To get a building permit in Scott County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

For property outside Scottsburg and Austin, Scott County’s Planning Department in the county building at 1 E. McClain Avenue, Scottsburg, handles building permits and zoning, while both cities run their own building offices.

Authority: Scott County Planning DepartmentBoards: Advisory Plan Commission and BZAPhone: 812-752-8445 ext. 1
Authority
County Planning Department1 E. McClain Ave., Suite G-40
Septic permit
$100 new systemScott County Health Department
Boards meet
Second WednesdayBZA 6:00 p.m.; plan commission 6:30
Hours
Mon–Fri 8:30–4:30812-752-8445 ext. 1

In unincorporated Scott County, building permits and zoning questions go to the Scott County Planning Department, Suite G-40 at 1 E. McClain Avenue, Scottsburg (812-752-8445, ext. 1), which staffs the Scott County Advisory Plan Commission and the Board of Zoning Appeals. The county’s own answer to “Where do I obtain a building permit?” is to call this office. Scottsburg and Austin issue their own permits, and septic permits ($100 for a new system) come from the Scott County Health Department.

What requires a building permit in Scott County?

Scott County does not post a permit list, zoning ordinance or building fee schedule on its website. Its frequently asked questions send both building permit and zoning questions to the Planning Commission office, so the first step for any new house, addition, garage or commercial building outside the two cities is a call to the Planning Department to confirm what that project needs.

County approvals to plan for

  • A building permit and zoning review from the Planning Department
  • Rezoning, variance or special approval from the Advisory Plan Commission or the BZA where the use or setbacks do not fit the zoning
  • A septic permit, or a site inspection and plan commission letter, from the Health Department
  • Culvert and ditch work along county roads through the Highway Department

State approvals that may apply

  • A Construction Design Release from IDHS for Class 1 buildings used by the public or by employees
  • Floodplain rules on mapped flood areas, administered locally
  • A state-licensed plumber for plumbing work

Rezoning activity in 2026 shows how land-use changes work here: in March 2026 the Advisory Plan Commission heard a petition to rezone seven parcels in Lexington from agricultural to single-family residential and sent a favorable recommendation to the Board of Commissioners, who make the final decision. In October 2026 the Commissioners approved another Lexington rezoning, of 888 N. State Road 3 from agricultural to general business, after both the plan commission and the BZA had acted on it; the petitioner told the board he had already spoken with the Health Department about septic permits.

What Scott County decides and what the state holds

The county decides zoning, rezonings, variances and local permit requirements through its plan commission, BZA and commissioners, and it collects building permit fees: on October 21, 2026 the Commissioners adopted Ordinance 2026-9, creating a separate fund for building permit fees, rezoning application fees and other fees collected by the plan commission or building commission, which the minutes say state law will require from 2027. The plan commission’s September 9, 2026 agenda also carried revised wording for the rule on splitting parcels and a rewritten easement ordinance for the Commissioners, so ask the office which version applies before dividing land. The building rules themselves are Indiana’s, and Class 1 structures need the state design release before construction, whichever local office issues the building permit.

Short on time to read all of this?

Get a free quote →

Scott County building department: who handles permitting

The Planning Department staffs the Scott County Advisory Plan Commission and the Board of Zoning Appeals under Area Plan Director Stacey Turner; the county has both a plan commission and a building commission, whose fees Ordinance 2026-9 places in one fund. The two incorporated cities each have their own building office.

Who issues building permits in Scott County
PlacePermit office
Unincorporated Scott County (including Lexington and other unincorporated communities)Scott County Planning Department, 1 E. McClain Avenue, Suite G-40, Scottsburg; 812-752-8445 ext. 1
City of ScottsburgCity Building, Planning & Zoning Commission, which takes building permit applications and plan commission and BZA petitions for the city
City of AustinCity Building Commission Office: residential, commercial and meter permits, building and fire protection inspections and contractor licenses; 812-794-2877

The county office is open Monday to Friday, 8:30 a.m. to 4:30 p.m.; fax 812-752-7512. To check whether an address is inside a city, use the county GIS map, which the Surveyor’s office (Suite G-42, same building and phone) helps maintain.

