For businesses, the health department evaluates and permits small-flow onsite sewage systems on the same fee basis as homes ($400 to evaluate the site, $650 to install), and it licenses food service operations, public swimming pools, campgrounds and tattoo shops, each with plan review where the fee schedule lists it. Building plans for a commercial project go to whatever department the state look-up map shows for the address.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Usable ground. The health department requires at least one acre of usable ground for a development site unless the lot was platted before 1994.
  • Site marking. Before the evaluation, post a sign with the address or owner’s name at the road and mark the home site with four corner stakes.
  • No clearing first. Land clearing, bulldozing or construction before the site evaluation raises the evaluation fee to $500.
  • Soils and design. After the department says the property is developable, a soil scientist evaluates the soils at the owner’s expense, and a septic designer or engineer may be needed if the report shows limiting conditions.
  • Flood areas. Development in a mapped flood area of the unincorporated county falls under the county’s flood damage prevention regulations; ask the commissioners’ office which firm now reviews those permits.

Adams County permit costs and fees

With no county building department, the published permit fees are the health department’s. Its sewage treatment system fees took effect January 1, 2026; several show the local fee plus the state’s share.

Adams County sewage fees (effective January 1, 2026)
ItemFee
Site evaluation, new installation; repair$400; $250
Site evaluation after clearing or construction has started$500
Lot split evaluation$400
Permit to install, new system (also gray water and small-flow systems)$650 ($576 plus $74)
Permit to install, 50% or more of disposal components$474 ($400 plus $74)
Septic tank replacement, or 49% or less of disposal components$335 ($300 plus $35)
Abandonment of an existing system$300
Operation and maintenance permit$60; $30 when another agency inspects
Subdivision review$200 plus $100 per lot
Loan (point-of-sale) evaluation; re-inspection$250; $100
Installing without a permitPermit fee plus 25%

Rather talk it over?

Call 1-855-478-4290 →
Adams County private water fees
ItemFee
Permit to install a new well, single- or multi-family$480 ($386 plus $74 plus $20)
Permit to install a cistern, hauled-water tank or spring$460 ($386 plus $74)
Repair, alteration or conversion$300
Sealing a private water system$200
Variance$100 plus the permit fee
Bacterial water test with a sanitarian visit$80

Worked example from the 2026 sewage schedule: a new home on an unsewered lot pays $400 for the site evaluation and $650 for the permit to install, or $1,050, before the soil scientist’s and designer’s own charges; adding a new well brings the health department total to $1,530. The site evaluation fee cannot be refunded or transferred once the application is filed.

Trade permits and who may pull them

The county pages show no local electrical, plumbing or HVAC permit program and no local contractor registration for building trades. What they do regulate:

  • Septic contractors. Only licensed and bonded installers may install septic systems in Adams County. The health department licenses installers, service providers and septage haulers each year ($250 each, per truck for haulers, or $500 for a combined license) and posts the 2026 lists.
  • Choosing an installer. You must know which registered contractor will install the system before the permit to install is issued, and the homeowner is responsible for buying every evaluation and permit before work starts.
  • Well drillers. The health department points owners to the state’s registered private water systems contractors.
  • State licenses. Electrical, HVAC, hydronics, plumbing and refrigeration contractors working on commercial buildings must be licensed by the Ohio Construction Industry Licensing Board; Ohio has no state license for general contractors.

Rather not deal with the Adams County building department?

Get a free quote →

How to get the permits for a new rural home

1. Confirm the jurisdiction

Check the parcel with the County Auditor and the state building-department look-up map, and ask the village office if the lot is inside village limits.

2. Prepare the site

Post an address sign and stake the four corners of the house; do not clear or grade yet.

3. File the site evaluation

Send the application, the $400 fee, the deed or land contract, a survey or plot map and the floor plan to the health department.

4. Get soils and design

Once the site is found developable, hire a soil scientist and, if needed, a designer, and submit their reports.

5. Buy the permits

Pay the $650 permit to install, plus the $480 well permit if you need a well, and name your registered installer.

6. Check flood status

If the lot is in a mapped flood area, ask the commissioners’ office how the floodplain permit is now handled.

Review, corrections and what causes delay

The health department says a site evaluation is done in a timely manner but may take up to 15 business days because of scheduling and limited staff, and nothing is scheduled until every paper and fee is in. A site that cannot be found, or a house location that moves after the evaluation, costs a $100 re-inspection. Poor soils are the other common hold-up, since an engineered design may be needed before the system can be approved.

Inspections in Adams County

The health department’s sanitarians make the site evaluation visit before any septic permit, and they carry out point-of-sale, operation and maintenance, and home-replacement inspections on request. Once soils reports and designs are approved, that approval is valid for five years from the date of signature. A failed or repeat visit costs $100. Water samples for a new well are included in the permit (up to three bacterial tests and one nitrate test), and a sanitarian can collect a bacterial sample from an existing system for $80. The department’s division also inspects public swimming pools, campgrounds and food operations. Building, electrical and mechanical inspections, where they apply, are made by whichever certified department the state look-up map shows for the address.

Want this handled start to finish?

Get a free quote →

Ohio building code in Adams County

The statewide codes apply to any project reviewed by a certified department or by the state. FEMA’s Community Status Book lists unincorporated Adams County (community 390001) as participating in the National Flood Insurance Program, with a current effective map date of December 3, 2010. The commissioners’ August 2026 request for proposals sought a firm to handle floodplain administration and permitting for the unincorporated area under those obligations and the county’s flood damage prevention regulations.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Adams County permit search and official resources

Septic and well permit history for a parcel is held by the health department; ask Environmental Health at 937-544-5547. For floodplain records, contact the commissioners’ office, and for parcel ownership and maps, the County Auditor.

Inspections are where schedules slip.

Get a free quote →

Adams County permit FAQs

Does Adams County have a building department?

Its office directory lists none; use the state look-up map to see which department, if any, covers an address.

What do I need before building a house on an unsewered lot?

A health department site evaluation ($400) and permit to install ($650) for the septic system, bought before construction of the house begins.

How much is a well permit?

$480 for a new well, which includes up to three bacterial tests and one nitrate test.

How big must a lot be for a septic system?

At least one acre of usable ground, unless the lot was platted before 1994.

Who handles floodplain permits?

The county sought a contracted firm for floodplain administration in the unincorporated area, with proposals due November 2, 2026; call the commissioners at 937-544-3286.

Can I start clearing the lot before the septic evaluation?

No. Clearing, bulldozing or building first raises the site evaluation fee to $500.

Simplify Adams County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Adams County sooner?

Let Alliance prepare, file, and track your Adams County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Adams County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.