Building permits inside the City of Portsmouth are issued by the city’s Engineering Department, which acts as the building department from the zoning check through to occupancy (728 Second Street, Room 25; 740-354-7557). Plans that need review go to the building official, an outside consultant working for the department, and the city puts that review at usually 2 to 3 weeks. A new house or addition costs $180 plus $0.09 a square foot for the building permit, plus trade fees and the 1% state fee, and every contractor on the job must hold a current city registration.
What requires a building permit in Portsmouth?
Portsmouth’s codified ordinance 1305.01, quoted on the city’s checklist, says no one may erect, construct, alter, repair, equip, remove or demolish a house, building or structure without first applying in writing to the Building Officer and getting a permit. The department’s Permit Required Checklist (revised August 31, 2021) then sorts common jobs:
Permit required
- New buildings, a change of use, and garages or accessory buildings over 200 square feet
- Decks over 200 square feet, ADA ramps, and retaining walls over 48 inches from the bottom of the footing
- New roof decking or structural roof changes, and any new commercial roof
- Interior alterations that remove walls or add framing or drywall
- Electric service work, new wiring, hardwired appliances and hardwired smoke or CO alarms
- Furnaces, air conditioners, ductwork, water heaters, fireplaces and gas piping
- New plumbing fixtures (in-ground pools included) and fixture work that changes piping
- Sprinklers and hood suppression, signs for non-residential property, and driveways, sidewalks or tree work in the public right-of-way
No permit on the checklist
- Painting, tiling, carpeting, cabinets and trim
- Same-size window and door replacement, garage doors and siding
- Fences not over 6 feet and retaining walls under 48 inches
- Slabs under 30 inches, private driveways and private landscaping
- Minor deck, roof, wiring and plumbing-fixture repairs
- Plug-in appliances, battery smoke alarms and playground equipment
The checklist marks new residential roof coverings as not needing a permit, but the later residential permit packet (May 2022) charges a roof replacement fee when all coverings are removed, so ask the department before a tear-off. A fence or a right-of-way job that needs no building permit can still need the city’s miscellaneous work permit described below.
What Portsmouth decides and what the state holds
The city enforces the Ohio Building Code for commercial and multifamily buildings and the Residential Code of Ohio for one-, two- and three-family homes, as the building department page states. What Portsmouth sets itself is the zoning code (revised January 9, 2023), contractor registration under Chapter 1323, the permit fee schedules, the flood damage prevention rules it must apply as an NFIP community, historic review under Chapter 1317, and right-of-way standards such as 6-inch concrete driveways and 4-inch sidewalks.
Short on time to read all of this?
Get a free quote →Portsmouth building department: who handles permitting
The Engineering Department is the city’s building department. It takes applications, checks zoning and right-of-way encroachment in-house, sends plans to the consultant building official for code review, issues the permit, inspection card and placard, and closes permits with a certificate of occupancy or completion. Residential, commercial, electrical, plumbing and HVAC permits all come from this one office.
| Detail | Information |
|---|---|
| Office | Engineering Department, Municipal Building, 728 Second Street, Room 25, Portsmouth, OH 45662 |
| Phone / fax | 740-354-7557 / 740-354-5383 |
| Department address on the Building Department page (applications accepted by email) | |
| Online | iWorQ citizen portal, linked from the Permits and Applications page |
| Plan review | Consultant building official working for the department |
| Income tax (before contractor registration) | City Income Tax Division, 605 Washington Street, 740-353-3111 |
| City Hall main line | 740-354-8807 |
The department’s authority stops at the city limits. For an address near the boundary, or in neighboring New Boston, which is a separate village, the Board of Building Standards look-up map shows which certified department covers it.
Portsmouth permit types
The department posts each permit as a packet with instructions, a fee sheet, an inspection guide and the application, and accepts it through the iWorQ portal, by email, or at Room 25.
Residential permits
- Residential Building Permit packet for new one-, two- and three-family dwellings and for additions and alterations. Interior-only work needs no site plan; new dwellings and substantial renovations attach two sets of plans and a site plan showing structures, streets, property lines, setbacks, grading and utilities.
- Residential electric service permit for a new service, upgrade, meter reinstall or temporary service, following AEP’s service and meter guide.
- Miscellaneous work permit for fences, gutters and downspouts on private property and for driveways, sidewalks, culverts, landscaping, sewer taps and material storage in the right-of-way. The owner or renter may do this work personally; a hired contractor must be registered.
- Demolition permit to take down all or part of a building.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
- Commercial Building Permit packet for non-residential and multifamily buildings, with structural, mechanical, electrical, plumbing, sprinkler, fire alarm, hood and cell tower fees on one sheet and a sub-contractor section.
