Howard County, Missouri Building Permit Guide

To get a building permit in Howard County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

No official source shows a Howard County building permit; septic permits come straight from the state health department, and Fayette, Glasgow and New Franklin issue building permits in town.

Authority: Howard County floodplain administrator (courthouse, Fayette)Building code: None published for unincorporated landPhone: 660-248-2193
County building permit
None published
Septic permits
Missouri DHSS, 573-751-6095 ext. 5
Fayette permit fee
$25 + $2 per $1,000 of value
Fayette codes
2015 International Codes, 2014 NEC

No official source publishes a building code, zoning ordinance or building permit for unincorporated Howard County. Septic systems there are permitted directly by the Missouri Department of Health and Senior Services, and SEMA lists the county floodplain administrator at the courthouse in Fayette. Fayette’s Department of Building Safety charges $25 plus $2 per $1,000 of construction value, and Glasgow and New Franklin also require permits.

Howard County building department: who handles permitting

Inside the cities, each city handles its own permits. For unincorporated land, the county contacts in the state listings are its floodplain administrator at the courthouse and, for septic systems, the state health department itself. Populations below are Census Bureau Vintage 2025 estimates.

Short on time to read all of this?

Get a free quote →
Who handles building permits in Howard County
PlaceWho permits building work
Fayette (2,848)City of Fayette Department of Building Safety, under the 2015 International Codes and 2014 NEC; City Hall, 117 S. Main Street, 660-248-5246
Glasgow (1,053 here; 27 in Chariton County)City of Glasgow: a permit before any construction, four inspections by the City Building Inspector; SEMA lists the city’s floodplain contact at 415 Saline Street, 660-338-2377
New Franklin (1,026)City of New Franklin: building, fence and demolition permits from City Hall, 130 East Broadway, 660-848-2288
Armstrong (241)The published sources do not say; SEMA lists the city’s floodplain contact at 102 S. Central, 660-888-2558
Franklin (67)The published sources do not say; SEMA lists the city’s floodplain contact at 603 Stephens Avenue, 660-888-9614
Unincorporated Howard CountyNo county building permit is published; DHSS septic permits and county floodplain review apply

Fayette and Glasgow permits and fees

Fayette, the county seat, requires a permit for any commercial or industrial building, any single-story residential or accessory structure over 160 sq ft, structural, electrical, plumbing, heating and air or insulation work, new homes, remodels, additions including decks, porches and sunrooms, re-roofing, garages, carports, sheds, pools, greenhouses and barns. Fences over 12 ft and retaining walls over 4 ft must be engineered. Commercial work needs plan review of 3 sets of construction documents.

Not sure this scope needs a permit?

Get a free quote →
City of Fayette building permit fees (form dated March 10, 2023)
ItemFee
Building permit base fee$25
Value of construction up to $300,000$2 per $1,000
Value over $300,000Additional $500 flat fee
Residential or commercial sewer tap$275
Residential water tap, same side of the street$1,250
Residential water tap, opposite side of the street$2,000

For example, a house valued at $250,000 pays $25 plus $500, or $525. A house application needs a copy of the deed or survey, the cost estimate, the square footage of each floor, garage, porch and deck, a site drawing showing the wastewater system and lot-line distances, the foundation type, a floor plan and elevations; applications are taken from 8:00 a.m. to 4:30 p.m. on weekdays. Fayette inspects the footing before concrete, the framing and sheathing, rough electrical, plumbing and mechanical work, insulation (at least R-15 in 2x4 walls) and the final.

In Glasgow, the permit costs $5 for work between $200 and $1,000, plus $2 for each $1,000 above the first $1,000. The city inspects at least four times, after the footings, after rough framing, after rough electrical and plumbing and at completion, and the signed permit serves as the certificate of occupancy that must be shown before utilities are connected. Glasgow’s code adopts the 1996 BOCA National Building Code and the 1995 CABO One- and Two-Family Dwelling Code.

Rather talk it over?

Call 1-855-478-4290 →

New Franklin requires building permits for all new structures, additions, outbuildings, decks, patios, carports and remodeling, but not for roofing, siding or window replacement. Every fence needs a permit, with no fee, and removing any building needs a demolition permit.

Septic and floodplain in Howard County

Septic systems: Howard County has no local onsite wastewater authority, so the Missouri Department of Health and Senior Services issues permits directly: request an application number through its online form or call 573-751-6095, ext. 5.

Floodplain: Howard County is in the National Flood Insurance Program on flood maps dated March 21, 2017, with its floodplain administrator listed by SEMA at 1 Courthouse Square, Fayette (660-248-2193). Armstrong, Fayette, Franklin, Glasgow and New Franklin also take part in the program.

Missouri building code

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Howard County permit FAQs

Rather not deal with the Howard County building department?

Get a free quote →

Does Howard County issue building permits?

No official source publishes a county building code or building permit for unincorporated Howard County. Septic and floodplain rules still apply.

Who issues septic permits in Howard County?

The Missouri Department of Health and Senior Services, directly; call 573-751-6095, ext. 5, or use its online application number request form.

How much is a building permit in Fayette?

$25 plus $2 per $1,000 of construction value, with an extra $500 when the value is over $300,000. A $250,000 house pays $525.

What building code does Fayette use?

The 2015 International Building, Residential, Plumbing, Mechanical, Fuel Gas, Energy Conservation, Fire and Property Maintenance Codes and the 2014 National Electrical Code.

Do I need a permit for a new roof in New Franklin?

No. New Franklin does not require building permits for roofing, siding or window replacement, though fences and new structures need one.

Want this handled start to finish?

Get a free quote →

Howard County permit search and official resources

Simplify Howard County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Howard County sooner?

Let Alliance prepare, file, and track your Howard County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Howard County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.