Gladstone, Missouri Building Permit Guide

To get a building permit in Gladstone, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Gladstone’s Community Development Department at 7010 N. Holmes issues building, electrical, mechanical and plumbing permits for property inside city limits, on paper forms with plans sent digitally.

Authority: Gladstone Community DevelopmentCode: 2021 I-Codes, 2020 NECPhone: 816-423-4111
Authority
City Community Development7010 N. Holmes
House plan review
$50 flat feeReview in 3–5 days
Inspections
Usually within 2 hoursCall 816-423-4111
Codes
2021 International CodesSince Jan. 1, 2022

Building permits in Gladstone come from the City’s Community Development Department, not Clay County. Applications are made on the City’s forms with plans sent by email or on a flash drive, and fees are paid by mail or in person. The building permit fee follows the City’s valuation table ($2,299.75 for a $250,000 project), a new house adds a $50 plan review fee, and residential review typically takes 3 to 5 days.

What requires a building permit in Gladstone?

Gladstone’s amendments to the 2021 residential code keep only a short list of exemptions, and unlike the model code they do not exempt small sheds. The City’s permit brochure and code list these:

Permit needed

  • New houses, additions and basement finishes or remodels
  • Decks and porches, new or replacement
  • Sheds, detached garages and carports, new or replacement
  • Roof replacement or repair, and solar panels
  • Fences over 6 feet and retaining walls over 4 feet
  • Driveway approaches, fireplaces and wood stoves
  • Pools and spas over 2 feet deep
  • Electrical work, furnace and A/C replacement, water heaters, sewer and water lines, lawn irrigation and sump pumps

No building permit

  • Fences up to 6 feet (zoning rules still apply)
  • Retaining walls up to 4 feet that support no surcharge
  • Sidewalks and driveways outside the city or state right-of-way
  • Painting, papering, tiling, carpeting, cabinets and countertops
  • Swings and playground equipment

Separate City permits cover demolition and relocation, dumpsters, portable storage containers, excavation and grading, land disturbance, signs, public improvements and utility work in the right-of-way.

Gladstone building department: who handles permitting

The Building and Construction Division of Community Development handles new homes, additions, remodels, accessory buildings, decks, pools, roofing, solar and commercial construction; the Planning and Zoning Division reviews subdivisions and site plans alongside it.

Short on time to read all of this?

Get a free quote →
Gladstone permit contacts
DetailInformation
OfficeCommunity Development Department
Address7010 N. Holmes, Gladstone, MO 64118
Phone (permits and inspections)816-423-4111
PaymentsBy mail or in person; no online payment

Gladstone applications and licences

The City’s online application system is listed as unavailable, so use the PDF forms on the Permit Applications page: building, demolition and relocation, a combined electrical, mechanical and plumbing (and excavation) application, excavating and grading, land disturbance, construction and operational fire permits, signs, solar photovoltaic systems (with a checklist), sump pumps, public improvements, utility work and reinspection requests.

Who can apply: a homeowner who lives in the house, or a contractor with a Gladstone business licence and a workers’ compensation certificate. A buyer who has just purchased the home brings the closing papers.

Trade licences: electrical permits are issued only to holders of a Gladstone master electrician licence and business licence, and plumbing work needs a master plumber licence. Licences are granted after an approved examination or on an equivalent county or city licence accepted by the City’s board of examiners, and run from July 1 to June 30. A homeowner who lives in the dwelling may take out an electrical permit for work on it.

Gladstone permit fees

Building permit fees follow the City’s Permit Fee Schedule, a table of fees by project valuation that is also printed on the building permit application (revised September 9, 2020). Some of its values:

Gladstone building permit fees by valuation (selected rows)
ValuationFee
Up to $500$31
$2,000$91
$10,000$231
$25,000$493.50
$50,000$812.25
$100,000$1,249.75
$250,000$2,299.75
$376,000$3,181.75, then $7 for each additional $1,000 up to $500,000
Over $500,000$4,035.75 for the first $500,000 plus $6 per $1,000 up to $1,000,000; above that $7,035.75 plus $4 per $1,000

Not sure this scope needs a permit?

Get a free quote →

The printed $500,000 figure is $14 less than continuing $7 per $1,000 from the last table row would give, so the table does not settle fees for projects between $376,000 and $500,000.

Other Gladstone permit charges
ItemFee
Plan review, new house or addition$50 flat
Plan review, new commercial building or addition$200 per 5,000 sq ft or fraction
Plan review, commercial remodel, tenant finish or exterior work$150 per 5,000 sq ft or fraction
Reinspection$25 residential, $100 commercial
Water or sewer service line work$50 excavation fee added to the permit
Land disturbance (refundable deposit)$500 per residential lot; $50 per lot for subdivisions; $5,000 per commercial lot or tract

The building permit application also has lines for a park fund fee and a double fee for work started without a permit, with no amounts printed. The permit fee is due when the permit is issued, by check, cash or card in person, or by mail.