Scott County permit types

The county posts no planning or building application forms online. That is changing: on October 7, 2026 the Commissioners approved an amended contract with iWorQ adding an online portal with permit management, online payment and web forms, so that owners and contractors can get their permits online once it is running. What the published county pages show today is the set of offices a typical project passes through.

Residential permits

  • New houses: the building permit through the Planning Department, a septic permit from the Health Department after a site evaluation and soil analysis, and any culvert or ditch work at the road through the Highway Department.
  • Additions and accessory buildings: handled through the same Planning Department office; setback or use problems go to the BZA or the plan commission.
  • Septic repairs: the Health Department issues full or partial system permits and inspects the work; it can also provide existing system diagrams where it has them.

Commercial permits

Commercial and other Class 1 buildings need the IDHS Construction Design Release before construction as well as the local permit. New businesses in a district that does not allow the use go through a rezoning, or a BZA approval, first.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning hearings. Under the 2027 schedule the BZA meets at 6:00 p.m. and the Advisory Plan Commission at 6:30 p.m. on the second Wednesday of each month in the County Hall building, formerly Scottsburg City Hall. Applications are due about three weeks ahead, at 3 p.m.; for example, December 15 at noon for January 13, 2027, January 20 for February 10, and February 17 for March 10.
  • Septic. The Environmental Health Specialist evaluates the site and a soil scientist analyzes the soil for each new system; the department issues permits and inspects installations.
  • Roads and drains. Culvert and ditch requests go to the Highway Department, 1101 S. Main Street (812-752-8470), through its online request portal; regulated drains are under the Drainage Board.
  • Floodplain. Unincorporated Scott County is a participating National Flood Insurance Program community; its posted pages do not set out the county’s floodplain rules, so raise any mapped flood area on the first call to the Planning Department.

Scott County permit costs and fees

The county has not posted a building or zoning permit fee schedule on its website, so the amount comes from the Planning Department (812-752-8445, ext. 1). A new fee schedule is coming: on October 7, 2026 the Commissioners approved an updated Planning and Building Commission fee schedule that the Advisory Plan Commission had approved, to begin on January 1, 2027 after publication, and starting in 2027 building permit and rezoning fees go into their own fund under Ordinance 2026-9, adopted October 21, 2026. Ask the Planning Department for the new amounts; the Commissioners’ minutes say the schedule is to be published in the Crothersville Times for two consecutive weeks before the end of 2026. The Health Department publishes its fees:

Scott County Health Department sanitation fees
ItemFee
New or full septic system permit$100
Partial septic permit$40
Site inspection / plan commission letter$40
Septic installer annual permit$50 per installer

The site inspection and plan commission letter line shows that the Health Department’s sign-off is part of the county planning process. The two cities publish their own permit fees, which apply only inside their limits:

Rather talk it over?

Call 1-855-478-4290 →
Building permit fees inside Scottsburg and Austin (city documents)
ItemFee
Scottsburg: new one- or two-family house (electrical included)$175 + $0.10 per sq ft
Scottsburg: remodel; accessory building, deck or detached garage$100 + $0.08 per sq ft; $50 + $0.08 per sq ft
Scottsburg: new-house HVAC; plumbing$100; $50 + $5 per additional fixture
Scottsburg: fence; pool; driveway access to a public road$50; $100; $50
Scottsburg: new commercial, industrial or multi-family building$250 + $0.15 per sq ft
Scottsburg: work started without a permitTwice the fee
Austin: building permit and improvement permit$25 each, plus $25 per inspection and a square-foot charge
Austin: commercial, industrial or multi-family$25 + $0.08 per sq ft up to 19,999 sq ft, falling to $0.05 above 60,000
Austin: re-inspection; permit after work began$50; twice the base fee

Scottsburg’s schedule was adopted April 22, 2024 and took effect May 1, 2024. Worked example: a 2,000-square-foot new house in Scottsburg pays $175 + $200 = $375 for the building permit, plus $100 for the new-structure HVAC permit, or $475 before plumbing fixtures. Class 1 projects also pay the state design release fee to IDHS: a $75 filing fee plus a processing fee, generally $0.050 per gross square foot of floor area, with a minimum processing fee of $75.

Trade permits and who may pull them

The county’s pages describe no county electrical, plumbing or mechanical license or contractor registration, and no separate trade permit forms are posted. Plumbing must be done by a plumber licensed by the state.