- Certificate of occupancy or change of use for commercial space, and time-limited certificates of occupancy for temporary uses.
- Sign permit for new signs, and a utility provider right-of-way permit package for utilities working in city streets.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning permit. The city calls checking the zoning the first step: the proposed use must be on the permitted list for the district. The zoning map is a layer on the Scioto County GIS viewer.
- Board of Zoning Appeals. A refused zoning permit can be appealed within 30 days for a $150 fee; the city publishes a newspaper notice, tells neighbors and expects the applicant or a representative to attend.
- Planning Commission. It handles subdivision platting, zoning districts and uses that need a public hearing; applications cost $150.
- Design Review Board. In the Boneyfiddle Historic District and at certain other historic properties, new construction, exterior changes and demolition need a Certificate of Appropriateness before any building permit is approved. The five-member board meets once a month.
- Floodplain development permit. A site in a mapped flood area needs this permit as well as the building permit, both approved before construction starts.
Portsmouth permit costs and fees
Fees are printed in the department’s permit packets (residential and commercial packets revised May 16, 2022; the electric service form revised May 2, 2024). Building permit fees are due when you submit, and a separate plan review fee is charged after each review of the drawings. Permits are not transferable or refundable.
| Work | Fee |
|---|---|
| New dwelling or addition (building) | $180 + $0.09 per sq ft |
| Renovation or alteration; detached accessory building over 200 sq ft | $60 + $0.09 per sq ft |
| Roof replacement removing all coverings | $50 + $0.03 per sq ft |
| Retaining wall over 4 ft; attached deck or porch over 200 sq ft or 30 in. above grade | $50 each |
| Electrical, new dwelling or addition | $75 + $0.05 per sq ft (alterations $30 + $0.05) |
| Electric service | $150 plus 1% BBS fee on the 2024 service form ($75 on the 2022 packet) |
| Panels, sub-panels, generators | $75 each |
| Plumbing, new dwelling or addition | $60 + $0.03 per sq ft; new fixtures $20 each; water heaters $35 |
| HVAC, new dwelling or addition | $60 + $0.03 per sq ft; each new heating or AC unit $35 |
| Solar or geothermal | $125 |
| Board of Building Standards fee | 1% of the subtotal |
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Commercial structural | $275 per structure + $10.50 per 100 sq ft (areas rounded up to the next 100 sq ft) |
| Commercial mechanical, electrical | $275 + $6.50 per 100 sq ft each |
| Commercial plumbing | $275 + $20 per fixture |
| Sprinkler / fire alarm | $275 + $6.50 per 100 sq ft / $275 + $6.50 per device |
| Commercial hood; certificate of occupancy or change of use | $200 each |
| Items with no plans; special inspection | $90; $150 |
| Board of Building Standards fee (commercial) | 3% of the subtotal |
| Miscellaneous work: driveway, sidewalk, fence, gutters, landscaping | $25 each; sewer tap $100 |
| Floodplain development permit | $50 residential; $100 commercial |
| Board of Zoning Appeals or Planning Commission application | $150 |
Worked example from the residential sheet: a 1,500 sq ft addition costs $180 + (1,500 × $0.09) = $315 for the building permit, and the 1% state fee adds $3.15, for $318.15 before the plan review fee, which the sheet does not price and is billed after review. Electrical, plumbing and HVAC for the same addition are added line by line on the same sheet. Where the 2024 electric service form and the 2022 packet differ, the newer form’s $150 is the one to budget.
Trade permits and who may pull them
All contractors and sub-contractors doing work in the city must be registered with the Engineering Department, and the department will not issue a building permit to an unregistered contractor. Registration starts with the city’s Income Tax Division, then needs the application, $300,000 of liability insurance, an Ohio workers’ compensation certificate (or a notarized statement from a self-employed contractor with no employees) and the annual fee: $100 for the first registration and $50 for each more trade. A $25,000 compliance bond is needed only for work on city property or under a city contract. Working unregistered is a second-degree misdemeanor, each day a separate offense.
- Electrical, plumbing, HVAC, refrigeration, hydronic and fire protection contractors attach a copy of their state OCILB license, which the city requires for commercial work; their city registration expires with the state license.
- General contractors register with the city and list their work types; Ohio has no state license for them.
- Homeowners acting as their own contractor may file the residential packet and, on miscellaneous work, the owner or renter may do the job personally; the inspection guide expects whoever performs the work to be present for inspections.
- Trade fees for houses are charged on the residential sheet by floor area, fixture or unit; commercial trades use the $275 processing fee per structure.