Electrical, plumbing and mechanical permits in Gladstone

Trade work goes on the City’s combined electrical, mechanical and plumbing application, which asks for the valuation of each trade’s work. Electrical permits are needed for new construction, service upgrades and new or replaced circuits and wiring; mechanical permits for new systems and furnace or A/C replacement; plumbing permits for new work, water heaters, waste and vent piping, water and sewer service lines, lawn irrigation (with a backflow test) and sump pumps. Work in the right-of-way needs an excavation permit with a surety bond posted by a City-licensed plumber.

Gladstone enforces the 2020 National Electrical Code and the 2021 plumbing, mechanical, fuel gas and energy conservation codes with local amendments. Gladstone Fire/EMS is a City department, and fire construction and operational permits are on the City’s application list.

Rather talk it over?

Call 1-855-478-4290 →

Application documents and review times

New house or addition

  • Completed building permit application and the $50 plan review fee
  • Site plan signed and sealed by an engineer
  • Full set of plans sent digitally, by email or flash drive
  • At issue: plans on a flash drive, two full-size sets (one is stamped and returned), the permit fee and a current business licence

Commercial

  • Application, plan review fee and a full digital plan set
  • New buildings and additions also need a code analysis sheet, colored elevations and rendering, photometric plan, landscaping plan with stormwater best practices, fire alarm and fire suppression plans and a materials board
  • At issue: four full-size signed and sealed sets (two are returned) plus a flash drive

Residential review typically takes 3 to 5 days. New commercial buildings, additions and exterior changes need City Council approval, which takes about 3 to 4 weeks including 2 weeks of review; staff recommend meeting before design starts and again when plans are 60 to 80% complete.

How to get a Gladstone building permit

1. Check setbacks

Additions and attached garages need 35 feet front and rear and 9 feet side setbacks, with no more than 30% lot coverage; easements cannot be built on.

2. Line up licences

Contractors need a Gladstone business licence; electricians and plumbers need City master licences.

3. Complete the forms

Fill in the building application and any electrical, mechanical and plumbing application from the Permit Applications page.

4. Submit plans

Send the digital plan set with the plan review fee and wait for staff comments.

5. Pay and pick up

Bring the full-size plan sets and pay the permit fee in person or by mail.

6. Call for inspections

Phone 816-423-4111 for each inspection through the final.

Rather not deal with the building department?

Get a free quote →

Gladstone inspections

Call 816-423-4111 to schedule. Inspections are usually made within 2 hours of the call, or can be booked for a set time. A new single-family house is typically inspected at the footings or piers, foundation, temporary electric, rebar grounding (Ufer), ground rough, electric and gas utility service, roofing in progress (before it is a quarter done), all-trades rough-in, driveway approach, City sidewalk, water and sewer service lines, and final.

Roofing permits get an in-progress and a final inspection. Homes and commercial buildings may have only one layer of roof covering, with an ice barrier running at least 24 inches inside the exterior wall line. A reinspection fee can be charged if the inspection card is not posted, approved plans are missing, the inspector cannot get in or the work departs from approved plans. A permit expires 180 days after it is issued unless the building official grants a written extension.

Local Gladstone rules

Floodplain: Gladstone takes part in the National Flood Insurance Program, with flood maps effective August 3, 2015, and its building code adopts the Clay County Flood Insurance Study maps. The building official decides whether work on an existing building in a flood hazard area is a substantial improvement.

Temporary containers: a dumpster permit lasts 30 days unless it is tied to a building permit, and a portable storage unit permit lasts 14 days, with no more than two units.

Pools: pools and spas must be at least 10 feet from side property lines (15 feet on a corner lot), 10 feet from the rear line, 35 feet from the front line and 20 feet from a neighbor’s house. They may never go in the front yard, a pool in a side yard must be at least 60 feet from the front line, and every pool sits inside a fence at least 4 feet high with a self-closing, latching gate.

Gladstone building codes

Since January 1, 2022 Gladstone has enforced the 2021 International Building, Residential, Existing Building, Energy Conservation, Fire, Fuel Gas, Mechanical, Plumbing, Property Maintenance and Swimming Pool and Spa codes and the 2020 National Electrical Code, each with local amendments in the City’s Building and Construction Ordinance.

Want this handled start to finish?

Get a free quote →

Missouri has no mandatory statewide building code for private construction: a county, fire protection district or municipality may adopt one (usually by reference under RSMo 67.280), and in parts of the state none has. Building codes in Missouri

Gladstone building permit FAQ

Who issues building permits in Gladstone?

The City’s Community Development Department at 7010 N. Holmes (816-423-4111), for property inside Gladstone city limits.

How much is a building permit?

It depends on valuation: $31 up to $500, $1,249.75 at $100,000 and $2,299.75 at $250,000. A new house or addition adds a $50 plan review fee.

Do I need a permit for a shed, fence or roof?

Sheds and roof replacements or repairs need permits. Fences need one only above 6 feet.

How long does plan review take?

Typically 3 to 5 days for residential plans. New commercial buildings take about 3 to 4 weeks because they also need City Council approval.

Can a homeowner pull a permit?

Yes, if they own and live in the house; otherwise a contractor licensed with the City applies.

Can I apply or pay online?

No. Online applications are listed as unavailable and payments are taken by mail or in person.

Gladstone permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Simplify Gladstone permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Missouri. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Gladstone sooner?

Let Alliance prepare, file, and track your Gladstone permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Gladstone permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.