Linn County, Missouri Building Permit Guide

To get a building permit in Linn County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

In Linn County, building permits come from the cities that run a program, chiefly Brookfield and Marceline; septic systems on county land are permitted by the Missouri Department of Health and Senior Services.

Authority: Brookfield Code Enforcement (city permits)Septic: Missouri DHSSPhone: 660-258-3377
Brookfield permits
Code Enforcement, 660-258-3377
Marceline permits
City Hall, 660-376-3528
Septic on county land
Missouri DHSS
Flood insurance
County not in NFIP

Linn County has no county building, planning or zoning office and is not in the National Flood Insurance Program; on county land the approval the state lists is the septic permit from the Missouri Department of Health and Senior Services. Building permits come from the cities: Brookfield’s Code Enforcement Officer (116 West Brooks; 660-258-3377) and Marceline City Hall (660-376-3528), where a permit for work valued at $4,000 or more is $25 plus $5 per additional $1,000.

Linn County building department: who handles permitting

Linn County runs no building, planning, zoning or floodplain office: the state septic directory names DHSS as the permitting authority, and FEMA lists the county as not participating in the flood insurance program. The county seat is Linneus. For a parcel outside the cities, ask the County Commission at the courthouse in Linneus whether anything beyond the state septic permit applies.

Brookfield and Marceline publish building permit programs on their own sites. Populations below are Census Bureau Vintage 2025 estimates.

Short on time to read all of this?

Get a free quote →
Who issues building permits in Linn County
PlaceWho permits building work
Brookfield (4,083)City of Brookfield Code Enforcement Officer: plan review, permits and inspections for building, plumbing, mechanical and electrical work; 116 West Brooks, 660-258-3377, 8 a.m. to 5 p.m.
Marceline (2,112 in Linn County; 4 in Chariton County)City of Marceline, City Hall, 116 N. Main Street, 660-376-3528, Monday to Friday 8 a.m. to 5 p.m.; separate forms for new construction and general building permits
Meadville (413)The published sources do not say; ask City Hall
Bucklin (410)The published sources do not say; City Hall 660-695-3221
Laclede (300)The published sources do not say; ask City Hall
Linneus (277)The published sources do not say; ask City Hall
Browning (161 in Linn County; 55 in Sullivan County)The published sources do not say; ask City Hall
Purdin (138)The published sources do not say; ask City Hall
Unincorporated Linn CountyNo county building permit office; septic permits from Missouri DHSS

Building permit fees in Marceline

Marceline posts its building permit fees, set in Title V, Chapter 500 of the city code (updated December 18, 2018), on its building permits page:

Not sure this scope needs a permit?

Get a free quote →
Marceline building permit fees
Project value or permitFee
Building work under $250No fee
$250 to $1,000$15
$1,000 to $4,000$25
$4,000 and over$25 plus $5 per $1,000 over $4,000
Change of use or occupancy$25
Conditional use, special use, variance or zoning amendment$25 each
DemolitionNo fee

For example, a $100,000 addition in Marceline would cost $25 plus 96 x $5, or $505. Marceline requires permits for new buildings, additions, structural alterations, and garages, sheds and other accessory buildings over 120 sq ft. Brookfield prints no fee on its permit form; ask the Code Enforcement Officer.

How permits work in Brookfield

Brookfield’s Code Enforcement Officer enforces the city’s building, plumbing, mechanical, electrical and zoning codes. The city’s page lists the 2006 International Building, Residential, Mechanical and Plumbing Codes and the 2005 National Electrical Code as its adopted codes, and in December 2024 the city adopted the 2015 International Fire Code (Ordinance 24-15).

Rather talk it over?

Call 1-855-478-4290 →
1. Download the forms

Print the building permit form, and the right-of-way permit form for work in a street, from the city’s Zoning/Building Permit/Code page.

2. Describe the structure

The form asks for the zoning district, parcel ID, lot size, the structure’s width, length, height, type, use and foundation, and all four setbacks.

3. Return it

Deliver the completed form to the Code Enforcement Officer at 116 West Brooks, or scan and email it.

4. Post the placard

Display the weatherproof permit placard on the property.

5. Call for the three inspections

Footings, drain tile, foundation and basement walls before backfill; framing after fire stopping and the electrical, plumbing and mechanical rough-ins; and the final. Reinforced concrete is also inspected after the steel is placed and before the pour.

Septic and floodplain in Linn County

Septic systems: the Missouri Department of Health and Senior Services (DHSS) is the permitting authority for on-site wastewater systems in Linn County. Start by submitting the state’s OWTS Application Number Request Form for an application number, then file the construction permit with DHSS, 930 Wildwood Drive, Jefferson City (573-751-6095, ext. 5).

Flood insurance: FEMA’s Community Status Book lists Linn County, Laclede, Meadville and Purdin in its section of communities not in the National Flood Insurance Program. Brookfield, Browning, Linneus and Marceline participate, and SEMA lists floodplain administrators only for those four cities. Bucklin is not listed by FEMA.

Rather not deal with the Linn County building department?

Get a free quote →

Missouri building code

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Linn County permit FAQs

Does Linn County issue building permits?

No. Linn County has no county building, planning or zoning office; building permits come from the cities that run a program, such as Brookfield and Marceline. Ask the County Commission in Linneus about a rural parcel.

Who issues building permits in Brookfield?

The City of Brookfield’s Code Enforcement Officer at 116 West Brooks (660-258-3377), who reviews plans, issues permits and carries out at least three inspections on new buildings, additions and alterations.

How much is a building permit in Marceline?

Nothing under $250 of work, $15 up to $1,000, $25 up to $4,000, and $25 plus $5 per $1,000 above $4,000.

Who issues septic permits in Linn County?

The Missouri Department of Health and Senior Services directly (573-751-6095, ext. 5), after an application number request.

Can I buy flood insurance in rural Linn County?

FEMA lists Linn County among communities not in the National Flood Insurance Program; Brookfield, Browning, Linneus and Marceline participate.

Want this handled start to finish?

Get a free quote →

Linn County permit search and official resources

Simplify Linn County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Inspections are where schedules slip.

Get a free quote →

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Linn County sooner?

Let Alliance prepare, file, and track your Linn County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Linn County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.