Rather not deal with the building department?
Get a free quote →How to apply for a Portsmouth building permit
Confirm the use is allowed in the district and file the zoning permit application.
Get a Certificate of Appropriateness in the historic districts and a floodplain development permit in a flood area.
Income tax registration first, then the city contractor registration with insurance and workers’ compensation.
Send the residential or commercial packet with plans and site plan through iWorQ, by email or at Room 25, and pay the permit fee.
The consultant building official reviews the plans; corrections come back as an adjudication letter and each resubmittal carries a plan review fee.
Pay the plan review fee and pick up the approved plans, permit, inspection card and placard before starting work.
Notify Ohio Utility Protection Services (8-1-1 or 1-800-362-2764) 48 hours before excavation.
Review, corrections and what causes delay
The city says the building official may take up to 30 days by state rule but usually reviews plans in 2 to 3 weeks. Each round of corrections restarts the review and adds another plan review fee, so complete drawings save both time and money. Permits expire after one year for new construction, after six months for alterations or repairs under $10,000, and after one year without activity.
Inspections and certificates in Portsmouth
Call the department at 740-354-7557 the business day before you want an inspection, with the permit number and address; a call on Friday books Monday. Staff inspections happen the next business day where possible, while inspections that need the consultant, and electric service inspections, are held on Tuesdays and Thursdays. The inspection card lists the stages the building official requires, which can include footing, foundation wall, slab, framing, underground and rough electrical, plumbing and HVAC, insulation, fire stopping, sprinkler and alarm, and the final building inspection.
The permit, approved plans and inspection card must stay on site, work must match the approved plans, and construction hours run from 7:00 a.m. to 6:00 p.m. When every final is approved, return the completed card; the department closes the permit and, on request, issues a certificate of occupancy or completion once fees are paid and site work is finished.
Want this handled start to finish?
Get a free quote →Ohio building code in Portsmouth
The Engineering Department enforces the Ohio Building Code and the Residential Code of Ohio inside the city. FEMA’s Community Status Book lists the City of Portsmouth (community 390498B) as participating in the National Flood Insurance Program, with its current flood map dated June 19, 2020, and the floodplain permit checks that a new or substantially improved building’s lowest floor reaches the flood protection elevation.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Portsmouth permit search and official resources
Permit and inspection files are held by the Engineering Department; ask at Room 25 of the Municipal Building, by phone at 740-354-7557 or by email for copies of a permit, approved plans or a certificate of occupancy. Applications filed online can be followed in the iWorQ portal.
- Portsmouth Building Department (Engineering)
- Permits and applications
- Residential building permit packet and fee schedule
- Commercial building permit packet and fee schedule
- Residential electric service permit
- Miscellaneous work permit (fences, driveways, sewer taps)
- Contractor registration requirements
- Permit required checklist
- Zoning permits and Board of Zoning Appeals
- Design Review Board application (Certificate of Appropriateness)
- Floodplain information and development permit
- Resources: certificates of occupancy, driveway standard drawing
- BBS building-department look-up map
- Ohio Construction Industry Licensing Board
Inspections are where schedules slip.
Get a free quote →Portsmouth building permit FAQs
Do I need a permit for a fence in Portsmouth?
A fence not over 6 feet needs no building permit under the city checklist, but fences are on the $25 miscellaneous work permit, which follows an approved zoning permit.
How much is a permit for a new house?
The building permit is $180 plus $0.09 a square foot, with electrical, plumbing and HVAC charged by area on the same sheet, 1% added for the state, and a plan review fee after review.
How long does plan review take?
Usually 2 to 3 weeks, according to the city’s packets; state rules allow the building official 30 days.
Does a shed need a permit?
An accessory building larger than 200 square feet does; the fee is $60 plus $0.09 a square foot.
Do contractors have to register?
Yes. Every contractor and sub-contractor registers with the Engineering Department, renewing every 12 months (licensed trades with their state license), and no building permit is issued to an unregistered contractor.
What extra approval does the Boneyfiddle district need?
A Certificate of Appropriateness from the Design Review Board before any building permit is approved for new construction, exterior changes or demolition.
When are inspections held?
Call the business day before. Staff inspections are next-day where possible; consultant and electric service inspections are on Tuesdays and Thursdays.
Simplify Portsmouth permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Portsmouth sooner?
Let Alliance prepare, file, and track your Portsmouth permits while your crew stays on the job.
More Ohio permitting guides
Pike County
Read guide →Lawrence County
Read guide →Adams County
Read guide →Powell Building Permit Guide
Read guide →Preble County Building Permit Guide
Read guide →Putnam County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Portsmouth permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.