  • Septic installers: pay the Health Department’s $50 annual installer permit before installing systems in the county.
  • Austin: the city’s Building Commission Office issues residential, commercial and meter permits, reviews contractor license applications and renewals, inspects fire protection systems, and helps the Clerk-Treasurer assess permit fees; its building and improvement permit application can be filed online.
  • Scottsburg: the city’s Building, Planning & Zoning Commission takes building permit applications and posts its own review and inspection schedules.

Rather not deal with the Scott County building department?

Get a free quote →

How to apply for a Scott County building permit

1. Confirm the jurisdiction

Check the county GIS map to see whether the parcel is in Scottsburg, Austin or the unincorporated county.

2. Call the Planning Department

Ask which permits and forms the project needs and whether the zoning allows it (812-752-8445, ext. 1).

3. Start the septic process

Contact the Health Department, 1296 N. Gardner Street (812-752-8455), for the site evaluation and soil analysis.

4. Request zoning relief if needed

File a rezoning or BZA application by the deadline on the yearly schedule.

5. File the building permit application

At Suite G-40, 1 E. McClain Avenue, with plans and the fee the office sets.

6. Get the state release for Class 1 work

File with IDHS before construction starts.

Review, corrections and what causes delay

A project that needs a rezoning waits for the monthly Advisory Plan Commission hearing and then the Commissioners’ vote; a variance needs a BZA hearing. Septic approval depends on the site evaluation and soil report, so order the soil analysis early. Confirm the meeting time with the office: the plan commission web page lists 7 p.m., while the 2027 schedule and the March 2026 minutes give 6:30 p.m.

Inspections and certificates in Scott County

The county pages do not publish a list of building inspection stages for county permits. The Health Department inspects new and repaired septic systems, writes septic inspection letters and investigates failing systems, and homeowners can ask it for a diagram of an existing system if one is on file.

The Health Department’s environmental services also include soil testing, water testing, inspections of existing systems and failures, and complaint investigations; failed onsite systems can lead to violation letters and, if needed, court action.

In the cities the stages are published. Scottsburg’s inspection report runs from the temporary and permanent electric service through footer, under-slab, plumbing rough-in, framing and electrical and mechanical rough-ins to final electric, plumbing, mechanical and energy code inspections and the final certificate of occupancy or compliance; since January 1, 2026 Scottsburg inspections are booked by email, with the site address and permit number in the subject line. Austin’s permit form lists footer or foundation, electrical or plumbing, and final inspections, and its permits expire one year after issue.

Indiana building code in Scott County

FEMA’s Community Status Book lists unincorporated Scott County (community 180474) as participating in the National Flood Insurance Program, with a current map dated June 9, 2014; that listing covers only the unincorporated county.

Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana

Want this handled start to finish?

Get a free quote →

Scott County building permit FAQs

Where do I get a building permit in Scott County?

Outside Scottsburg and Austin, from the Scott County Planning Department, 1 E. McClain Avenue, Suite G-40 (812-752-8445, ext. 1).

Does the county issue permits in Scottsburg or Austin?

No. Scottsburg’s Building, Planning & Zoning Commission and Austin’s City Building Commission Office issue permits inside each city.

How much is a septic permit?

$100 for a new or full system and $40 for a partial permit, from the Scott County Health Department.

How much is a county building permit?

The county has not posted its fee schedule online; the Planning Department gives the amount, and a new schedule begins January 1, 2027.

When do the plan commission and BZA meet?

On the second Wednesday of each month: the BZA at 6:00 p.m. and the Advisory Plan Commission at 6:30 p.m., in the County Hall building.

Can I apply for a county permit online?

Not yet on the county website; in October 2026 the Commissioners approved an iWorQ portal so owners and contractors can apply and pay for permits online once it is set up.

Where is my septic tank?

Call the Health Department’s environmental staff; they can check for a drawing of your system on file.

Scott County permit search and official resources

Permit and zoning records for the unincorporated county are held by the Planning Department; ask the office with the address or parcel number. Advisory Plan Commission and BZA agendas, minutes and yearly schedules are posted in the county’s Agenda Center.

Inspections are where schedules slip.

Get a free quote →

Simplify Scott County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Scott County sooner?

Let Alliance prepare, file, and track your Scott County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Scott County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.